Professional Documents
Culture Documents
EEMUA 147 Recommendations for refrigerated liquefied storage tanks.
EEMUA 147 Recommendations for refrigerated liquefied storage tanks.
PUBLICATION 147
Edition 3
Publication 147
Edition 3
EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association
Recommendations for refigerated liquefied gas storage tanks Publication147
II EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association
Publication147 Recommendations for refigerated liquefied gas storage tanks
EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association III
Recommendations for refigerated liquefied gas storage tanks Publication147
Contents
Preface ................................................................................................................................................................... IX
1. Introduction .......................................................................................................................................................1
IV EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association
Publication147 Recommendations for refigerated liquefied gas storage tanks
4.1 General.............................................................................................................................................................................................................. 21
4.2 Inner tank testing ........................................................................................................................................................................................ 21
4.3 Testing of outer steel tanks of double and full containment ............................................................................................ 21
4.4 Filling rates and level checks ................................................................................................................................................................ 21
4.5 Outer concrete tank testing.................................................................................................................................................................. 21
4.6 Pneumatic testing ...................................................................................................................................................................................... 21
EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association V
Recommendations for refigerated liquefied gas storage tanks Publication147
6. Operations ....................................................................................................................................................... 29
VI EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association
Publication147 Recommendations for refigerated liquefied gas storage tanks
8. De-commissioning .......................................................................................................................................... 42
References ............................................................................................................................................................ 50
EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association VII
Recommendations for refigerated liquefied gas storage tanks Publication147
List of Figures
Figure 1 Scheme of tank categories for Refrigerated Liquefied Gas products ........................................................................... 3
Figure 2 Scheme of tank categories for RLG products (cont.) ............................................................................................................. 4
Figure 3 Scheme of tank types for RLG products (cont.) ........................................................................................................................ 5
Figure 4 Detail of a Type 2 above ground single containment storage tank.............................................................................. 6
Figure 5 Detail of a Type 3 above ground double containment storage tank ........................................................................... 6
Figure 6 Detail of a Type 4 above ground full containment storage tank .................................................................................... 7
Figure 7 Detail of a Type 5/Type 8 above ground full containment storage tank ................................................................... 7
Figure 8 Detail of a Type 6/Type 7 above ground full containment storage tank ................................................................... 8
Figure 9 Typical detail of a Type 1 above ground membrane storage tank ................................................................................ 8
Figure 10 Typical detail of a Type 11 in-ground membrane tank...................................................................................................... 9
Figure 11 Artist impression of a double concrete tank with no liner ........................................................................................... 10
Figure 12 Selection diagram refrigerated storage systems ................................................................................................................ 11
Figure 13 LNG tank designed and constructed to best practice principle ................................................................................ 15
Figure 14 Supported concrete foundation slab........................................................................................................................................ 15
Figure 15 Concrete foundation slab elevated from ground .............................................................................................................. 16
Figure 16 Arrangement of pressure control valves to flare ................................................................................................................ 17
Figure 17 Prevention of an overfill.................................................................................................................................................................... 19
Figure 18 Floating of the inner tank ................................................................................................................................................................ 30
Figure 19 Typical example of condensation in dome roof for butane gas ............................................................................... 31
List of Tables
VIII EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association
Publication147 Recommendations for refigerated liquefied gas storage tanks
Preface
EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association IX
Recommendations for refigerated liquefied gas storage tanks Publication147
X EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association
Publication147 Recommendations for refigerated liquefied gas storage tanks
1. Introduction
Boil-off
Boil-off is the process of vaporisation of very small
quantities of refrigerated liquid by heat conducted
through the insulation surrounding the storage
tank.
Embankment
A bank of selected earth and other materials placed
against the outer face of a reinforced concrete tank
or high wall.
EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association 1
Recommendations for refigerated liquefied gas storage tanks Publication147
The first Edition of this Publication described the The outer tank will not be designed to contain
world s first categorisation of storage tanks suitable vapour released due to product leakage from the
for storing refrigerated or cryogenic liquefied inner tank (See Figures 1 and 5).
gases. The second Edition further develops this
concept by introducing tank Type/Classes based 2.1.3 Full containment
on a safety evaluation. The smaller the risk during
an incident the higher the classification, i.e. Class A double wall tank designed and constructed
B represents higher risk compared to Class A. so that both inner and outer tanks are capable
Storage categories and classifications are defined of containing the refrigerated liquid stored. The
in this Chapter. outer wall is located at approximately 1 to 2 metres
distance from the inner wall (See Figures 2 and
6 ‒ 8).
