PROJECT: WEST SUPERBLOCK - THE SUITES

LOCATION: 28TH ST.COR. 3RD & 5TH AVENUE, CRESCENT PARK, BGC TAGUIG
P.O. NO.: 5200001056

ACTIVITY ID ACTIVITY DESCRIPTION ORIG DUR EARLY START EARLY FINISH


NOTICE TO PROCEED
1.O Notice to Proceed
1.1 Receipt of Notice to Proceed 123 26-Jul-18 26-Nov-18
BONDS & INSURANCES
2.0 Bonds & Insurances
2.1 Secure Bonds & Insurances 7
SITE MOBILIZATION
3.0 Site Mobilization
3.1 Preparation of Temfacil 10 8/13/2018 8/22/2018
3.2 Site Verification 10 8/13/2018 8/22/2018
3.3 Secure of Permits 10 8/13/2018 8/22/2018
TECHNICAL SUBMITTALS
5.0 Technical Submittals 7 8/8/2018 8/15/2018
5.1 CEILING METAL FRAMING 7 8/8/2018 8/15/2018
5.2 CEILING BOARDS - GYPSUM BOARD 7 8/8/2018 8/15/2018
5.3 CEILING BOARDS - MOISTURE RESISTANT BOARD 7 8/8/2018 8/15/2018
5.4 TILE ADHESIVE 7 8/8/2018 8/15/2018
5.5 CEMENT 7 8/8/2018 8/15/2018
5.6 SKIMCOAT 7 8/8/2018 8/15/2018
5.7 WATERPROOF 7 8/8/2018 8/15/2018
5.8 PAINT (CEILING) 7 8/8/2018 8/15/2018
5.9 PAINT (DOOR) 7 8/8/2018 8/15/2018
5.10 PAINT(WALL) 7 8/8/2018 8/15/2018
5.11 HIGH PRESSURE LAMINATE 7 8/8/2018 8/15/2018
5.12 WOOD LAMINATE (lavatory countertop) 7 8/8/2018 8/15/2018
5.13 DRYWALL METAL FRAMING 7 8/8/2018 8/15/2018
5.14 DRYWALL BOARDS 7 8/8/2018 8/15/2018
5.15 ALUMINUM (SHADOW GAP) 7 8/8/2018 8/15/2018
5.16 STAINLESS STEEL SHEET 7 8/8/2018 8/15/2018
5.17 LAMINATED MFC (RECEPTION COUNTER) 7 8/8/2018 8/15/2018
5.18 SOLID SURFACE (RECEPTION COUNTER) 7 8/8/2018 8/15/2018
5.19 CARCASS (RECEPTION COUNTER) 7 8/8/2018 8/15/2018
5.20 FRAMING (RECEPTION COUNTER) 7 8/8/2018 8/15/2018
5.21 SOLID WOOD ACCENT WALL 7 8/8/2018 8/15/2018
5.22 FACIAL MIRROR 7 8/8/2018 8/15/2018
5.23 GLASS SEALANT 7 8/8/2018 8/15/2018
5.24 GLASS RAILING 7 8/8/2018 8/15/2018
5.25 DOORS 7 8/8/2018 8/15/2018
5.26 DOORS HARDWARES (HINGES, LOCKSET, CLOSER) 7 8/8/2018 8/15/2018
5.27 GRAPHICOTE 7 8/8/2018 8/15/2018
5.28 LAMITAK 7 8/8/2018 8/15/2018
5.29 VENEER 7 8/8/2018 8/15/2018
MATERIAL PROCUREMENT, SITE DELIVERIES & HAULING ACTIVITIES
6.0 BASEMENT
6.0.1 MATERIAL PROCUREMENT
6.0.1.1 TILES (TO WALL) OSM
6.0.1.2 CEILINGS GYPSUM BOARD 14 13-Aug-18 26-Aug-18
6.0.1.3 CEILINGS COVELIGHT 14 23-Aug-18 5-Sep-18
6.0.1.4 CEILINGS SHADOW GAP 14 23-Aug-18 5-Sep-18
6.0.1.5 CEILINGS DROP WALL 14 23-Aug-18 5-Sep-18
6.0.1.6 PAINTINGS & COATINGS 7 30-Aug-18 5-Sep-18
6.0.1.7 ALUMINUM 14 10-Sep-18 23-Sep-18
6.0.1.8 WOOD LAMINATE 14 18-Sep-18 1-Oct-18
6.0.1.9 STAINLESS STEEL SHEET 14 18-Sep-18 1-Oct-18
6.0.1.10 ELEVATOR THRESHOLD 14 18-Sep-18 1-Oct-18
6.0.1.11 TILES (TO FLOOR) OSM
6.0.1.12 DOORS 14 2-Oct-18 15-Oct-18
6.0.2 SITE DELIVERY
6.0.2.1 TILES (TO WALL) OSM

