Professional Documents
Culture Documents
JSA-Electrical work 3060 Bldng.
JSA-Electrical work 3060 Bldng.
JSA-Electrical work 3060 Bldng.
Obtain a Hot Work Permit from the Area Supervisor before starting the job and
closing the Work Permit once task is done. See SA-G.I. 2.100.
Unauthorized work Get the permit validated for the specific day.
Invalid permit Conduct Tool-box talk and make sure to communicate all the contents of this JSA
(Job safety Analysis) to all workers involved in the activities.
1. Work start-up and obtaining Failures of communication The work permit receiver shall conduct the pre-job safety meeting and to be
Work Permit about the identified hazards explained about the identified hazards and preventive measure from the work
by the work permit issuer and permit.
receiver.
Responsible person must conduct inspection, monitor the work activities, and have
Improper knowledge of work to ensure safety standards and procedures are strictly adhered to according to SA-
is lead to incident/accident. CSM-I-11 Hand Tools and Power Tools under Section 11.5 Portable Power Tools-
General Requirements, SA-G.I. No.: 6.012 Isolation, Lockout and Use of Hold Tags.
and SA-CSM-I 5.4 Electrical Lockout and Tagout (Lock, Tag, Clear, Try)
2. Clearing of Access and Unsecured debris Clear pathways from obstruction.
Egress
Unattended tools/materials
Implement good housekeeping.
Tripping/Slipping
Only Authorized/certified electrical technicians shall directly engaged with
3. Assignment/selection of Lack of competence energized facilities.
workers Full supervision.
Training for electrical technicians.
Installation of electrical equipment and circuits shall conform to NFPA 70.
Personnel shall not wear rings, wristwatches, jewelry or other similar metallic
objects.
Ground-Fault Circuit Interrupter installed (GFCI).
4. Working on energized panels Contact with energized parts Protective equipment.
and/or services
Isolation Confirmation Certificate (ICC) and PTW.
LOTO procedure implementation.
LOTO Training.
Power test before operation
Improper isolation
5. Isolation of Live Circuit Unfamiliar of lockout/tagout Refer and comply with G.I. No.: 6.012 Isolation, Lockout and Use of Hold Tags.
Breaker system Use SA approved lockout/tag out items.
6. Use of Electrical Tools Defective power tools / Battery-driven hand tools should be used as much as possible to minimize the
equipment need for 220V tools.
Ensure portable electrical tools are double insulated
Untagged power tools
Do not use handheld breakers within 500 mm from underground cables.
Improper routing of electrical Ensure all portable electrical equipment has correct safety guarding and
cable. protective devices are in place.
Provision of socket outlets for distribution cables are located as close to the
Slip, Trip and Fall
working point as possible to prevent the need for long trailing wires.
Cables should be hanged up at workstations whenever practicable to reduce trip
hazards and damage to cables.
Use PVC insulated hooks/stands for cable routing.
Provide properly constructed and insulated electrode holders (IP67, male female
socket).
Ensure cables are sufficiently insulated, covered, or armored, have protection
from chemical damage and where necessary additional protection,e.g. guarding,
to prevent mechanical damage.
Ensure all welding machines are installed with voltage reducing devices.
Portable electric tools and extension cables should be inspected and tagged every
three months by a competent person in compliance with color coding
requirements.
Faulty electrical equipment or equipment without a tag must be taken out of
service and labeled with an ‘out of service’ tag and should be reported to a
supervisor.
Engagement of trained and competent person for power tool operation.
Job specific PPE’s should be used for the activity.
Authorization card to be provided for operator.
Ensure rubber mat is placed at all DB’s
7. Cable, EMT and Use approved leather or rubber gloves
instrumentation tubes Store and secure properly loose sharp edges items
pulling and installation Inspection of issued tools prior to use.
pulling activity Any defective tools must be disposed of from the site.
One person designated to control the pull to ensure all cable pullers are working as
a team
Sharp edges Damaged/Faulty Suitably maintained drum roller frames, jacks, rollers and operatives controlled
Tools to ensure hands are clear when cable is moving.
