Professional Documents
Culture Documents
Optimization Scheduling Project Rehabilitation Bui
Optimization Scheduling Project Rehabilitation Bui
Optimization Scheduling Project Rehabilitation Bui
Constructions of UNTAN
Jurnal Teknik Sipil
Journal homepage: https://jurnal.untan.ac.id/index.php/jtsuntan
1. Introduction
A construction project is a temporary facility or infrastructure development project carried out within
a limited period with specific financial resources to achieve clear goals (Setiawati et al., 2017).
Projects usually have a deadline, meaning they must be completed before or precisely at the
specified time (Taurusyanti & Lesmana, 2015).
The planning stage measures project success and determines the allocation of resources, time, and
quality to be achieved. Proper project management is needed to achieve work efficiency and
effectiveness (S. et al. Dewi, 2017). Project management is when individuals maintain, develop,
control, and implement programs as part of an organization, all consistent with predetermined goals
and sustainable over time (Oka & Kartikasari, 2019).
989
Layla Mutiara Halim, 2024. Jurnal Teknik Sipil: Vol 24, No. 1, February 2024
Planning and scheduling influence project implementation to achieve efficiency and effectiveness.
Scheduling is part of the planning results and can provide information about the planned schedule
and project progress (Hidayah et al., 2018). Optimization analysis can be interpreted as
decomposing the project duration and using various alternatives to achieve the best (optimal)
acceleration of implementation time. Reducing activity time in the work network by shortening the
time on the critical path to shorten the overall completion time is called project crashing (Muhammad,
2015). The Critical Path Method (CPM) is frequently used for project scheduling and time
management because it can characterize project activities in a work network and may be applied to
project planning and control.
Scheduling optimization will be done for the Building Rehabilitation Project, Dekranasda Hall, and
Kalimantan Barat Museum Fence. Scheduling will be done using the critical path method (CPM) to
optimize the project duration. Critical Path Method (CPM) as a scheduling method, the results will
be obtained as a critical path, making it easier to analyze the activities to be optimized. Although in
this method, overlapping activities cannot be carried out, another reason for continuing to use the
Critical Path Method (CPM) in this research is that researchers want to know that by modifying this
method, it can optimize in terms of time without changing the basic rules of the Critical Path Method
(CPM).
990
Layla Mutiara Halim, 2024. Jurnal Teknik Sipil: Vol 24, No. 1, February 2024
Dependency Logic
A working network is a dependency relationship between parts of the work described or visualized
in a network diagram. With the work network, it can find out the area that is the critical path so that
it can find out the work that is prioritized and the work that can be postponed. (Sugiyarto, S.,
Qomariyah, S., & Hamzah, F., 2013).
Dependency logic plays a vital role in creating a work network by determining the order of work and
the dependency of each item. The activity that is the point in time that is the predecessor is called
the predecessor, and the activity after it is the successor. Activities that can be performed
simultaneously with ongoing activities are called parallel or concurrent relationships. The first event
in the project schedule is the starting point where the project will begin, and the end event is the
point at which the project has been completed.
Forward and Backward Count
Using the Critical Path Method (CPM) for scheduling, two computations—the forward count and the
backward—are made to determine the overall project length. The critical path can be found using a
forward count method. Through the use of the maximum value, this forward count helps determine
the earliest start time (EETi = Earliest Even Time node i) on the i-node and the earliest start time
(EETj = Earliest Even Time node j) on the j-node of all functions. The forward count formula functions
as listed below:
ESij = EETi ..............................................................................................................................(2.1)
EFij = ESij + dA..........................................................................................................................2.2)
Description:
ESij = Earliest Start, earliest activity start time
EFij = Earliest Finish, the earliest activity time completed
The countdown aims to determine the latest time to start and end each activity without delaying the
overall project timeframe generated by the forward count. This calculation also aims to obtain the
latest finish time (LETi = Latest Even Time node i) at i-node and the latest finish time (LETj = Latest
Even Time node j) at j-node of all activities by taking the minimum value. The following is the formula
for the countdown.