Page 1of 5
PROJECT: WEST SUPERBLOCK - THE SUITES
LOCATION: 28TH ST.COR. 3RD & 5TH AVENUE, CRESCENT PARK, BGC TAGUIG
P.O. NO.: 5200001056

ACTIVITY ID ACTIVITY DESCRIPTION ORIG DUR EARLY START EARLY FINISH


6.0.2.2 CEILINGS GYPSUM BOARD 3 27-Aug-18 29-Aug-18
6.0.2.3 CEILINGS COVELIGHT 3 6-Sep-18 8-Sep-18
6.0.2.4 CEILINGS SHADOW GAP 3 6-Sep-18 8-Sep-18
6.0.2.5 CEILINGS DROP WALL 3 6-Sep-18 8-Sep-18
6.0.2.6 PAINTINGS & COATINGS 3 6-Sep-18 8-Sep-18
6.0.2.7 ALUMINUM 3 24-Sep-18 26-Sep-18
6.0.2.8 WOOD LAMINATE 3 2-Oct-18 4-Oct-18
6.0.2.9 STAINLESS STEEL SHEET 3 2-Oct-18 4-Oct-18
6.0.2.10 ELEVATOR THRESHOLD 3 2-Oct-18 4-Oct-18
6.0.2.11 TILES (TO FLOOR) OSM
6.0.2.12 DOORS 3 16-Oct-18 18-Oct-18
6.0.3 HAULING & SEGREGATION
6.0.3.1 TILES (TO WALL) 18 30-Aug-18 17-Sep-18
6.0.3.2 CEILINGS GYPSUM BOARD 14 9-Sep-18 23-Sep-18
6.0.3.3 CEILINGS COVELIGHT 3 9-Sep-18 12-Sep-18
6.0.3.4 CEILINGS SHADOW GAP 7 9-Sep-18 16-Sep-18
6.0.3.5 CEILINGS DROP WALL 1 9-Sep-18 10-Sep-18
6.0.3.6 PAINTINGS & COATINGS 10 27-Sep-18 7-Oct-18
6.0.3.7 ALUMINUM 7 5-Oct-18 12-Oct-18
6.0.3.8 WOOD LAMINATE 12 5-Oct-18 17-Oct-18
6.0.3.9 STAINLESS STEEL SHEET 2 5-Oct-18 7-Oct-18
6.0.3.10 ELEVATOR THRESHOLD 6 5-Oct-18 11-Oct-18
6.0.3.11 TILES (TO FLOOR) 16 19-Oct-18 4-Nov-18
6.0.3.12 DOORS 6 19-Oct-18 25-Oct-18
6.1 UPPER & LOWER GROUND LOBBY
6.1.1 MATERIAL PROCUREMENT
6.1.1.1 TILES (TO WALL) OSM
6.1.1.2 RUBBED CONCRETE & SKIMCOAT 7 16-Aug-18 22-Aug-18
6.1.1.3 SCULPTURAL WALL 10 13-Aug-18 22-Aug-18
6.1.1.4 DRYWALL 10 13-Aug-18 22-Aug-18
6.1.1.5 WATERPROOFING 7 16-Aug-18 22-Aug-18
6.1.1.6 DRYPACK FOR TILES 7 16-Aug-18 22-Aug-18
6.1.1.7 CEILINGS GYPSUM BOARD 14 19-Aug-18 1-Sep-18
6.1.1.8 CEILINGS COVELIGHT 14 19-Aug-18 1-Sep-18
6.1.1.9 CEILINGS SHADOW GAP 14 19-Aug-18 1-Sep-18
6.1.1.10 CEILINGS MOISTURE RESISTANT BOARD 14 19-Aug-18 1-Sep-18
6.1.1.11 PAINTINGS & COATINGS 7 26-Aug-18 1-Sep-18
6.1.1.12 WOOD LAMINATE 14 6-Sep-18 19-Sep-18
6.1.1.13 STAINLESS STEEL SHEET 14 14-Sep-18 27-Sep-18
6.1.1.14 VENEER 14 14-Sep-18 27-Sep-18
6.1.1.15 RECEPTION COUNTER 14 14-Sep-18 27-Sep-18
6.1.1.16 COUNTERTOP 14 14-Sep-18 27-Sep-18
6.1.1.17 HIGH PRESSURE LAMINATE 14 14-Sep-18 27-Sep-18
6.1.1.18 ACCENT WALL 14 14-Sep-18 27-Sep-18
6.1.1.19 GRAPHICOTE 14 14-Sep-18 27-Sep-18
6.1.1.20 FACIAL MIRROR 14 14-Sep-18 27-Sep-18
6.1.1.21 ELEVATOR JAMB 14 14-Sep-18 27-Sep-18
6.1.1.22 TILES (TO FLOOR) OSM
6.1.1.23 TILES (COUNTER) OSM
6.1.1.24 DOORS 14 14-Sep-18 27-Sep-18
6.1.1.25 BASEBOARD OSM
6.1.1.26 GLASS RAILING 14 28-Sep-18 11-Oct-18
6.1.1.27 ALUMINUM SHADOW GAP 14 28-Sep-18 11-Oct-18
6.1.1.28 TOILET/PANTRY FIXTURES & ACCESSORIES OSM
6.1.1.29 CARPET OSM
6.1.2 SITE DELIVERY
6.1.2.1 TILES (TO WALL) OSM
6.1.2.2 RUBBED CONCRETE & SKIMCOAT 3 22-Aug-18 24-Aug-18
6.1.2.3 SCULPTURAL WALL 3 22-Aug-18 24-Aug-18

