Gharapjhong Rural Municpality

Office of the Rural Municipal Executive


Jomsom, Mustang
Bill Of Quantity
Project name:- Renovation work in house owned by RM infront of airport
location:- gharapjhong ga.Pa ward no-3
Rate
S.No. Description Unit Quantity Remarks
in figures Inwords
Chiselling is required on the existing floor for new leveling,
1 minor maintainance, and ground levelling as needed to meet site job 1.00
requirements
2 stone masonry work in 1:6 c/s mortar m3 0.32
3 stone soiling work m3 0.59
4 1:2:4 PCC works m3 0.47
5 12.5mm thick plaster work in 1:4 c/s mortar m2 13.78
6 3mm cement punning works m2 10.33
7 Iron work for railings kg 105.05
8 Prime coat followed by two coat enamail paintings m2 5.1
9 Prime coat followed by two coat plastict emulsion paintings m2 13.71
Plumbing work and maintainance work in the first floor as per
job 1
10 the site incharge
Total civil work
Vat @ 13%
Grand total cost of project

Signature and Stamp:-


Name of the Firm:-
Date:-
Signature and Stamp:-
Name of the Firm:-
Date:-
Gharapjhong Rural Municpality
Office of the Rural Municipal Executive
Jomsom, Mustang
Abstract of Cost
Project name:- Renovation work in house owned by RM infront of airport
location:- gharapjhong ga.Pa ward no-3
S.No. Items Unit Quantity Unit Rate Total cost Remarks

Chiselling is required on the existing floor for new leveling,


1 minor maintainance, and ground levelling as needed to meet site job 1.00 2000.00 2000.00
requirements
2 stone masonry work in 1:6 c/s mortar m3 0.32 11722.40 3751.17
3 stone soiling work m3 0.59 2732.40 1612.12
4 1:2:4 PCC works m3 0.47 13643.29 6412.35
5 12.5mm thick plaster work in 1:4 c/s mortar m2 13.78 436.7 6017.73
6 3mm cement punning works m2 10.33 336.19 3472.84
7 Iron work for railings kg 105.05 196.99 20693.80
8 Prime coat followed by two coat enamail paintings m2 5.1 337.5 1721.25
9 Prime coat followed by two coat plastict emulsion paintings m2 13.71 346.46 4749.97
Plumbing work and maintainance work in the first floor as per
10 job 1 4111.84 4111.84
the site incharge
Sub total 54543.06
Vat @ 13% 7090.60
Grand total cost of the project 61633.65
d=n]=k= kmf=g+ !&^

!_ of]hgfsf] gfd M एयरपोर्ट अगाडि R.M स्वामित्वमा रहेको घरमा नवीकरण कार्य &_ Oli6d]6 eGbf 36La9L :- +367.65
7]ufgf M घरपझोङ गाउँपालिका ३ नं. वडा Gharapjhong Rural Municipality *_ 36La9Lsf] k||ltzt M =+0.69%
#_ cfly{s jif{ M 2080/81 Office of Rural Municipality Executive (_ sfd z'? ePsf] ldlt M 2080/06/14
$_ cg'bfg /sd ?=M ^!@^^ jomsom,Mustang !)_ sfd ;DkGg ug'{ kg]{ ldlt M 2080/06/18
%_ Oli6d]6sf] s'n c+s M^!^##=^% !!_ ;DkGg ePsf] ldlt M2080/06/18
^_ vr{ ePsf] s'n c+s %)(!@=!!
sfo{ ;DkGg k|ltj]bg
Oli6d]6 adf]lhdsf] v'b ePsf] sfd km/s s}lkmot
qm=;+= sfdsf] ljj/0f PsfO{ kl/df0f b/ hDdf kl/df0f b/ hDdf kl/df0f b/ hDdf
Chiselling is required on the existing floor for new
leveling, minor maintainance, and ground levelling job 1.00 2000.00 1.00 2000.00 1.00 2000.00
1 as needed to meet site requirements 2000 2000 2000
2 stone masonry work in 1:6 c/s mortar m3 0.32 11722.40 3751.168 0.32 11722.40 3751.168 0.32 11722.40 3751.168
3 stone soiling work m3 0.59 2732.40 1612.116 0.59 2732.40 1612.116 0.59 2732.40 1612.116
4 #REF! m3 0.47 13643.29 6412.3463 0.47 13643.29 6412.3463 0.47 13643.29 6412.3463
5 #REF! m2 13.78 436.7 6017.726 13.78 436.7 6017.726 13.78 436.7 6017.726
6 #REF! m2 10.33 336.19 3472.8427 10.33 336.19 3472.8427 10.33 336.19 3472.8427
7 #REF! kg 105.05 196.99 20693.7995 105.05 196.99 20693.7995 105.05 196.99 20693.7995
8 #REF! m2 5.1 337.5 1721.25 5.1 337.5 1721.25 5.1 337.5 1721.25
#REF! m2 13.71 346.46 13.71 346.46 13.71 346.46
9 4749.9666 4749.9666 4749.9666
10 #REF! job 1 4111.84 4111.84 1 4111.84 4111.84 1 4111.84 4111.84
Sub total:- 54543.06
VAT@13% 7090.60
Grand total cost of project 61633.65
gf]6 M– a9L ePdf -±_ 36L ePdf -—_ lrGx clÍt ug]{ .
Oli6d]6 eGbf 36L a9L vr{ ePsf d'Vo sf/0f M–
:jLs[t l8hfOg / :k]l;lkms]zg sfd ePsf] 5 egL k|dfl0ft ug]{ M–