LFij = LETj................................................................................................................................(2.3)
LSij = LFij – dA...........................................................................................................................2.4)
Description:
LFij = Latest Finish, the latest time activities must be completed
LSij = Latest Start, the latest time the activity must start
Activity time or Activity Time can be seen in Figure 1
991
Layla Mutiara Halim, 2024. Jurnal Teknik Sipil: Vol 24, No. 1, February 2024
Critical Path
The critical path is a series of activities with zero float, with the definition of float being the delay time
allowed for an activity without causing delays to the project as a whole. In the critical path method,
the total project duration is determined by calculating the longest path in the project work network
diagram (Hamzah et al., 2020).
Total Float
According to Husen (2011), Float is the final tolerance limit for delays in an activity that can be used
for time optimization. Meanwhile, according to (Muhammad Khalil et al., 2018), the total completion
time of activities can be postponed without affecting the fastest time to complete a project. This stage
is critical or the longest implementation path determining the project completion time. Total Float
(TF) can state how long an activity can be late but does not affect the completion time of a project.
All activities on the path in question own this float. It can be formulated using the following equation:
TF = LETj - EETi - Dij.................................................................................................................2.5)
Description:
LETj = The latest time activities must be completed
EETi = Earliest activity start time
Dij = Duration from activity I to J
WBS organizes projects structurally through hierarchical reporting to solve the project work process
in stages in each detail (Varsani et al., 2020). The following is the composition of the WBS in the
Kalimantan Barat Museum Building and Hall Rehabilitation project.
992
Layla Mutiara Halim, 2024. Jurnal Teknik Sipil: Vol 24, No. 1, February 2024
BUILDING AND
HALL
DEKRANASDA
GALERY HALL
AC, CEILING
DOOR, WINDOW MECHANICAL CLEAN, USED &
DEMOLITION & FAN &
PRELIMINARY STRUCTURE FLOOR & & WALL & PAINTING SANITARY ROOFING ELECTRICAL & DIRTY WATER LANSECAP
CLEARANCE EXHAUST FAN
WORK WORK CEILING WORK VENTILATION FACADE WORK WORK WORK WORK PLUMBING INSTALLATION WORK
WORK INSTALLATION
(A) (C) (D) WORK (F) (G) (H) (I) WORK WORK (M)
(B) WORK
(E) (J) (L)
(K)
- A.1 - B.1 - S.4 - C.22 - D.1 - E.1 - E.14 - F.1 - G.1 - H.1 - I.1 - J.1 - S.13 - S.14.1 - S.16
- A.2 - B.2 - C.1 - C.23 - D.2 - E.2 - E.15 - F.2 - G.2 - H.2 - I.2 - S.10 - S.14.2
- A.3 - B.3 - C.2 - C.24 - D.3 - E.3 - E.16 - F.3 - G.3 - H.3 - I.3 - S.11 - S.15
- A.4 - S.2 - C.3 - C.25 - D.4 - E.4 - E.17 - S.7 - H.4 - I.4 - S.12
- A.5 - S.3 - C.4 - C.26 - S.6 - E.5 - E.18 - S.8 - H.5 - I.5
- S.1 - C.5 - C.27 - D.5 - E.6 - E.19 - H.6 - I.6
- C.6 - C.28 - E.7 - E.20 - H.7 - I.7
- C.7 - C.29 - E.8 - E.21 - H.8 - I.8
- C.8 - C.30 - E.9 - E.22 - H.9 - I.9
- C.9 - C.31 - E.10 - E.23 - H.10