Page 2of 5
PROJECT: WEST SUPERBLOCK - THE SUITES
LOCATION: 28TH ST.COR. 3RD & 5TH AVENUE, CRESCENT PARK, BGC TAGUIG
P.O. NO.: 5200001056

ACTIVITY ID ACTIVITY DESCRIPTION ORIG DUR EARLY START EARLY FINISH


6.1.2.4 DRYWALL 3 22-Aug-18 24-Aug-18
6.1.2.5 WATERPROOFING 3 22-Aug-18 24-Aug-18
6.1.2.6 DRYPACK FOR TILES 3 22-Aug-18 24-Aug-18
6.1.2.7 CEILINGS GYPSUM BOARD 3 1-Sep-18 3-Sep-18
6.1.2.8 CEILINGS COVELIGHT 3 1-Sep-18 3-Sep-18
6.1.2.9 CEILINGS SHADOW GAP 3 1-Sep-18 3-Sep-18
6.1.2.10 CEILINGS MOISTURE RESISTANT BOARD 3 1-Sep-18 3-Sep-18
6.1.2.11 PAINTINGS & COATINGS 3 1-Sep-18 3-Sep-18
6.1.2.12 WOOD LAMINATE 3 19-Sep-18 21-Sep-18
6.1.2.13 STAINLESS STEEL SHEET 3 27-Sep-18 29-Sep-18
6.1.2.14 VENEER 3 27-Sep-18 29-Sep-18
6.1.2.15 RECEPTION COUNTER 3 27-Sep-18 29-Sep-18
6.1.2.16 COUNTERTOP 3 27-Sep-18 29-Sep-18
6.1.2.17 HIGH PRESSURE LAMINATE 3 27-Sep-18 29-Sep-18
6.1.2.18 ACCENT WALL 3 27-Sep-18 29-Sep-18
6.1.2.19 GRAPHICOTE 3 27-Sep-18 29-Sep-18
6.1.2.20 FACIAL MIRROR 3 27-Sep-18 29-Sep-18
6.1.2.21 ELEVATOR JAMB 3 27-Sep-18 29-Sep-18
6.1.2.22 TILES (TO FLOOR) OSM
6.1.2.23 TILES (COUNTER) OSM
6.1.2.24 DOORS 3 27-Sep-18 29-Sep-18
6.1.2.25 BASEBOARD OSM
6.1.2.26 GLASS RAILING 3 11-Oct-18 13-Oct-18
6.1.2.27 ALUMINUM SHADOW GAP 3 11-Oct-18 13-Oct-18
6.1.2.28 TOILET/PANTRY FIXTURES & ACCESSORIES OSM
6.1.2.29 CARPET OSM
6.1.3 HAULING & SEGREGATION
6.1.3.1 TILES (TO WALL) 18 25-Aug-18 11-Sep-18
6.1.3.2 RUBBED CONCRETE & SKIMCOAT 6 25-Aug-18 30-Aug-18
6.1.3.3 SCULPTURAL WALL 16 25-Aug-18 9-Sep-18
6.1.3.4 DRYWALL 3 25-Aug-18 27-Aug-18
6.1.3.5 WATERPROOFING 1 25-Aug-18 25-Aug-18
6.1.3.6 DRYPACK FOR TILES 7 25-Aug-18 31-Aug-18
6.1.3.7 CEILINGS GYPSUM BOARD 14 4-Sep-18 17-Sep-18
6.1.3.8 CEILINGS COVELIGHT 3 4-Sep-18 6-Sep-18
6.1.3.9 CEILINGS SHADOW GAP 7 4-Sep-18 10-Sep-18
6.1.3.10 CEILINGS MOISTURE RESISTANT BOARD 1 4-Sep-18 4-Sep-18
6.1.3.11 PAINTINGS & COATINGS 5 4-Sep-18 8-Sep-18
6.1.3.12 WOOD LAMINATE 6 22-Sep-18 27-Sep-18
6.1.3.13 STAINLESS STEEL SHEET 2 30-Sep-18 1-Oct-18
6.1.3.14 VENEER 5 30-Sep-18 4-Oct-18
6.1.3.15 RECEPTION COUNTER 6 30-Sep-18 5-Oct-18
6.1.3.16 COUNTERTOP 2 30-Sep-18 1-Oct-18
6.1.3.17 HIGH PRESSURE LAMINATE 3 30-Sep-18 2-Oct-18
6.1.3.18 ACCENT WALL 1 30-Sep-18 30-Sep-18
6.1.3.19 GRAPHICOTE 7 30-Sep-18 6-Oct-18
6.1.3.20 FACIAL MIRROR 1 30-Sep-18 30-Sep-18
6.1.3.21 ELEVATOR JAMB 2 30-Sep-18 1-Oct-18
6.1.3.22 TILES (TO FLOOR) 16 30-Sep-18 15-Oct-18
6.1.3.23 TILES (COUNTER) 1 30-Sep-18 30-Sep-18
6.1.3.24 DOORS 6 30-Sep-18 5-Oct-18
6.1.3.25 BASEBOARD 7 14-Oct-18 20-Oct-18
6.1.3.26 GLASS RAILING 2 14-Oct-18 15-Oct-18
6.1.3.27 ALUMINUM SHADOW GAP 4 14-Oct-18 17-Oct-18
6.1.3.28 TOILET/PANTRY FIXTURES & ACCESSORIES 4 24-Oct-18 27-Oct-18
6.1.3.29 CARPET 5 28-Oct-18 1-Nov-18
SITE WORKS
7.0 SITE WORKS

