NAME: CHRISTOPHER CHEE ZHUO HONG ELEMENT : W.B.L.F.

F
PROJECT: CONSTRUCTION AND COMPLETION OF SCHOOL FOR MENTALLY RETARDED CHILDREN AT
JALAN DATO KERAMAT,10450 GEORGETOWN PULAU PINANG
DRAWING NO:

Taking-off List:

1. Site clearance ha.


2. Earthwork cutting and filling 𝑚
3. Excavation of top soil 𝑚
4. Deposition of top soil 𝑚
5. Pit Excavation to red. col. base max. depth n.e. 1 m Type 2 Pile Cap 𝑚
6. Pit Excavation to red. col. base max. depth n.e. 1 m Type 3 Pile Cap 𝑚
7. Pit Excavation to red. col. base max. depth n.e. 1 m Type 1 Pile Cap 𝑚
8. Filling to Excation with material arising from excavation 𝑚
9. E.o. excavation in rock 𝑚
10. Allow for keeping the surface of the site &excavation free from surface water ITEM
11. Concrete Work (Foundation Pile Cap) 𝑚
12. Reinforcement (Foundation Pile Cap) kg
13. Formwork (Foundation Pile Cap) 𝑚
14. Concrete Work (Column Stump) 𝑚
15. Reinforcement (Column Stump) kg
16. Formwork (Column Stump) 𝑚
AMJ48103 INTEGRATED DESIGN PROJECT II
DRAWING NO: ELEMENT SLIP NO: 1
2018/05/28/FLY/SUNGAIARA/KEBAJIKANKANAK/S/FP W.B.L.F.F
PROJECT:CONSTRUCTION AND COMPLETION OF SCHOOL FOR MENTALLY RETARDED
CHILDREN AT JALAN DATO KERAMAT,10450 GEORGETOWN PULAU PINANG

3
DESCRIPTION: Work Below Lowest Floor Finish UNIT:m²,m
QTY:
W.B.L.F.F
Site Clearance
Area of Site
105 m
54 m
2
5670 m

Cutting down trees & clearing sire of


undergrowth, bushes, scrub and hedges
& grubbing up their roots & filling voids
left by removal of roots with selected
105.00 material arising from excavation.
54.00 (in 0.567 ha)
2
5670.00 m

Earthwork Cutting and Filling


Filling over area to required formation
level including forming and grading side
of slopes as shown on Engineer's drawings
and specifications
3
(in 6394m )
3
6394.00 m

Excavation of Top Soil


105 m
54 m
2
5670 m

Excat. Top soil for preservation. Avg.


105.00 100 mm dp.
54.00
2
5670.00 m
AMJ48103 INTEGRATED DESIGN PROJECT II
DRAWING NO: ELEMENT SLIP NO: 2
2018/05/28/FLY/SUNGAIARA/KEBAJIKANKANAK/S/FP W.B.L.F.F
PROJECT:CONSTRUCTION AND COMPLETION OF SCHOOL FOR MENTALLY RETARDED
CHILDREN AT JALAN DATO KERAMAT,10450 GEORGETOWN PULAU PINANG

DESCRIPTION: Work Below Lowest Floor Finish UNIT:m²,m³


QTY:
105.00 Dep. Preserved top soil in temp. spoil
54.00 heaps avg. 10m dist.
0.10
3
567.00 m

Pit Excavation
depth
(+)Blinding 0.05 m
(+)Pile Cap 1.00 m
(+)Stump 1.00 m
(-)Top Soil 0.10 m
1.95 m
138 /
1.05 Excat. pit to rec. col. Base max. depth n.e.
0.50 1.00 m (Type 2 Pile Cap)
1.00
3
72.45 m

138 / ditto.
/ 1.05
0.50
0.95
3
68.83 m

7/ Excat. pit to rec. col. Base max. depth n.e.