- S.5 - C.32 - E.11 - E.24
- C.10 - C.33 - E.12 - E.25
- C.11 - C.34 - E.13 - E.26
- C.12 - C.35
- C.13 - C.36
- C.14 - C.37
- C.15 - C.38
- C.16 - C.39
- C.17 - C.40
- C.18 - C.41
- C.19 - C.42
- C.20 - C.43
- C.21 - C.44
993
Layla Mutiara Halim, 2024. Jurnal Teknik Sipil: Vol 24, No. 1, February 2024
Table 2. Description Activity Sequence Code Scheduling with Critical Path Method CPM
994
Layla Mutiara Halim, 2024. Jurnal Teknik Sipil: Vol 24, No. 1, February 2024
Table 2. (Continued) Description Activity Sequence Code Scheduling with Critical Path Method CPM
995
Layla Mutiara Halim, 2024. Jurnal Teknik Sipil: Vol 24, No. 1, February 2024
Table 3. Backward and Forward Calculation and Total Float Normal Scheduling
ES LS EF LF TF
No Item Duration Predecessor Dec
Eli LFij – dA ESij + dA LFj LFj - ESi - Dij
996
Layla Mutiara Halim, 2024. Jurnal Teknik Sipil: Vol 24, No. 1, February 2024
997
Layla Mutiara Halim, 2024. Jurnal Teknik Sipil: Vol 24, No. 1, February 2024
998
Layla Mutiara Halim, 2024. Jurnal Teknik Sipil: Vol 24, No. 1, February 2024
Figure 4. Work Network with Critical Path Method (CPM) Scheduling Optimization
The work diagram above shows that the most extended activity is on the activity path:
S.2 → (B.3/B.2) → B1 → A.2 → A.3 → C.1 → C.3 → C.2 → C.8 → C.7 → C.5 → C.21 → C.22 →
C.13.2 → C.11 → (C.19.2/C.23.2) → C.38 → (C.16/C.20) → C.36 → C.32.3 → C.37.1 →
(C.37.2/C.39) → C.33.2 → (C.33.3/C.34) → C.35.2 → (I.3/I.4) → I.1.1 → F.1.1 → (E.1/E.6/S.11) →
(E.11/E.15/E.21) → F.2.1 → F.3.1 → G.3 → (D.1/D.3) → (D.2.1/S.7) → D.2.2
3 + 2 + 2 + 2 + 2 + 19 + 2 + 2 + 1 + 1 + 2 + 2 + 2 + 2 + 2 + 2 + 1 + 1 + 2 + 4 + 3 + 2 + 4 + 2 + 3 + 1
+ 6 + 10 + 1 + 1 + 10 + 6 + 4 + 13 + 2 + 1 = 125 days.
The above activities are critical paths because they have a grace period (float) or TF = 0. The TF
value is obtained from forward calculations and backward calculations. The activities on the critical
path above are the results obtained from the optimization carried out in the previous stage. After the
steps are taken to optimize scheduling, there is a change in the total duration. Regular scheduling
has a total duration of 249 working days. After scheduling optimization using the Critical Path
Method, the total duration becomes 125 working days. The total duration is obtained from the
summation of the duration of activities through the critical path.
Forward, Backward, and Float Counts of Scheduling with the Critical Path Method (CPM)
1. ES Calculation
a. ES Activity S.2 = EET5 = 0
b. ES Activity B.3 = EET8 = 0 + 3 = 3
c. ES Activity B.1 = EET11 = 3 + 2 = 5, etc.
999
Layla Mutiara Halim, 2024. Jurnal Teknik Sipil: Vol 24, No. 1, February 2024
2. EF Calculation
a. EF Activity S.2 = ES5-8 + dS.2 = 0 + 3 = 3
b. EF Activity B.3 = ES8-11 + dB.3 = 3 + 2 = 5
c. EF Activity B.1 = ES11-14 + dB.1 = 5 + 2 = 7, etc.
3. LF Calculation
a. LF Activity S.9 = LET120 = 125
b. LF Activity I.8 = LET95 = 125 – 5 = 120
c. LF Activity I.9 = LET89 = 120 – 6 = 114, etc.
4. LS Calculation
a. LS Activity S.9 = LF120-95 – dS.9 = 125 – 5 = 120
b. LS Activity I.8 = LF95-89 – dI.8 = 120 – 6 = 114
c. LS Activity I.9 = LF89-84 – dI.9 = 114 – 4 = 110, etc.