Page 3of 5
PROJECT: WEST SUPERBLOCK - THE SUITES
LOCATION: 28TH ST.COR. 3RD & 5TH AVENUE, CRESCENT PARK, BGC TAGUIG
P.O. NO.: 5200001056

ACTIVITY ID ACTIVITY DESCRIPTION ORIG DUR EARLY START EARLY FINISH


7.0.1 TILES (TO WALL) 18 30-Aug-18 17-Sep-18
7.0.2 RUBBED CONCRETE & SKIMCOAT 6 30-Aug-18 5-Sep-18
7.0.3 SCULPTURAL WALL 16 30-Aug-18 15-Sep-18
7.0.4 DRYWALL 3 30-Aug-18 2-Sep-18
7.0.5 WATERPROOFING 2 30-Aug-18 1-Sep-18
7.0.6 DRYPACK FOR TILES 15 30-Aug-18 14-Sep-18
7.0.7 CEILINGS GYPSUM BOARD 14 9-Sep-18 23-Sep-18
7.0.8 CEILINGS COVELIGHT 3 9-Sep-18 12-Sep-18
7.0.9 CEILINGS SHADOW GAP 7 9-Sep-18 16-Sep-18
7.0.10 CEILINGS DROP WALL 1 9-Sep-18 10-Sep-18
7.0.11 CEILINGS MOISTURE RESISTANT BOARD 2 9-Sep-18 11-Sep-18
7.0.12 PAINTINGS & COATINGS 10 27-Sep-18 7-Oct-18
7.0.13 ALUMINUM 7 5-Oct-18 12-Oct-18
7.0.14 WOOD LAMINATE 12 5-Oct-18 17-Oct-18
7.0.15 STAINLESS STEEL SHEET 2 5-Oct-18 7-Oct-18
7.0.16 ELEVATOR THRESHOLD 6 5-Oct-18 11-Oct-18
7.0.17 VENEER 10 5-Oct-18 15-Oct-18
7.0.18 RECEPTION COUNTER 6 5-Oct-18 11-Oct-18
7.0.19 COUNTERTOP 1 5-Oct-18 6-Oct-18
7.0.20 HIGH PRESSURE LAMINATE 3 5-Oct-18 8-Oct-18
7.0.21 ACCENT WALL 1 5-Oct-18 6-Oct-18
7.0.22 GRAPHICOTE 13 5-Oct-18 18-Oct-18
7.0.23 FACIAL MIRROR 1 5-Oct-18 6-Oct-18
7.0.24 ELEVATOR JAMB 2 5-Oct-18 7-Oct-18
7.0.25 TILES (TO FLOOR) 16 19-Oct-18 4-Nov-18
7.0.26 TILES (COUNTER) 1 19-Oct-18 20-Oct-18
7.0.27 DOORS 6 19-Oct-18 25-Oct-18
7.0.28 BASEBOARD 7 29-Oct-18 5-Nov-18
7.0.29 GLASS RAILING 2 2-Nov-18 4-Nov-18
7.0.30 ALUMINUM SHADOW GAP 4 2-Nov-18 6-Nov-18
7.0.31 TOILET/PANTRY FIXTURES & ACCESSORIES 6 2-Nov-18 8-Nov-18
7.0.32 CARPET 5 4-Nov-18 9-Nov-18
PUNCHLIST / RECTIFICATION
8.0 Punchlist / Rectification
8.1 TILES (TO WALL) 7 6-Sep-18 12-Sep-18
8.2 RUBBED CONCRETE & SKIMCOAT 7 6-Sep-18 12-Sep-18
