Installation Procedure of Heat Exchanger-Samtech
Installation Procedure of Heat Exchanger-Samtech
Installation Procedure of Heat Exchanger-Samtech
24-Feb-2019
By Chk’d App’d
Rev. Date Description
1
1. GENERAL
This procedure covers minimum requirements for handling and installation of Heat
Exchanger.
2. APPLICABLE ITEMS
Heat Exchanger
3. BASIC INFORMATION
4. PREPARATION
2
4.3 Equipment Drawing / Data Sheet / Manual Instruction / Installation Procedure
Prior to install, all equipment shall be provided with drawing or data sheet or manual
instruction or installation procedure to make sure that all activities doing by correct
manner. If needed, the supervise by vendor is a must.
a. All equipment shall be checked on received at site for any damage and any
missing parts from the packing list. If any discrepancies found shall be
reported as described in the material control procedure. An OSD (Overage,
Shortage, Damage) report shall be prepared for any discrepancies.
b. Care shall be taken to transportation and storage of the equipment to
make
sure proper procedures are adopted as per manufactures recommendations.
c. Packaging shall be removed except the pallet. But if the equipment is packed
to the pallet and bended with strip plate, no needed to remove the packaging.
d. Used appropriate crane or forklift to move and lift up the equipment to truck.
e. Make sure the position is steady and balanced.
f. Tightened.
g. Equipment are ready to transport to the installed foundation.
3
a. The orientation four position ( 0º, 90º, 180º and 270º ) to be marked on the
equipment for checking orientation as per drawing.
b. Leveling and verticality shall be done with packing plates and shims to correct
location and elevation and checked with plumb at least 4 points.
c. If not specified, maximum plumb not more than 25 mm or 1/200h wherever
the smaller to be used.
d. Coordination with Civil Contractor, Once the equipment has been set in
correct location and elevation and approved the base can be grouted with
approved grouting materials (civil contractor scoop).
The surface to be grouted shall be saturated with water for at least 24 hours
in advance. Any free standing water must be removed before placing the
grout (civil contractor scoop).
e. Recheck the concrete surface to ensure that it is free from dirt, oil, grease, or
any loose materials.
f. Lift down equipment from truck.
g. Removed all stripped bend/plate that it is part of packaging and also all
tightening part to pallet.
h. Using webbing sling, placed on four position (Lifting lugs) and appropriate
crane capacity, standing up the tank.
4
k. Prior tank installation to the foundation, make sure foundation has levelled.
l. Place the tank orientation as per lay out drawing and fit the anchor bolt holes
to the foundation anchor.
m. Set the level, use water pass to make sure the level is correct.
n. Check the settlement.
o. Tightened the anchor bolt.
5
5.4. Inspection
When equipment has been installed and ready for inspection, the QC Engineer
shall arrange and to invite the Client Representative to witness and approve the
location and orientation check as per Inspection & Test Plan (ITP).
1. Foundation check M W R
3. Plumbness / levelling M W W
Internal Installation,
4. M W W
Cleaning and boxing up
6. DOCUMENTATION
6.1. All Inspection Records shall be filed and documented as per procedure
6.2. After construction works are finished as contract, all original required
documentations as per contract shall be submitted to Client and copied for
our file.