Professional Documents
Culture Documents
Hardware Implementation of R-Goose for Wide-Area Protection and Coordination
Hardware Implementation of R-Goose for Wide-Area Protection and Coordination
Hardware Implementation of R-Goose for Wide-Area Protection and Coordination
modern microprocessor based intelligent electronic devices IED Station Bus for GOOSE
to and fro between
Ethernet
(IEDs) equipped with IEC61850 communication capability Breakers
Breaker
Controller
Switch
Substation controller
and bay level IED’s
allows implementation of wide-area protection and coordination
between different substations with the help of virtual local area Substation
Controller
network (VLAN). IEC 61850-90-1/90-5 offers detailed Ethernet
GPS Switch
guidelines on implementing VLAN based communication
between substations that would enable to transmit GOOSE Instrument Merging Ethernet
IED N
messages over WAN. In this paper, the implementation of inter Transformers Unit Switch
IED
substation coordination via routable GOOSE (R-GOOSE) is
Breaker
demonstrated and distance protection with permissive under Breakers
Controller
1
978-1-5386-5583-2/18/$31.00 ©2018University.
Authorized licensed use limited to: Lakehead IEEE Downloaded on February 24,2024 at 13:38:58 UTC from IEEE Xplore. Restrictions apply.
II. R-GOOSE BASICS AND L ABORATORY S ETUP B. Laboratory Setup
A. R-GOOSE Basics As discussed in the earlier section, the lab setup is mainly
based on using a layer-3 router which is configured with
IEC 61850-8-1 defines GOOSE as a multicast message VLAN and specific VLAN Id’s are assigned to substation
that is intended to be used only within a substation and does level switches. Below are the steps followed during the lab
not provide any structural recommendations to transmit over setup.
a wide-area network. In network topology terms, GOOSE is
1) Fig. 3 provides a detailed overview of lab setup for the
a layer-2 messaging service and to transmit this over WAN,
proposed configuration. Here, DOBLE F6150SV
layer-3 routers are required to be used and configured with
simulator is sued to provide voltage and current
specific VLAN Id’s to the ethernet ports [8]. This paper uses
measurements to the relays. SEL 411L relays are
the methodology of utilizing VLAN capabilities and layer-3
configured to publish and subscribe the GOOSE
router to route the GOOSE over wide-area network. The
messages. Rugged-com layer 2 switches (RSG2100)
router converts the GOOSE into a routable IP packets and
are used to create two different networks that represent
transports to the destination address. IEC61850-90-5, which
two substations. Finally, CISCO SG300-28 layer-3
was released in 2011, offers additional support in terms of
router is used to configure the VLAN and acts as
higher security, ability to send synchrophasor data, and a
medium to route/allow the GOOSE packets between
defined encryption apart from layer-3 routing into WAN [9].
The advantage of choosing VLAN is that the central the substations.
application server can listen to specific GOOSE packet based
on the VLAN identification, this would reduce the network
traffic as GOOSE message are multicast services and there is R-GOOSE R-GOOSE
no need of controller/relay to subscribe to every GOOSE CISCO SG 300-28 Layer 3 Router
Substation 1 Substation 2
message. Therefore, it is helpful to put GOOSE messages
into controllable network segments through the use of
VLANs. This creates multiple logical LANs that selectively LAN A LAN B
DOBLE
VLAN Between F6150SV
Substations Control
Center
IP Communication
Substation 3...n Fig. 3. Laboratory Setup at Michigan Tech to demonstrate the application
GOOSE Messages
using R-GOOSE.
2
Authorized licensed use limited to: Lakehead University. Downloaded on February 24,2024 at 13:38:58 UTC from IEEE Xplore. Restrictions apply.
setup sends digital inputs between the substations, which
certifies the setup is working without data loss.
In this case, substation A sends a breaker close latch to
substation B. Once the close acknowledgement is received
from substation B, then Breaker A is closed. There is a
delay of 10 ms on breaker A, which is configured to make
sure that the breaker A should wait for acknowledgement
from Breaker B. As per [7], this operation should be
performed within 100 ms, and with the proposed setup the
operation is performed within 4ms.
B. Distance Protection with PUTT
In order to reduce the fault clearing time, it is imperative
Fig. 4. Layer 3 Router configuration to allow Specific VLAN Id.
to isolate the faulty line completely from the system. When
there is a fault on the transmission line, it is not enough just
to trip the breaker at local end of the line but to trip the
breaker at remote end of the line. In distance protection,
accelerated transfer trip schemes such as permissive under
reaching transfer trip (PUTT) and permissive over reaching
transfer trips (POTT) are implemented using a dedicated
communication channel such as power line carrier
communication (PLCC). The use of these schemes is to
achieve the shortest fault clearing time. However, in order to
minimize the fault isolation time, we are adopting IEC
61850 based R-GOOSE [14].