5. TF Calculation
a. EF Activity S.2 = LF8 – ES5 – dS.2 = 3 – 0 – 3 = 0
b. EF Activity B.3 = LF11 – ES8 – dB.3 = 5 – 3 – 2 = 0
c. EF Activity B.1 = LF14 – ES11 – dB.1 = 7 – 5 – 2 = 0, etc.
The following is an example of a calculation table for Demolition & Clearance Work.
Table 7. Backward and Total Float Calculation of Scheduling Optimization
4. Conclusion
Based on the results of this study, the project completion duration can be optimized from the standard
249 working days to 125 working days. Two methods to optimize the scheduling are: First, divide
the work item volumes into several parts so that some tasks can commence without waiting entirely
for the preceding tasks to be finished. The work items that can be divided can be prefabricated either
on-site or off-site. Second, scheduling optimization is achieved by setting a target duration to
optimize task completion and calculating the adequate number of workers needed through trial-and-
error calculations.
5. Acknowledgement
The authors would like to thank those who have contributed to this research. The authors also thank
the Civil Engineering Journal (JTS) of Tanjungpura University for uploading this research journal.
6. Author’s Note
This article, published in the Jurnal Teknik Sipil UNTAN (JTS), is the result of original research
conducted by the author(s). The work presented herein is free from any form of plagiarism. Any
similarities to other works are purely coincidental. All reference sources utilized during the
preparation of this journal article have been appropriately cited following applicable guidelines and
are included in the article's references section.
7. References
Andiyan, A., Putra, R. M., Rembulan, G. D., & Tannady, H. (2021). Construction project evaluation
using CPM-crashing, CPM-Pert, and CCPM to minimize project delays. Journal of
Physics: Conference Series, 1933(1), 012096. https://doi.org/10.1088/1742-
6596/1933/1/012096.
1000
Layla Mutiara Halim, 2024. Jurnal Teknik Sipil: Vol 24, No. 1, February 2024
Ariana, I. K. A., Nuraga, I. K., Budiarnaya, P., Ariawan, P., Wismantara, I. G. N. N., Riana, I. N.,
Pangestu, I. K. P. (2021). Analisis Perbandingan Penjadwalan Menggunakan Critical Path
Method (CPM) dengan Precedence Diagram Method (PDM) (Studi Kasus : Proyek
Pembangunaan SD Negeri 5 Pecatu). Bali: Jurnal Ilmiah TELSINAS, 4(1), 56-61.
Ba'Its, H. A., Puspita, I. A., & Bay, A. F. (2020). Combination Of Program Evaluation and Review
Technique (PERT) and Critical Path Method (CPM) for Project Schedule
Development. International Journal of Integrated Engineering, 12(3), 68-75.
Chen, K., Si, J., Zhou, F., Zhang, R., Shao, H., & Zhao, H. (2015). Optimization of Air Quantity
Regulation in Mine Ventilation Networks Using The Improved Differential Evolution
Algorithm and Critical Path Method. International Journal of Mining Science and
Technology, 25(1), 79–84.
Ervianto, W. I. 2009. Manajemen Proyek Konstruksi, Yogyakarta: ANDI OFFSET.
Gazalba, Z., & Warka, I. G. P. (2022). Evaluasi Kewajaran Schedule Kontraktor Menggunakan
Work Breakdown Structure (WBS) dan Microsoft Project (Studi Pada Proyek
Pembangunan SDN 5 Sokong, Tanjung, Lombok Utara). GANEC SWARA, 16(1), 1285-
1296.
Hidayah, R., Ridwan, A., & Cahyo, Y. (2018). Analisa Perbandingan Manajemen Waktu Antara
Perencanaan dan Pelaksanaan. Jurnal Manajemen Teknologi dan Teknik Sipil
(JURMATEKS), 1(2), 281-290.