1.20 1.00 m (Type 3 Pile Cap)
1.30
1.00
3
10.92 m

7/ ditto.
1.20
1.30
0.95
3
10.37 m
AMJ48103 INTEGRATED DESIGN PROJECT II
DRAWING NO: ELEMENT SLIP NO: 3
2018/05/28/FLY/SUNGAIARA/KEBAJIKANKANAK/S/FP W.B.L.F.F
PROJECT:CONSTRUCTION AND COMPLETION OF SCHOOL FOR MENTALLY RETARDED
CHILDREN AT JALAN DATO KERAMAT,10450 GEORGETOWN PULAU PINANG

DESCRIPTION: Work Below Lowest Floor Finish UNIT:m²,m³


QTY:
depth
(+)Blinding 0.05 m
(+)Pile Cap 0.60 m
(+)Stump 1.00 m
(-)Top Soil 0.10 m
1.55 m
35 /
0.60 Excat. pit to rec. col. Base max. depth n.e.
0.60 1.00 m (Type 1 Pile Cap)
1.00
3
12.60 m

35 / ditto.
0.60
0.60
0.55
3
6.93 m
&
Filling.to excavation with material arising
from excavation

10 / 100 / E.o. pit excavation for ecavating in rock


182.10 (10% of total pit exacation)
3
18.21 m

ITEM Allow for keeping the surface of the site &


excavation free from surface water
AMJ48103 INTEGRATED DESIGN PROJECT II
DRAWING NO: ELEMENT SLIP NO: 4
2018/05/28/FLY/SUNGAIARA/KEBAJIKANKANAK/S/F/1-3 W.B.L.F.F
PROJECT:CONSTRUCTION AND COMPLETION OF SCHOOL FOR MENTALLY RETARDED
CHILDREN AT JALAN DATO KERAMAT,10450 GEORGETOWN PULAU PINANG

3
DESCRIPTION: Work Below Lowest Floor Finish UNIT:m²,m
QTY:
Concrete Work (P1)

35 / 0.60 Concrete grade 20 blinding n.e. 100mm


0.60 thickness laid on earth
0.05
3
0.63 m

Mass concrete grade 40


35 / 0.60
0.60
0.60
3
7.56 m

Reinforcement (P1)

470 mm

540 mm

X - Direction - T 12
Length 600 mm
(-)Cover (2) 60 mm
540 mm
(+)Bend (2) 1000 mm
(-)Cover (2) 60 mm
1480 mm
AMJ48103 INTEGRATED DESIGN PROJECT II
DRAWING NO: ELEMENT SLIP NO: 5
2018/05/28/FLY/SUNGAIARA/KEBAJIKANKANAK/S/F/1-3 W.B.L.F.F
PROJECT:CONSTRUCTION AND COMPLETION OF SCHOOL FOR MENTALLY RETARDED
CHILDREN AT JALAN DATO KERAMAT,10450 GEORGETOWN PULAU PINANG

DESCRIPTION: Work Below Lowest Floor Finish UNIT:m²,m³


QTY:
No. of Bar = (Y Length-2*Cover/Spacing)+1
35 / 6/ = 6
1.48
331.52 m T 12

470 mm

540 mm

Y - Direction - T 12
Length 600 mm
(-)Cover (2) 60 mm
540 mm
(+)Bend (2) 1000 mm
(-)Cover (2) 60 mm
1480 mm

No. of Bar = (Y Length-2*Cover/Spacing)+1


35 / 6/ = 6
1.48
331.52 m T 12

Stirrup 3R 8
X- Length = 600 mm
Y- Length = 600 mm

X- Length (2) 1200 mm


(-)Cover (2) 60 mm
1140 mm
Y- Length 2) 1200 mm
(-)Cover (2) 60 mm
(+)Hook 24d 192 mm
3/ 2472 mm
2.47
7.42 m R8
AMJ48103 INTEGRATED DESIGN PROJECT II
DRAWING NO: ELEMENT SLIP NO: 6
2018/05/28/FLY/SUNGAIARA/KEBAJIKANKANAK/S/F/1-3 W.B.L.F.F
PROJECT:CONSTRUCTION AND COMPLETION OF SCHOOL FOR MENTALLY RETARDED
CHILDREN AT JALAN DATO KERAMAT,10450 GEORGETOWN PULAU PINANG

