Professional Documents
Culture Documents
SMA_M05_Example_Printable-version_16a
SMA_M05_Example_Printable-version_16a
PERT Example
PRINTABLE VERSION
Version 16a
© Copyright CPA Australia unless otherwise indicated.
PERT EXAMPLE PRINTABLE VERSION | 1
Activity 1 —
Activity 2 1
Activity 3 1
Activity 4 1
Activity 5 2
Activity 6 3
Activity 7 4
Activity 8 5
Activity 9 6
Activity 1
a
Activity 1
a b
2 | STRATEGIC MANAGEMENT ACCOUNTING
2
i ty
tiv
Ac
Activity 1 Activity 3
a b
Ac
tiv
ity
4
2
iv ity
A ct
Activity 1 Activity 3
a b d
Ac
tiv
ity
4
e
PERT EXAMPLE PRINTABLE VERSION | 3
So now we draw Activity 5 and its completion node into the diagram, directly after the
completion (node) of Activity 2.
Activity 5 f
c
2
iv ity
Act
Activity 1 Activity 3
a b d
Ac
tiv
ity
4
Activity 5 f
c
2
ty
tivi
Ac
Ac
tiv
ity
4
e
4 | STRATEGIC MANAGEMENT ACCOUNTING
Activity 5 f
c
Ac
tiv
2
ity
ivity
8
Act
Ac
tiv 7
ty
ity tivi
4 Ac
Activity 5 f
c
Ac
tiv
2
ity
ivity
8
Act
Ac
tiv 7
ty
ity tivi
4 Ac
e
PERT EXAMPLE PRINTABLE VERSION | 5
Activity 1 20 25 30
Activity 2 1 10 20 30
Activity 3 1 15 20 25
Activity 4 1 6 20 40
Activity 5 2 6 35 70
Activity 6 3 20 28 60
Activity 7 4 8 19 24
Activity 8 5 10 45 50
Activity 9 6 6 9 18
The following formula is used to calculate the overall ‘expected time’ for each activity.
ET = (O + 4ML + P)/6
or for Activity 6:
Once the expected times have been calculated for each activity, they should be added to the
network diagram as shown below.
Activity 1 20 25 30 25
Activity 2 1 10 20 30 20
Activity 3 1 15 20 25 20
Activity 4 1 6 20 40 21
Activity 5 2 6 35 70 36
Activity 6 3 20 28 60 32
Activity 7 4 8 19 24 18
Activity 8 5 10 45 50 40
Activity 9 6 6 9 18 10
Activity 5 f
c
36
Ac
tiv
2
ity
ty
40
ivi
8
t
Ac
20
Ac
tiv 7
ity tivity
4 Ac
18
21
e
PERT EXAMPLE PRINTABLE VERSION | 7
In this case, the critical path is path 1 (shown using the bold arrows in the diagram below).
Activity 5 f
c
36
Ac
2
tiv
ty
ity
ivi
40
t
8
Ac
20
Ac
tiv 7
ty
ity tivi
4 Ac
18
21