2.1 Definitions of containments
The inner tank stores the refrigerated liquid under
2.1.1 Single containment
normal operating conditions. The outer roof is
supported by the outer wall.
Either a single or double wall tank designed and
constructed so that only the containing element in
The outer tank is capable of containing the
contact with the refrigerated product is required to
refrigerated liquid and vapour resulting from
meet the low temperature ductility requirements
product leakage from the inner tank.
for storage of the product. The outer wall (if any)
of a single containment storage system is primarily
This category can be sub-divided into different
for the retention and protection of insulation and
classes:
is not designed to contain liquid in the event of
product leakage from the inner container.
• Class A(1): A full containment tank where
the outer metal or concrete container/
A single containment tank will be surrounded by a
component may not be able to resist
traditional bund wall to contain any leakage (See
accidental loads from outside;
Figures 1 and 4).
• Class A(2): As Class A(1), but the inner tank
2.1.2 Double containment is constructed as a pre-stressed concrete
container, without a metal liner;
A double wall tank designed and constructed • Class B(1): A full containment tank where
so that both inner and outer walls are capable the outer concrete container is designed and
of containing the refrigerated liquid stored. To constructed to resist all accidental loads from
minimise the pool of escaping liquid the outer outside, such as: impacts from explosions,
wall should generally be located at a distance not flying objects, acts of sabotage or fires and
exceeding 6 metres from the inner wall. The inner the inner tank is ‒ under normal operation ‒
tank stores the refrigerated liquid under normal a liquid tight container; and
operating conditions. The outer tank contains the • Class B(2): As class B(1) but ‒ but the inner
refrigerated liquid product leakage from the inner tank is constructed as a pre-stressed concrete
tank. container, without a metal liner.
2 EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association
Publication147 Recommendations for refigerated liquefied gas storage tanks
The following Figures give an indication of the The membrane is in turn welded to a carbon steel
available and developed tank categories. Types 1 liner on the inside of the dome roof. There are
and 2 correspond to single containment and Type both in-ground and above ground membrane
3 for double containment. Full containment is tanks. (See Figure 3 and 9 ‒ 10).
further divided into two Classes and then Types 4
to 11. Note that Type 11 is an in-ground type that Most approval Authorities consider the above
has been primarily used in Japan. ground membrane tanks as equivalent to full
containment tanks. However, other Authorities
2.1.4 Membrane tanks may instead treat them as single containment
tanks and may impose the addition of a bund wall.
Membrane tanks consist of a single wall pre-
stressed concrete tank that is lined with a stainless Membrane tanks are sometimes referred to as total
steel membrane which is both liquid and gas tight. integrity tanks.
RLG
Tanks
* Including half in-ground Tanks
EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association 3
Recommendations for refigerated liquefied gas storage tanks Publication147
Full
containment Tanks
Reinforced
concrete Outer Roof
4 EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association
Publication147 Recommendations for refigerated liquefied gas storage tanks
RLG
Tanks
Membrane Tanks
Type 1 Type 11
Stainless Steel Stainless Steel
membrane and membrane and
pre-stressed concrete concrete tank
Membrane/ Membrane/
insulation/pre-stressed insulation/
concrete Outer concrete Outer
Tank Shell Tank Shell
- Ground
EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association 5
Recommendations for refigerated liquefied gas storage tanks Publication147
CS Roof
AL Suspended Deck
Fibreglass Blanket
Perlite Powder
CS Outer Tank
Bund Wall
9% Ni Inner Tank
Heater
Foamglass Insulation
Figure 4 Typical detail of a Type 2 above ground single containment storage tank
CS Roof
AL Suspended Deck
Fibreglass Blanket
Weather Shield
Perlite Powder
PC High Dyke
CS Outer Tank
9% Ni Inner Tank
9% Ni
Secondary
Barrier Foamglass Insulation
Heater
Figure 5 Typical detail of a Type 3 above ground double containment storage tank
6 EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association
Publication147 Recommendations for refigerated liquefied gas storage tanks
CS Roof
AL Suspended Deck
Fibreglass Blanket
Perlite Powder
9% Ni Outer Tank
9% Ni Inner Tank
Heater
Foamglass Insulation
Figure 6 Typical detail of a Type 4 above ground full containment storage tank
CS or RS Roof
AL Suspended Deck
Fibreglass Blanket
Perlite Powder
Vapour Barrier
PC Outer
Tank Wall
9% Ni Inner Tank
9% Ni
Secondary
Barrier
Foamglass Insulation
Heater
Figure 7 Typical detail of a Type 5/Type 8 above ground full containment storage tank
EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association 7
Recommendations for refigerated liquefied gas storage tanks Publication147
CS or RC Roof
AL Suspended Deck
Fibreglass Blanket
Heater
RC Wall
Earthen
Berm
9% Ni Inner Tank
Perlite Powder
Foamglass Insulation
Vapour
Barrier
Figure 8 Typical detail of a Type 6/Type 7 above ground full containment storage tank
CS or RC Roof
FG Blanket
AL Suspended Deck
PCont Wall
PUF Insulation
SS Membrane
Heater
8 EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association
Publication147 Recommendations for refigerated liquefied gas storage tanks
CS or RC Roof
FG Blanket
AL Suspended Deck
RC Wall
PUF Insulation
SS Membrane
Heater Heater
RC SLAB
Impermeable Layer
Bottom Heater
All such storage tanks are primarily designed the exemplary safety record achieved by the gas
and constructed to contain the refrigerated or industry using the existing types of storage tanks.