Husen, A. (2011). Manajemen Proyek. Andi Offset. Yogyakarta
Iwawo, E. R. (2016). Penerapan Metode CPM Pada Proyek Konstruksi . Jurnal Sipil Statik Vol.4
No.9 September 2016, 551-558.
Kholil, M., Alfa, B. N., & Hariadi, M. (2018, April). Scheduling Of House Development Projects
With CPM and PERT Method for Time Efficiency (Case Study: House Type 36). In IOP
Conference Series: Earth and Environmental Science (Vol. 140, No. 1, p. 012010). IOP
Publishing.
Muhammad, A. H. (2017). Optimasi Pelaksanaan Proyek Konstruksi Dengan Metode PERT dan
CPM. Jurnal Ilmiah Ecosystem, 17(2), 698-709.
Oka, J., & Kartikasari, D. (2017). Evaluasi Manajemen Waktu Proyek Menggunakan Metode
PERT dan CPM Pada Pengerjaan “Proyek Reparasi Crane Lampson” di PT Mcdermott
Indonesia. Journal of Applied Business Administration, 1(1), 28-36.
Safitri, E., Basriati, S., & Latifah, H. (2019). Optimasi Penjadwalan Proyek Menggunakan CPM
Dan PDM (Studi Kasus: Pembangunan Gedung Balai Nilah Dan Manasik Haji Kua
Kecamatan Kateman Kabupaten Indragiri Hilir). Riau: Jurnal Sains dan Matematika, 5(2),
17-25.
Saputra, N., Handayani, E., & Dwiretnani, A. (2021). Analisa Penjadwalan Proyek dengan Metode
Critical Path Method (CPM) Studi Kasus Pembangunan Gedung Rawat Inap RSUD Abdul
Manap Kota Jambi. Jurnal Talenta Sipil, 4(1), 44-52.
Setiawati, S., & Syahrizal, R. A. D. (2017). Penerapan metode CPM dan PERT Pada Penjadwalan
Proyek Konstruksi (Studi Kasus: Rehabilitasi/Perbaikan dan Peningkatan Infrastruktur
Irigasi Daerah Lintas Kabupaten/Kota DI Pekan Dolok). Jurnal Teknik Sipil USU, 6(1), 1-
15.
Soeharto, I. (1999). Manajemen Proyek (Dari Konseptual Sampai Operasional). Jakarta:
Erlangga.
Soleman, A. R. C., Pratami, D., & Bay, A. F. (2018). Designing Project Schedule for Migration
Project Sto Dago in PT. XYZ to Accelerate Project Duration Using Schedule
Compression A Lesson Learn Case Study for Another Similar Project. In Proceeding of
International Seminar & Conference on Learning Organization
1001
Layla Mutiara Halim, 2024. Jurnal Teknik Sipil: Vol 24, No. 1, February 2024
Sugiyarto, S., Qomariyah, S., & Hamzah, F. (2013). Analisis Network Planning Dengan CPM
(Critical Path Method) Dalam Rangka Efisiensi Waktu dan Biaya Proyek. Matriks Teknik
Sipil, 1(4), 408.
Taurusyanti, D., & Lesmana, M. F. (2015). Optimalisasi Penjadwalan Proyek Jembatan Girder
Guna Mencapai Efektifitas Penyelesaian Dengan Metode PERT dan CPM Pada PT Buana
Masa Metalindo. JIMFE (Jurnal Ilmiah Manajemen Fakultas Ekonomi), 1(1), 32-36.
Varsani, P. D., Bhavsar, A. N., & Pitroda, J. R. (2020). Effective Scheduling and Control of
Construction Project Using Primavera P6: A Review. UGC Care J, 40(50), 5050-5064.
Warsika, P. D. (2016). Analisa Biaya Dan Waktu Dengan Metode Fast Track Pada Pelaksanaan
Proyek Konstruksi (Studi Kasus: Proyek Pembangunan Gedung Di Kabupaten
Badung). Bali: Fakultas Teknik, Universitas Udayana.
1002