DESCRIPTION: Work Below Lowest Floor Finish UNIT:m²,m³


2
QTY: 50.4 m
Formwork (P1)
Sawn timber of 38mm thickness for
35 ∕ 2 ∕ foundation
0.60
0.60
2
25.2 m

35 ∕ 2 ∕
0.60
0.60
2
25.2 m
AMJ48103 INTEGRATED DESIGN PROJECT II
DRAWING NO: ELEMENT SLIP NO: 7
2018/05/28/FLY/SUNGAIARA/KEBAJIKANKANAK/S/F/1-3 W.B.L.F.F
PROJECT:CONSTRUCTION AND COMPLETION OF SCHOOL FOR MENTALLY RETARDED
CHILDREN AT JALAN DATO KERAMAT,10450 GEORGETOWN PULAU PINANG

3
DESCRIPTION: Work Below Lowest Floor Finish UNIT:m²,m
QTY:
Concrete Work (P2)

138 / 1.05 Concrete grade 20 blinding n.e. 100mm


0.50 thickness laid on earth
0.05
3
3.62 m

Mass concrete grade 40


138 / 1.05
0.50
1.00
3
72.45 m

Reinforcement (P2)

870 mm

440 mm

X - Direction - T 12
Length 500 mm
(-)Cover (2) 60 mm
440 mm
(+)Bend (2) 1800 mm
(-)Cover (2) 60 mm
2180 mm
AMJ48103 INTEGRATED DESIGN PROJECT II
DRAWING NO: ELEMENT SLIP NO: 8
2018/05/28/FLY/SUNGAIARA/KEBAJIKANKANAK/S/F/1-3 W.B.L.F.F
PROJECT:CONSTRUCTION AND COMPLETION OF SCHOOL FOR MENTALLY RETARDED
CHILDREN AT JALAN DATO KERAMAT,10450 GEORGETOWN PULAU PINANG

DESCRIPTION: Work Below Lowest Floor Finish UNIT:m²,m³


QTY:
No. of Bar = (Y Length-2*Cover/Spacing)+1
138 / 11 / = 11
2.18
3279.16 m T 12

870 mm

990 mm

Y - Direction - T 12
Length 1050 mm
(-)Cover (2) 60 mm
990 mm
(+)Bend (2) 1800 mm
(-)Cover (2) 60 mm
2730 mm

No. of Bar = (X Length-2*Cover/Spacing)+1


138 / 5/ = 5
2.73
2034.40 m T 12

Stirrup 3R 8
X- Length = 500 mm
Y- Length = 1050 mm

X- Length (2) 1000 mm


(-)Cover (2) 60 mm
940 mm
Y- Length 2) 2100 mm
(-)Cover (2) 60 mm
(+)Hook 24d 192 mm
3/ 3172 mm
3.17
9.52 m R8
AMJ48103 INTEGRATED DESIGN PROJECT II
DRAWING NO: ELEMENT SLIP NO: 9
2018/05/28/FLY/SUNGAIARA/KEBAJIKANKANAK/S/F/1-3 W.B.L.F.F
PROJECT:CONSTRUCTION AND COMPLETION OF SCHOOL FOR MENTALLY RETARDED
CHILDREN AT JALAN DATO KERAMAT,10450 GEORGETOWN PULAU PINANG