;j OlGhlo/ OlGhlgo/ k|d'v k|zf;sLo clws[t


M 2080/06/18
Gharapjhong Rural Municpality
Office of the Rural Municipal Executive
Jomsom, Mustang
DETAILED QUANTITY ESTIMATE
Project name:- Renovation work in house owned by RM infront of airport
location:- gharapjhong ga.Pa ward no-3
S.No. Description of work Nos. Length Breadth Height Quantity Remarks

Chiselling is required on the existing floor for new leveling, minor


1 maintainance, and ground levelling as needed to meet site requirements
1 1

2 stone masonry work in 1:6 c/s mortar


for the base 1 2.40 0.30 0.45 0.32
0.32

3 stone soiling work

1 5.45 0.45 0.1 0.25


in front of main doors
1 1.5 1.5 0.1 0.23
in side ways
1 2 0.6 0.1 0.12

0.59
1:2:4 PCC works
4

1 5.45 0.45 0.08 0.20


in front of main doors
1 1.5 1.5 0.08 0.18
in side way up to main door
1 2 0.6 0.08 0.10

0.47

5 12.5mm thick plaster work in 1:4 c/s mortar

in the front platforms


1 2.8 1.6 4.48
in main doors 1 1.5 1.5 2.25

in side ways upto main doors


1 2 0.6 1.20
in required places
1 5.4 0.15 0.81
for staircase
4 2.8 0.3 3.36
4 2.8 0.15 1.68
13.78
6 3mm cement punning works
in fornt of platfroms 1 2.8 1.6 4.48
in required places 1 5.4 0.15 0.81
for staircase 4 2.8 0.3 3.36
4 2.8 0.15 1.68
10.33
7 Iron work for railings
in front places( 80*40*3.2) tubes 3 3.3 5.5 54.45
verticals 3 0.4 5.5 6.60
in side way in stair case 3 1.8 5.5 29.70
for verticals in stair case 2 1.3 5.5 14.30
105.05
8 Prime coat followed by two coat enamail paintings
in the railings 1 5.1 1 5.10
5.10
9 Prime coat followed by two coat plastict emulsion paintings
in the sides 1 22.85 0.6 13.71
13.71
Plumbing work and maintainance work in the first floor as per the site
10 incharge
1 1.00

Prepared by:- Checked by:- Approved by:-


Gharapjhong Rural Municpality
Office of the Rural Municipal Executive
Jomsom, Mustang
Cost measurement sheet

Project name:- Renovation work in house owned by RM infront of airport


location:- gharapjhong ga.Pa ward no-3
Description Unit Quantity Rate Amount(NRs.) Remarks

Chiselling is required on the existing floor for new leveling,


1 minor maintainance, and ground levelling as needed to meet site job 1.00 2000.00 2000.00
requirements
2 stone masonry work in 1:6 c/s mortar m3 0.32 11722.40 3751.17
3 stone soiling work m3 0.59 2732.40 1612.12
4 1:2:4 PCC works m3 0.47 13643.29 6412.35
5 12.5mm thick plaster work in 1:4 c/s mortar m2 13.78 436.7 6017.73
6 3mm cement punning works m2 10.33 336.19 3472.84
7 Iron work for railings kg 105.05 196.99 20693.80
8 Prime coat followed by two coat enamail paintings m2 5.1 337.5 1721.25
9 Prime coat followed by two coat plastict emulsion paintings m2 13.71 346.46 4749.97
Plumbing work and maintainance work in the first floor as per
10 job 1 4111.84 4111.84
the site incharge
Sub total 54543.06
Vat @ 13% 7090.60
Grand total cost of the project 61633.65
Gharapjhong Rural Municipality
Office of the Rural Municipal Executive
Jomsom, Mustang
Project name:- Renovation work in house owned by RM infront of airport Contract Effective Date: 2080/12/12
Completion Date: 2080/12/30
Name of Contractor: Ritika construction Measurement Date: 2081/01/02

Bill of Contract
As per BOQ Till date Previous bill Current Bill
S. No. Description of Items Unit
Quantity Rate Amount Quantity Amount Quantity Amount Quantity Amount
Chiselling is required on the existing floor for new leveling, minor maintainance, and ground
1 job 1.00 2000.00 2000.00 0.00 2000.00 - 0.00
levelling as needed to meet site requirements - -
2 stone masonry work in 1:6 c/s mortar m3 0.32 11722.40 3751.17 0.32 3751.17 - - 0.32 3,751.17
3 stone soiling work m3 0.59 2732.40 1612.12 0.59 1612.12 - - 0.59 1,612.12
1:2:4 PCC works m3 0.47 13643.29 6412.35 0.00 7363.28 - - 0.00 5,363.28
12.5mm thick plaster work in 1:4 c/s mortar m2 13.78 436.7 6017.73 13.78 957.23 - - 13.78 697.23

3mm cement punning works m2 10.33 336.19 3472.84 10.33 8320.51 -


-
10.33 6,060.51
Iron work for railings kg 105.05 196.99 20693.80 105.05 - - 105.05
Prime coat followed by two coat enamail paintings m2 5.1 337.5 1721.25 5.1 - - 5.1
Prime coat followed by two coat plastict emulsion paintings m2 13.71 346.46 4749.97 13.71 - - 13.71
Plumbing work and maintainance work in the first floor as per the site incharge job 1 4111.84 4111.84 1 - - 1
Sub total 54543.06
vat @ 13% 7090.60
Grand Total 61633.65
Measurement Book
( A.G.O. Form No.171)

Project Name:- Renovation work in house owned by RM infront of airport

Location :- Gharpjhong Ga. Pa. Ward no. 03

Office Name:- Gharapjhong Rural Municipality

Date of Aggrement:- 2080/09/18

Date of Completion :- 2080/10/29

Date of Completed:- 2080/10/29

Date of Measurement:- 2080/11/02

Date of First entry:-

Date of Last entry:-


-
No. of Bill:- Final Bill