cryogenic product under operational conditions.
Tanks constructed with the steel outer roofs EEMUA Publication 207 is double concrete tank
(whether constructed from 9% nickel steel or design guidelines which is the result of mutual
normal carbon steel) or steel outer tanks may not work between its Storage Tank Committee
provide containment against accidental loads. and experts from the civil engineering and gas
industries.
EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association 9
Recommendations for refigerated liquefied gas storage tanks Publication147
2.3 Refrigerated/cryogenic or
pressurized storage
Large volumes of products that are in the gaseous
phase at ambient temperature and have a flash
point lower than 0ºC are most economically stored
at their boiling point in refrigerated or cryogenic
storage. In this case storage takes place nominally
at ambient pressure.
10 EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association
Start
Publication147
Total volume
N
of product to be
stored > 10,000 m3
(1)
Y Mixture C3/C4
Y Y Above ground N
storage allowed
(6)
International
only. Volume < 10,000 m3 not economical
N Go to
tender procedure N
pressurised Site available with
for storage Unit (2) creates difficulties for refrigerated storage in respect
storage adequate separation/
available? (5) of variations in boil off rating and stratification in storage
safety distances
tank
Y
(3) maximum 80,000 m3 refrigerated storage capacity for
Y
one unit
Existing
capacity of flare, N
Select product (4) in the range of 10,000 m3 to 20,000 m3 the cost drainage, fire protection
properties advantage of refrigerated storage to pressurised storage systems can be
may be marginal depending on the costs for auxiliary expanded?
equipment
storage of single Y
Refrigerated
product gases
storage (5) limited available contractors to build refrigerated tanks
(no mixtures) Above ground
Covered storage
according to BS EN 14620 storage
Storage of gas (6) legislation in some countries mandate for covered Mounded or
Pressurised Spheres or bullets
mixtures (mounded and submerged) storage vessels only submerged
storage pressurised storage
considered storage
EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association
Figure 12 Selection diagram refrigerated storage systems
Recommendations for refigerated liquefied gas storage tanks
11
Recommendations for refigerated liquefied gas storage tanks Publication147
12 EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association
Publication147 Recommendations for refigerated liquefied gas storage tanks
3. Design considerations
EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association 13
Recommendations for refigerated liquefied gas storage tanks Publication147
The heat radiation criterion is approximately Where ignition occurs the fire front will burn back
1·5kW/m2 for the following location types: towards the source with a maximum flame velocity
of approximately 10 to 15m/s. Eventually, this will
• Areas with a high population; result in a total tank fire (open pool fire). However,
• Areas where important work may be since it is difficult to assess the exact LFL, most
executed under most operational conditions; tank installations containing LNG storage tanks
• At the plot fence lines where critical off-plot are designed using a limit of half the theoretical
areas exist; LFL value. In addition, the presence of concrete
• Access roads that have to remain open structures for the outer tank and outer roof may
during the case of credible and non-credible eliminate the risk for an open pool fire.
emergency conditions ; and
• Areas too difficult or too dangerous to be Some users and owners of tanks that are only
evacuated by work staff at short notice. constructed from carbon steel or 9% nickel
steel outer tanks and roofs may consider them
Operators may require separation distances of 2.5 unsuitable for most planned locations even though
to 4 * tank diameter for 1·5 kW/m2 heat radiation these tanks are categorized as full containment
based on the open pool fire scenario depending according to EN 14620.
on prevailing weather and local site conditions.