DESCRIPTION: Work Below Lowest Floor Finish UNIT:m²,m³


2
QTY: 427.8 m
Formwork (P2)
Sawn timber of 38mm thickness for
138 ∕ 2 ∕ foundation
1.00
0.50
2
138 m

138 ∕ 2 ∕
1.00
1.05
2
289.8 m
AMJ48103 INTEGRATED DESIGN PROJECT II
DRAWING NO: ELEMENT SLIP NO: 10
2018/05/28/FLY/SUNGAIARA/KEBAJIKANKANAK/S/F/1-3 W.B.L.F.F
PROJECT:CONSTRUCTION AND COMPLETION OF SCHOOL FOR MENTALLY RETARDED
CHILDREN AT JALAN DATO KERAMAT,10450 GEORGETOWN PULAU PINANG

3
DESCRIPTION: Work Below Lowest Floor Finish UNIT:m²,m
QTY:
Concrete Work (P3)

7/ 1.20 Concrete grade 20 blinding n.e. 100mm


1.30 thickness laid on earth
0.05
3
0.55 m

Mass concrete grade 40


7/ 1.20
1.30
1.00
3
10.92 m

Reinforcement (P3)

870 mm

1240 mm

X - Direction - T 16
Length 1300 mm
(-)Cover (2) 60 mm
1240 mm
(+)Bend (2) 1800 mm
(-)Cover (2) 60 mm
2980 mm
AMJ48103 INTEGRATED DESIGN PROJECT II
DRAWING NO: ELEMENT SLIP NO: 11
2018/05/28/FLY/SUNGAIARA/KEBAJIKANKANAK/S/F/1-3 W.B.L.F.F
PROJECT:CONSTRUCTION AND COMPLETION OF SCHOOL FOR MENTALLY RETARDED
CHILDREN AT JALAN DATO KERAMAT,10450 GEORGETOWN PULAU PINANG

DESCRIPTION: Work Below Lowest Floor Finish UNIT:m²,m³


QTY:
No. of Bar = (Y Length-2*Cover/Spacing)+1
7/ 12 / = 12
2.98
258.66 m T 16

870 mm

1140 mm

Y - Direction - T 12
Length 1200 mm
(-)Cover (2) 60 mm
1140 mm
(+)Bend (2) 1800 mm
(-)Cover (2) 60 mm
2880 mm

No. of Bar = (X Length-2*Cover/Spacing)+1


7/ 13 / = 13
2.88
270.14 m T 16

Stirrup 4R 8
X- Length = 1300 mm
Y- Length = 1200 mm

X- Length (2) 2600 mm


(-)Cover (2) 60 mm
2540 mm
Y- Length 2) 2400 mm
(-)Cover (2) 60 mm
(+)Hook 24d 192 mm
4/ 5072 mm
5.07
20.29 m R8
AMJ48103 INTEGRATED DESIGN PROJECT II
DRAWING NO: ELEMENT SLIP NO: 12
2018/05/28/FLY/SUNGAIARA/KEBAJIKANKANAK/S/F/1-3 W.B.L.F.F
PROJECT:CONSTRUCTION AND COMPLETION OF SCHOOL FOR MENTALLY RETARDED
CHILDREN AT JALAN DATO KERAMAT,10450 GEORGETOWN PULAU PINANG

DESCRIPTION: Work Below Lowest Floor Finish UNIT:m²,m³


2
QTY: 35 m
Formwork (P3)
Sawn timber of 38mm thickness for
7 ∕ 2 ∕ foundation
1.00
1.30
2
18.2 m

7 ∕ 2 ∕
1.00
1.20
2
16.8 m
AMJ48103 INTEGRATED DESIGN PROJECT II
DRAWING NO: ELEMENT SLIP NO: 13
2018/05/28/FLY/SUNGAIARA/KEBAJIKANKANAK/S/C/1-5 W.B.L.F.F
PROJECT:CONSTRUCTION AND COMPLETION OF SCHOOL FOR MENTALLY RETARDED
CHILDREN AT JALAN DATO KERAMAT,10450 GEORGETOWN PULAU PINANG

DESCRIPTION: Work Below Lowest Floor Finish UNIT:m,m²


QTY:
Concrete Work (C1)

