Meeting No. 17
Distribution
Wanderley HENRIQUE DA COSTA, Gina DILU MURTAR PILICA BILALE, Dassirota
JAMBO, Nyasha MHUTE, Nicole RIBEIRO, Zaido ABIBO Benilde SAETE,Ivone CIPRIANO
pmcamillo.sanlo@gmail.com, donaminawe.sanlo@gmail.com,
thstbalama.sanlo@gmail.com, thst.sanlo@gmail.com, candeadoelidio@gmail.com,
marcelinopedro.sanlo@gmail.com, encnaminawe.sanlo@gmail.com,
encbalama.sanlo@gmail.com, qscadeado.sanlo@gmail.com,
aliaidar.sanlo@gmail.com ,qcarsenio.sanlo@gmail.com,
dogildo.sanlo@gmail.com , delfos.sanlo@gmail.com
Delfa Santos
Site Engineer
Gildo Uane
Site Engineer
Ali Aidar
Site Administrator
Juma Momade
HSSE Rep
Vanessa Monteiro
Quality Inspector
2. Meeting Agenda
1.Pending points
2.Technical aspects
3.Work Progress
5.HR Points
6.Final Notes
3. Minutes of Meeting
Item No Agenda Discussed Meeting Minutes Proposed Action Action by/ Due
Date
1
Pending Points 1.1 Pending Points by UNOPS
a) Difference in the beam The Site Engineer to Delfa Santos/ ASAP
dimensions on the draws: in send the design review
some draws the beams are
300x300 and in others the
dimensions are 300x400. The
Site engineer gave the
contractor a site Instruction
according to the new drawings
and will send the revised
drawings this week after the
signature of the PM.
2
Technical Aspects 2.1 Drawings issues/questions The Site Engineer to Delfa Santos/ ASAP
a) The contractor advised about send the issues to the
the lack of details about the design team
elevated water tank position;
3
Work Progress/ a) Construction Progress
- Main Building excavation - 85%
- Backfilling on the foundation
and soil compact - 15%
- Compaction tests - 10%
- Soil Treatment - 10%
- Rock demolition - 90%
- Preparation of the Armor for
the foundations- 40%
- Cleaning Concrete - 8%
- Execution of bays for the
concrete area - 100%
- Incinerator excavation - 10%
b) HSSE Progress
- Wc For the Workers - 100%
- Wardrobe - 100%
- Improvement of the pedestrian
Safety route
c) Quality Progress
- Execution of the Inspection of
materials/works:
- Iron Bending Machine
(Approved)
- Excavation (Approved)
- Compaction tests (Approved)
- Plastic Sheet (Approved)
- Crushed Stone (Approved)
- Anti Termite (Approved)
5.
HR Points 5.1 Contracts, Payslips, Code of
conduct, etc
- There are 8 Temporary helpers
on site, working on removal of
the rock.
6
Final Notes
- The Contractor has to print the
biweekly plan and put on the
board;
- Next meeting scheduled to
Monday, 13.02.2023, at 09:30
am