8.3 SCULPTURAL WALL 7 6-Sep-18 12-Sep-18
8.4 DRYWALL 7 6-Sep-18 12-Sep-18
8.5 WATERPROOFING 7 6-Sep-18 12-Sep-18
8.6 DRYPACK FOR TILES 7 6-Sep-18 12-Sep-18
8.7 CEILINGS GYPSUM BOARD 7 16-Sep-18 22-Sep-18
8.8 CEILINGS COVELIGHT 7 16-Sep-18 22-Sep-18
8.9 CEILINGS SHADOW GAP 7 16-Sep-18 22-Sep-18
8.10 CEILINGS DROP WALL 7 16-Sep-18 22-Sep-18
8.11 CEILINGS MOISTURE RESISTANT BOARD 7 16-Sep-18 22-Sep-18
8.12 PAINTINGS & COATINGS 7 4-Oct-18 10-Oct-18
8.13 ALUMINUM 7 12-Oct-18 18-Oct-18
8.14 WOOD LAMINATE 7 12-Oct-18 18-Oct-18
8.15 STAINLESS STEEL SHEET 7 12-Oct-18 18-Oct-18
8.16 ELEVATOR THRESHOLD 7 12-Oct-18 18-Oct-18
8.17 VENEER 7 12-Oct-18 18-Oct-18
8.18 RECEPTION COUNTER 7 12-Oct-18 18-Oct-18
8.19 COUNTERTOP 7 12-Oct-18 18-Oct-18
8.20 HIGH PRESSURE LAMINATE 7 12-Oct-18 18-Oct-18
8.21 ACCENT WALL 7 12-Oct-18 18-Oct-18
8.22 GRAPHICOTE 7 12-Oct-18 18-Oct-18
8.23 FACIAL MIRROR 7 12-Oct-18 18-Oct-18
8.24 ELEVATOR JAMB 7 12-Oct-18 18-Oct-18

Page 4of 5
PROJECT: WEST SUPERBLOCK - THE SUITES
LOCATION: 28TH ST.COR. 3RD & 5TH AVENUE, CRESCENT PARK, BGC TAGUIG
P.O. NO.: 5200001056

ACTIVITY ID ACTIVITY DESCRIPTION ORIG DUR EARLY START EARLY FINISH


8.25 TILES (TO FLOOR) 7 26-Oct-18 1-Nov-18
8.26 TILES (COUNTER) 7 26-Oct-18 1-Nov-18
8.27 DOORS 7 26-Oct-18 1-Nov-18
8.28 BASEBOARD 7 5-Nov-18 11-Nov-18
8.29 GLASS RAILING 7 9-Nov-18 15-Nov-18
8.30 ALUMINUM SHADOW GAP 7 9-Nov-18 15-Nov-18
8.31 TOILET/PANTRY FIXTURES & ACCESSORIES 7 9-Nov-18 15-Nov-18
8.32 CARPET 7 11-Nov-18 17-Nov-18
CLOSED DOCUMENTS
9.0 Closed Out Documents
9.1 As Built Plans 20 3-Nov-18 23-Nov-18
Warranty 14 3-Nov-18 16-Nov-18
HANDOVER
10.0 Handover
10.1 Handover & Turnover 7 24-Nov-18 30-Nov-18

Prepared By:

Roselle Jo Mae D. Utalia


PROJECT-IN-CHARGE

Page 5of 5