35 / 0.30 Mass concrete grade 40


0.30
1.00
3
3.15 m

Reinforcement (C1)
Rebar 8 T 16
Length 1500 mm
(+) Bend 5d 80 mm
(+) Lapping 40d 640 mm
(-) Dia. Rebar (2) 24 mm
35 / 8/ 2196 mm
2.20
614.88 m 8 T 16

Stirrup 1 R 6
Length 1200 mm
(-) Cover (4) 120 mm
(+) Hook 24d 144 mm
1224 mm

Stirrup 2&3 R 6
Length 300 mm
(-) Cover (2) 60 mm
(+) Hook 24d 144 mm
384 mm
AMJ48103 INTEGRATED DESIGN PROJECT II
DRAWING NO: ELEMENT SLIP NO: 14
2018/05/28/FLY/SUNGAIARA/KEBAJIKANKANAK/S/C/1-5 W.B.L.F.F
PROJECT:CONSTRUCTION AND COMPLETION OF SCHOOL FOR MENTALLY RETARDED
CHILDREN AT JALAN DATO KERAMAT,10450 GEORGETOWN PULAU PINANG

DESCRIPTION: Work Below Lowest Floor Finish UNIT:m²


QTY:
No. of Stirrup = (Length/Spacing)+1
35 / 16 / = 16
1.99
1115.52 m R6

Formwork (C1)
Sawn timber of 38mm thickness for
stump

35 / 4/
1.00
2
140.00 m
AMJ48103 INTEGRATED DESIGN PROJECT II
DRAWING NO: ELEMENT SLIP NO: 15
2018/05/28/FLY/SUNGAIARA/KEBAJIKANKANAK/S/C/1-5 W.B.L.F.F
PROJECT:CONSTRUCTION AND COMPLETION OF SCHOOL FOR MENTALLY RETARDED
CHILDREN AT JALAN DATO KERAMAT,10450 GEORGETOWN PULAU PINANG

DESCRIPTION: Work Below Lowest Floor Finish UNIT:m,m²


QTY:
Concrete Work (C2)

138 / 0.30 Mass concrete grade 40


0.30
1.00
3
12.42 m

Reinforcement (C2)
Rebar 8 T 16
Length 1900 mm
(+) Bend 5d 80 mm
(+) Lapping 40d 640 mm
(-) Dia. Rebar (2) 24 mm
138 / 8/ 2596 mm
2.60
2865.98 m 8 T 16

Stirrup 1 R 6
Length 1200 mm
(-) Cover (4) 120 mm
(+) Hook 24d 144 mm
1224 mm

Stirrup 2&3 R 6
Length 300 mm
(-) Cover (2) 60 mm
(+) Hook 24d 144 mm
384 mm
AMJ48103 INTEGRATED DESIGN PROJECT II
DRAWING NO: ELEMENT SLIP NO: 16
2018/05/28/FLY/SUNGAIARA/KEBAJIKANKANAK/S/C/1-5 W.B.L.F.F
PROJECT:CONSTRUCTION AND COMPLETION OF SCHOOL FOR MENTALLY RETARDED
CHILDREN AT JALAN DATO KERAMAT,10450 GEORGETOWN PULAU PINANG

DESCRIPTION: Work Below Lowest Floor Finish UNIT:m²


QTY:
No. of Stirrup = (Length/Spacing)+1
138 / 20 / = 20
1.99
5497.92 m R6

Formwork (C2)
Sawn timber of 38mm thickness for
stump

138 / 4/
1.00
2
552.00 m
AMJ48103 INTEGRATED DESIGN PROJECT II
DRAWING NO: ELEMENT SLIP NO: 17
2018/05/28/FLY/SUNGAIARA/KEBAJIKANKANAK/S/C/1-5
W.B.L.F.F
PROJECT:CONSTRUCTION AND COMPLETION OF SCHOOL FOR MENTALLY RETARDED
CHILDREN AT JALAN DATO KERAMAT,10450 GEORGETOWN PULAU PINANG