Cable kicking during the Awareness of maximum permitted cable pulling tensions and minimum bending
radii.
pulling activity Inspection of a cable prior to pulling for damage.
Cable drums stored on level stable surfaces.
8. Termination of cables from Contact with energized parts Installation of electrical equipment and circuits shall conform to NFPA 70.
power source Personnel shall not wear rings, wristwatches, jewelry or other similar metallic
objects.
Ground-Fault Circuit Interrupter installed (GFCI).
Protective equipment.
Isolation Confirmation Certificate (ICC) and PTW.
LOTO procedure implementation.
LOTO Training.
Power test before operation
Installation / fixing of disconnect Electrical personnel must undergo the energy isolation & permit to work
switches, DDC panel orientation and LOTO training.
programming Adhere with current applicable project procedure (LOTO, Commissioning, etc.)
and associated PTW system.
9. Follow the electrical testing/ programming project method of statement and risk
assessment.
Only trained and experienced technician / electrician must carry out the electrical
test/ programming.
Electrical Shock Electrical test/ programming activity must be supervised closely by the designated
• Fire electrical engineer/ supervisor.
Applicable PTW to be completed and discussed with the workforce in line with
• Personnel injury the toolbox talks before the task begins.
A readily useable CO2 portable fire extinguisher (20 kg.) capacity shall be
deployed in the area.
Signs and barricades shall be erected in the test area to avoid unauthorized entry.
Comply as per Section Electrical Hand Tools Safety & Hot Work. Ensure that the
tools to be use is properly inspected and tagged prior to use. Tools with damage
or frayed wiring must not be allowed to use and must be removed from the
worksite. Repair can only be done by an authorized person with expertise to
electrical works.
10. Loading, Transporting& Off- (Moving parts) Struck by
loading Lashings to be applied to load. (Sufficient lashing)
/Trapped or in between
All operatives to be versed in manual handling regulation.
All operators to be trained in use of equipment
Maneuvering Boom truck,
Banks man shall control the heavy vehicles and equipment with reflecting jacket.
trailer etc. Area to be barricaded & warning display sign
Power interruption
Termination
/installation failure
14. Cable pulling and EMT Cable kicking during the pulling
installation
activity Working on Stepladder One person designated to control the pull to ensure all cable pullers are working as a
team
Suitably maintained drum roller frames, jacks, rollers and operatives controlled to
ensure hands are clear when cable is moving.
Awareness of maximum permitted cable pulling tensions and minimum bending radii.
Inspection of a cable prior to pulling for damage.
Cable drums stored on level stable surfaces.
Wear proper gloves.
Personnel shall not stand on a step ladders top, platform.
Make sure somebody’s holding the ladder while a worker is working on it.
Clear pathways from obstruction.
Unsecured tools and materials
Implement good housekeeping.
Instructions
1. Use as many lines as needed to list the critical steps. Be specific.
2. There may be more than one hazard per step. List each hazard.
3. Identify the proper control for addressing each hazard. The preferred priorities are engineering, administrative (procedures) and then PPE.
4. Identify any recommended actions required, e.g., develop a new procedure or perform an industrial hygiene assessment. Assign a responsible party for
any required actions.
5. List each type of PPE needed for the task. Be specific.
6. Identify key steps as “STOP WORK TRIGGERS” (in the “Controls” column) if there are any conditions, job changes or distractions that will
prompt personnel to stop all work activities associated with the job until further assessment is conducted or additional controls are implemented.
7. Criteria for Stopping the work if any body see the condition such as if Fire Alarm rings in the building, changes in bad weather condition, if there is
any change in SOW or Plan, in emergency situation, Equipment improperly use, Lack of knowledge, understanding or information, near miss
incident or unsafe condition at site work.
JSA Prepared By: Altaf Hassain Signature:
Safety Officer-AlMoallam
JSA Reviewed By: Tawfeeq Alam Signature:
Project Engineer-AlMoallam
JSA Approved By: Sara A Mousa Signature:
Project Engineer-Aramco