PUTT scheme is the one when a Zone-1 element of the local
Fig. 5. Rugged-com switch configuration for VLAN.
distance relay picks up because of the fault, the trip signal
will be communicated to the remote end. This trip signal is
further validated with the Zone-2 pick-up of the remote end
III. A PPLICATIONS OF R-GOOSE
distance relay as shown in Fig 7. When the both the values
A. Interlocking are true, the breaker at the remote end of the line will be
Interlocking is a method of closing breakers at two ends of tripped. POTT scheme is similar to PUTT scheme except that
a transmission line, which is performed after synchronization it uses the overreaching Zone-2 element of the distance relay
check. This process requires an acknowledge from the remote for Transfer Trip. Further, in POTT scheme there is a need if
end breaker, before closing the local breaker. In this paper, directional relay to confirm the relay only trips for the faults
the basic interlocking scheme is explored and it assumes that when it is within its protected zone.
synchronization check was already performed and also a logic
for interlocking is designed as per [7]. Fig. 6 presents the basic
Trip signal to
schematic that was simulated on the lab setup. Remote end
Zone 1
Substation_A Substation_B
Bus_A Breaker_A Bus_B
Breaker_B
Zone 2 Delay for Zone 2
Trip
GOOSE_LAN_A Layer 3 Router GOOSE_LAN_B breaker
RSG 2100 Cisco SG300-28 RSG 2100
Close_A Tx Tx Zone 3 Delay for Zone 3
Rx Rx
Fig. 6. Interlocking schematic. In the lab setup as discussed in Fig 8, a PUTT scheme has
been implemented using two SEL 411L distance relays and
The main goal of this case study is to ensure that the R-GOOSE. For each relay, functionally constrained data
communication link between two substations is up and this attribute of PDIS nodes (dedicated logical nodes for distance
3
Authorized licensed use limited to: Lakehead University. Downloaded on February 24,2024 at 13:38:58 UTC from IEEE Xplore. Restrictions apply.
protection) were used in the R-GOOSE messages sent to the
remote end substation. The R-GOOSE in this case provides a
faster communication passage as the bandwidth of the
communication channel is much higher than a PLCC (100
Mpbs vs 112 kpbs). In addition, as the GOOSE messages
will be sent through a different VLAN the communication
inherently much secure than a PLCC [1]. Because of the
multicast nature of the GOOSE signal, it makes the
communication channel much more reliable. The reliability
can be further improved by using redundant communication
channels. [12] provides a basic implementation of GOOSE
based distance protection, where as in this paper we have
studied distance protection with R-GOOSE in a
inter-substation setup.
4
Authorized licensed use limited to: Lakehead University. Downloaded on February 24,2024 at 13:38:58 UTC from IEEE Xplore. Restrictions apply.
[4] IEC standard for Communication Networks and Systems in Substations, over wan.” In Proceedings of the International Conference on Wireless
Part 5: Communication Requirements for Functions and Device Models, Networks (ICWN) (p. 1). The Steering Committee of The World Congress
IEC 61850-5, Jul. 2003. in Computer Science, Computer Engineering and Applied Computing
[5] IEC standard for Communication networks and systems for power utility (WorldComp).
automation - Part 8-1: Specific communication service mapping (SCSM) - [11] IEC standard for Communication networks and systems for power utility
Mappings to MMS (ISO 9506-1 and ISO 9506-2) and to ISO/IEC 8802-3, automation - Part 7-4: Basic communication structure - Compatible
IEC 61850-8-1, Jul. 2011. logical node classes and data object classes, IEC 61850-7-4, Jul. 2010.
[6] IEC standard for Communication networks and systems for power utility [12] B. Falahati, Z. Darabi and M. Vakilian, “Implementing distance line
automation - Part 9-2: Specific communication service mapping (SCSM) protection schemes among IEC61850-enabled substations,” 2014 IEEE
- Sampled values over ISO/IEC 8802-3. IEC61850-9-2, Jul. 2011. PES TD Conference and Exposition, Chicago, IL, USA, 2014, pp. 1-5.
[7] IEC standard for Communication networks and systems for power utility doi: 10.1109/TDC.2014.6863322
automation - Part 90-1: Use of IEC 61850 for the communication between [13] V.Skendzic, I.Ender, G.Zweigle, “IEC 61850-9-2 process bus and its
substations, IEC 61850-90-1, Jul. 2010. impact on power system protection and control reliability.” In proceedings
[8] IEC standard for Communication networks and systems for power utility of the 9th Annual Western Power Delivery Automation Conference, 2007,
automation - Part 90-4: Network engineering guidelines, IEC 61850-90- April, Spokane, WA.
4, Jul. 2013. [14] A. Apostolov, “Impact of IEC 61850 on the interoperability and
[9] IEC standard for Communication networks and systems for power utility reliability of protection schemes,” 2013 IEEE Power Energy
automation - Part 90-5: Use of IEC 61850 to transmit synchrophasor Society General Meeting, Vancouver, BC, 2013, pp.1-5. doi:
information according to IEEE C37.118, IEC 61850-90-5, Jul. 2012. 10.1109/PESMG.2013.6673051
[10] C. H. R.de Oliveira, & A. P. Bowen, “ Iec 61850 goose message
5
Authorized licensed use limited to: Lakehead University. Downloaded on February 24,2024 at 13:38:58 UTC from IEEE Xplore. Restrictions apply.