DESCRIPTION: Work Below Lowest Floor Finish UNIT:m,m²


QTY:
Concrete Work (C3)

4/ 0.30 Mass concrete grade 40


0.30
1.00
3
0.36 m

Reinforcement (C3)
Rebar 8 T 20
Length 1900 mm
(+) Bend 5d 100 mm
(+) Lapping 40d 800 mm
(-) Dia. Rebar (2) 32 mm
4/ 8/ 2768 mm
2.77
88.58 m 8 T 20

Stirrup 1 R 6
Length 1200 mm
(-) Cover (4) 120 mm
(+) Hook 24d 144 mm
1224 mm

Stirrup 2&3 R 6
Length 300 mm
(-) Cover (2) 60 mm
(+) Hook 24d 144 mm
384 mm
AMJ48103 INTEGRATED DESIGN PROJECT II
DRAWING NO: ELEMENT SLIP NO: 18
2018/05/28/FLY/SUNGAIARA/KEBAJIKANKANAK/S/C/1-5 W.B.L.F.F
PROJECT:CONSTRUCTION AND COMPLETION OF SCHOOL FOR MENTALLY RETARDED
CHILDREN AT JALAN DATO KERAMAT,10450 GEORGETOWN PULAU PINANG

DESCRIPTION: Work Below Lowest Floor Finish UNIT:m²


QTY:
No. of Stirrup = (Length/Spacing)+1
4/ 20 / = 20
1.99
159.36 m R6

Formwork (C3)
Sawn timber of 38mm thickness for
stump

4 / 4/
1.00
2
16.00 m
AMJ48103 INTEGRATED DESIGN PROJECT II
DRAWING NO: ELEMENT SLIP NO: 19
2018/05/28/FLY/SUNGAIARA/KEBAJIKANKANAK/S/C/1-5 W.B.L.F.F
PROJECT:CONSTRUCTION AND COMPLETION OF SCHOOL FOR MENTALLY RETARDED
CHILDREN AT JALAN DATO KERAMAT,10450 GEORGETOWN PULAU PINANG

DESCRIPTION: Work Below Lowest Floor Finish UNIT:m,m²


QTY:
Concrete Work (C4)

1/ 0.30 Mass concrete grade 40


0.30
1.00
3
0.09 m

Reinforcement (C4)
Rebar 8 T 25
Length 1900 mm
(+) Bend 5d 125 mm
(+) Lapping 40d 1000 mm
(-) Dia. Rebar (2) 32 mm
1/ 8/ 2993 mm
2.99
23.94 m 8 T 25

Stirrup 1 R 10
Length 1200 mm
(-) Cover (4) 120 mm
(+) Hook 24d 240 mm
1320 mm

Stirrup 2&3 R 10
Length 300 mm
(-) Cover (2) 60 mm
(+) Hook 24d 240 mm
480 mm
AMJ48103 INTEGRATED DESIGN PROJECT II
DRAWING NO: ELEMENT SLIP NO: 20
2018/05/28/FLY/SUNGAIARA/KEBAJIKANKANAK/S/C/1-5 W.B.L.F.F
PROJECT:CONSTRUCTION AND COMPLETION OF SCHOOL FOR MENTALLY RETARDED
CHILDREN AT JALAN DATO KERAMAT,10450 GEORGETOWN PULAU PINANG

DESCRIPTION: Work Below Lowest Floor Finish UNIT:m²


QTY:
No. of Stirrup = (Length/Spacing)+1
1/ 20 / = 20
2.28
45.60 m R 10

Formwork (C4)
Sawn timber of 38mm thickness for
stump

1 / 4/
1.00
2
4.00 m
AMJ48103 INTEGRATED DESIGN PROJECT II
DRAWING NO: ELEMENT SLIP NO: 21
2018/05/28/FLY/SUNGAIARA/KEBAJIKANKANAK/S/C/1-5 W.B.L.F.F
PROJECT:CONSTRUCTION AND COMPLETION OF SCHOOL FOR MENTALLY RETARDED
CHILDREN AT JALAN DATO KERAMAT,10450 GEORGETOWN PULAU PINANG

DESCRIPTION: Work Below Lowest Floor Finish UNIT:m,m²


QTY:
Concrete Work (C5)

2/ 0.30 Mass concrete grade 40


0.30
1.00
3
0.18 m

Reinforcement (C5)
Rebar 8 T 20
Length 1900 mm
(+) Bend 5d 100 mm
(+) Lapping 40d 800 mm
(-) Dia. Rebar (2) 32 mm
2/ 8/ 2768 mm
2.77
44.29 m 8 T 25

Stirrup 1 R 6
Length 1200 mm
(-) Cover (4) 120 mm
(+) Hook 24d 144 mm
1224 mm

Stirrup 2&3 R 6
Length 300 mm
(-) Cover (2) 60 mm
(+) Hook 24d 144 mm
384 mm
AMJ48103 INTEGRATED DESIGN PROJECT II
DRAWING NO: ELEMENT SLIP NO: 22
2018/05/28/FLY/SUNGAIARA/KEBAJIKANKANAK/S/C/1-5 W.B.L.F.F
PROJECT:CONSTRUCTION AND COMPLETION OF SCHOOL FOR MENTALLY RETARDED
CHILDREN AT JALAN DATO KERAMAT,10450 GEORGETOWN PULAU PINANG

DESCRIPTION: Work Below Lowest Floor Finish UNIT:m²


QTY:
No. of Stirrup = (Length/Spacing)+1
2/ 20 / = 20
1.99
79.68 m R6

Formwork (C4)
Sawn timber of 38mm thickness for
stump

2 / 4/
1.00
2
8.00 m
ITEM DESCRIPTIONS UNIT QUANTITY RATE AMOUNT
(RM) (RM)
1 Site clearance ha. 0.57
2 Earthwork cutting and filling m
3 6394.00
3 Excavation of top soil 2 5670.00
m
4 Deposition of top soil m
3 567.00
5 Pit Excavation to red. col. base max. depth m
3 141.28
n.e. 1 m Type 2 Pile Cap
6 Pit Excavation to red. col. base max. depth m
3 21.29
n.e. 1 m Type 3 Pile Cap
7 Pit Excavation to red. col. base max. depth m
3 19.53
n.e. 1 m Type 1 Pile Cap
8 Filling to Excation with material arising m
3

from excavation
9 E.o. excavation in rock m
3 18.21
10 Allow for keeping the surface of the site m
3 ITEM
&excavation free from surface water
11 Concrete Work (Foundation Pile Cap)
Concrete Blinding G20 m
3 7.40
Mass concrete G40 m
3 107.13
12 Reinforcement (Foundation Pile Cap)
2
T12, 6505m (3.14*0.006 *6505*7850) kg 6505.00
2
T16, 529m (3.14*0.008 *529*7850) kg 529.00
2
R8, 38m (3.14*0.004 *38*7850) kg 38.00
3
Density of steel bar, assume = 7850kg/m
13 Formwork (Foundation Pile Cap)
Sawn timber of 38mm thickness for pile cap 2 513.20
m
14 Concrete Work (Column Stump)
Mass concrete grade 40 m
3 16.20
15 Reinforcement (Column Stump)
2
T16, 3481m (3.14*0.008 *3481*7850) kg 3481.00
2
T20, 133m (3.14*0.010 *133*7850) kg 133.00
2
T25, 24m (3.14*0.013 *24*7850) kg 24.00

R6, 6853m (3.14*0.003 *6853*7850)


2
kg 6853.00
2
R10, 46m (3.14*0.005 *46*7850) kg 46.00
3
Density of steel bar, assume = 7850kg/m
16 Formwork (Column Stump)
Sawn timber of 38mm thickness for column 2 720.00
m
stump

Total Bill RM