Figures 13 to 15 below show an LNG tank that can
For the scenario where gas clouds escape from be regarded as satisfying best practice principles.
a storage tank (vapour cloud scenario) the According to the earlier referenced EN norm this is
vaporization rate of the cold methane (in the case categorized as a full containment tank constructed
of an LNG-tank) is low as it needs significant heat with a pre-stressed concrete outer tank and a
from the surroundings for vaporization to take place. reinforced concrete outer roof. This tank concept
Initially the methane flows over the edge of the is not only capable of carrying all operational
tank and spreads out over the facility depending on loads and load combinations and most (if not all)
wind velocity and direction. The absorption of heat accidental loads. This type of storage tank allows
progresses through time and the cloud becomes for the smallest (safety) distances to be used.
progressively lighter than the surrounding air. At the
end of the vaporization period the cloud consists of
an air/vapour mixture. It should be noted that the
cloud could only be ignited when the methane/
air ratio is between the Lower Flammability Limit
(LFL) and the Upper Flammability Limit (UFL). LFL
is equal to the lowest ignition level under which
the gas mixture has an excess of oxygen and too
little product vapour to ignite. UFL is equal to the
upper ignition level above which the gas mixture
contains too little oxygen and an excess of product
vapour to ignite. The distance from the tanks to
the LFL boundary, at or near ground/sea level, is
a maximum of 250m with an average of 100m
depending on weather conditions.
14 EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association
Publication147 Recommendations for refigerated liquefied gas storage tanks
Figure 13 Typical LNG tank designed and constructed to best practice principle
Note: The tank can also be constructed on an elevated concrete slab or a concrete slab
fully supported by the soil. In the latter case a heating system is installed in order to prevent
frost heaving induced by the freezing water in the (sub) soil (see figures below).
EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association 15
Recommendations for refigerated liquefied gas storage tanks Publication147
Concrete Slab
Columns
3.2.2 Basic requirements for pressure The hydrocarbon vapour outflow from internal
and vacuum relief positive pressure relief valves can be ignited by one
of the following:
3.2.2.1 Spare venting capacity
• Lightning: Except for emergency relief
Internal positive pressure relief valves and internal associated with power failure or atmospheric
negative pressure relief valves for refrigerated pressure drop which may occur during a
storage tanks should be provided with interlocked thunder storm, the probability of lightning
block valves and spare positions, so that a faulty occurring simultaneously with the opening
pressure relief valve can be exchanged without the of a relief valve is negligible. Leaking relief
opening of the tank to atmosphere. See Figure 16. valves increase the probability of lightning
ignition. The snuffing system connected
3.2.2.2 Relief of compressed vapour to the discharge pipework may be used to
extinguish the ignited vapours; or
There are two means of relieving the compressed • Adjacent tank fire: The expansion of
vapour of a tank system as follows. vapour in the dome of the tank subject to
radiation from an adjacent tank fire could
• Relief to controlled system: Vapour relieved cause the atmospheric relief valve to open.
from the pressure relief valve of a tank should If the venting vapour ignites, the additional
be conducted to a location such as a flare radiation from the vent fire causes further
system where it is safely discharged; and expansion thus requiring additional venting
• Relief to atmosphere: Vapour should be capacity, and results in high roof-plate
safely vented directly to atmosphere, temperatures. If necessary, use should be
provided that this is accomplished without made of adequate water spray/exposure
creating the following problems: protection facilities.
o Formation of flammable toxic mixtures
at ground level or on elevated structures
where personnel are likely to perform their
duties; and
o Ignition of the relieved vapours at point of
emission.
16 EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association
Publication147 Recommendations for refigerated liquefied gas storage tanks
L = Locked Closed
To Atmosphere
LO = Locked Open
Vacuum
Spare
Spare Breaker
Position
Position
LO
L LO
L
PC
PVC Let-Down to
Common System
Motor-Operated Valve
Boil-Off Header
3.3 Leakage and spillage When larger spills are to be taken into account,
measures are normally taken to limit the surface
3.3.1 General area (pool diameter) of the spill and hence the rate
of vapour formation. These may take the form
Both the volume of the leak or spill and the nature of concrete guard walls, earth bunds, or a system
of the product should be taken into account of channels leading to a remote collection area.
when considering the consequence of leakage Some tanks are located below ground level for
or spillage. All spilled refrigerated liquids will similar reasons.
evaporate at a rate which is directly related to the
surface area of the spilled liquid. Small leaks and Vapour cloud generation should be avoided for
spills may require forced ventilation of potential other reasons than those associated with fire and
pockets of gas, for instance under the bases of explosion. Ammonia, for instance, can be highly
above-ground tanks. This is particularly the case poisonous in comparatively small concentrations
for heavy gases such as butane or propane. In this and thus requires special consideration. Dense
connection, gases such as methane, which are vapour clouds can also cause suffocation and
lighter than air at ambient temperature are usually the low temperature of the liquid and vapour is a
denser than air when they are first evacuated, and hazard.
are thus capable of forming a low lying vapour
cloud.
EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association 17
Recommendations for refigerated liquefied gas storage tanks Publication147
18 EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association
Publication147 Recommendations for refigerated liquefied gas storage tanks
The maximum allowable liquid level (design liquid Reference is made to Chapter 6 to the following
level) is calculated by using time intervals based issues:
on local operating conditions so that a stepwise
overfill protection system exists. • Prevention of overpressure;
• Prevention of vacuum;
The typical levels to be noted are shown in Figure • Tank heating system;
17. The distances a, b and c should be determined • Liquid in annulus;
on the basis of the selected time intervals (e.g. one • Prevention of roll over; and
hour) and the pump-in rate. • Refilling after maintenance.
3.3.7 Spillage
EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association 19
Recommendations for refigerated liquefied gas storage tanks Publication147
Where necessary, the tank areas where such 3.5 Effect of radio
spillage is possible should be protected by
provision of low temperature steel roof plating or transmissions, static electricity
product catchment trays, liquid proof insulation & cathodic protection systems
and suitable drainage directing the spillage to a
safe disposal area. The size of these trays should In some circumstances a hazard may exist when
take account of wind dispersion. a flammable substance is stored in the vicinity of
certain types of radio transmitters. Radio waves
3.4 Lightning protection can induce sufficient energy in steel members to
cause incendiary sparks at distances up to 20 km
The structure should be provided with adequate (based on MF broadcast radio transmitter of
protection to prevent damage and fire from 150 kW and a Group llC Gas) from certain high
lightning. The requirements of local codes power transmitters. Normal provision of on-site
pertaining to fire caused by lightning should radio systems, amateur and CB radios should not
be observed in full. Where tankage is required create a hazard at distances above 200m. If there
to be protected against lightning the following is any doubt on the possibility of a hazard existing
recommendations are made: then expert advice should be sought.
See PD CLC/TR 50427(9).
• Provided there is a minimum steel thickness
of 5 mm, a lightning discharge should not Static voltages can also be built up in unearthed
penetrate the tank and the absolute value of metalwork with a danger of spark creation.
the earthing of a vertical storage tank is not
important as far as the tank is concerned. Cathodic protection systems for buried steelwork
Where it is necessary to earth a storage tank can also give rise to break sparks. If any of these
for other reasons, e.g. because of installed hazards are relevant to a particular location a more
electrical equipment, static discharge, or detailed study should be undertaken. Enhanced
protection of the supporting structures, the earthing provisions may be necessary to overcome
absolute value of the earthing resistance the danger thus arising.
should be determined;
• Electrical appliances and cabling either on 3.6 Earthquakes
or in tankage should be electrically earthed.
Any metal part which may be electrically For information on earthquakes see EN 14620.
isolated from the tank, e.g. by a gasket or
even by a rust layer, should be bonded to the
tank by the shortest possible route; and
• Where tanks or pipelines are cathodically
protected, either spark arresters, enclosed
spark gap devices or similar devices should
be fitted across any insulated flanges.
20 EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association
Publication147 Recommendations for refigerated liquefied gas storage tanks
Unless otherwise agreed the inner tank should be Tank filling rates and all related checks for
hydrostatically tested to the water level required by foundation levels of the inner and outer tanks
the specific design Code used. should be agreed between Purchaser and
Contractor (See EN 14620).
In accordance with EN 14620 all joints should be
checked for leakage. However, small leaks in the 4.5 Outer concrete tank testing
bottom may not be readily detected. For this
reason it is recommended to repeat the vacuum A hydrostatic test of outer tanks constructed of
box test of the bottom plate welds after the pre-stressed concrete, or reinforced concrete in
hydrostatic testing. conjunction with an earth embankment, does
not need to be carried out unless specified by the
Purchaser.
EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association 21
Recommendations for refigerated liquefied gas storage tanks Publication147
5. Tank Commissioning
22 EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association
Publication147 Recommendations for refigerated liquefied gas storage tanks
EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association 23
Recommendations for refigerated liquefied gas storage tanks Publication147
24 EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association
Publication147 Recommendations for refigerated liquefied gas storage tanks
Once purging is commenced it should be The purging end point data with a 20% safety
continued to completion without interruption. factor are given in this Table, in terms of
However, should it be necessary, to suspend the percentage of oxygen for the purging of tanks in
operation, steps need to be taken to ensure that preparation for reception of various hydrocarbon
a positive pressure is maintained so a vacuum products. The safety factor of 20% allows for the
condition is prevented. possibility of sampling error and non-uniformity of
oxygen distribution inside the tank system.
5.5.2 Types of inert gas
Table 1 Oxygen concentration end-points for
The success of a drying and purging operation purging from air
depends on the inert gas selected for use. Product Percent oxygen
(volume) below which the
The inert gas should not be combustible and mixture is not flammable
should contain less than 0.5% volume of oxygen. (20% safety factor included)
It should not be corrosive and to accomplish an Methane 9.7
effective drying of the tank, the dew point of Ethane 8.8
the inert gas should be -40°C. Nitrogen (in bulk Propane 9.1
or from an air separation plant) is the preferred N-Butane 9.7
medium. For LNG and pure component storage Isobutane 9.6
(e.g. ethylene, propylene, ammonia) it is the Ethylene 8.0
only acceptable purge medium. For liquefied Propylene 9.2
petroleum gas (LPG) tanks, dry inert gas may be Butadiene 8.3
used.
Note: To allow a higher degree of safety, it is
recommended that the purging operation
5.5.3 Purging tanks from air to inert
should proceed until an oxygen level of less than
atmosphere
5% volume is reached.
It is convenient to control the purging operation
by determining the oxygen content of the purged On completion of purging, a positive pressure
gas. Inert gas is supplied to the tank, until the should be maintained to prevent vacuum
oxygen concentration at all locations inside the conditions being created by changes of ambient
tank has decreased to a level where no mixture of conditions.
the contents with the product would be flammable
or cause off specification product after cool-down, Throughout the purging operation and on
e.g. ethylene, propylene. completion, the tank is not safe for entry without
breathing apparatus. Notices to this effect must be
The maximum allowable oxygen levels to ensure prominently displayed at all potential entry points
a non-flammable mixture as indicated by the US and vents.
Bureau of Mines (28) are given in Table 1.
EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association 25
Recommendations for refigerated liquefied gas storage tanks Publication147
5.5.4 Purging tanks from inert to 5.5.5.2 Purging ancillary piping and equipment
hydrocarbon atmosphere
All piping inside the tank and the pressure and
Normally, the inert gas is displaced by product vacuum relief valves should be purged by venting
vapour before liquid is introduced. This prevents any to atmosphere and allowing the purge gas to flow
undercooling that may take place during the cool- through the lines until the required endpoints have
down. This is especially important for LPG tanks. been reached. All lines connected to the tank up
to the physical disconnection or to the position of
Table 2 Minimum temperature reached the blinds should be purged.
Min. Temp. °
C ABP °
C
After the purging has been completed the tank
Methane -180 -161
should be sealed-off and kept under a purge gas
Ethane -120 -89
atmosphere at a slight overpressure. It may be
Ethylene -130 -104
necessary to maintain the pressure in the tank by
Propane -80 -42
addition of purge gas at intervals.
Propylene -85 -48
N-butane -45 -1
Atmospheric pressure changes may cause venting
Butadiene -50 -5
and vacuum breathing with ingress of humid air if
purge gas is not topped up. The topping up purge
Note: The presence of an inert gas atmosphere
gas should be supplied directly into the inner tank.
results in low hydrocarbon partial pressure and
therefore a liquid boiling point significantly below
the atmospheric boiling point (ABP) of the liquid. 5.6 Commissioning of the tank
An estimation of the minimum temperature
heating system
reached by an inert or nitrogen atmosphere during
the initial stage of cool-down is summarised in
When a tank has been provided with a heating
Table 2.
system to protect the tank structure against frost-
heave, this system should be commissioned before
5.5.5 Drying and purging procedure
the cool-down operations start.
26 EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association
Publication147 Recommendations for refigerated liquefied gas storage tanks
The heating system should not be immediately o the temperature indicators located at the
activated after cool-down. In the days following bottom and annular space, if applicable;
the cool-down, the foundation temperatures o the level instruments (servo/radar-
should be carefully monitored. operated and back-up level instruments)
and, where applicable, liquid detection
For additional information see EN 14620. instruments located in the annular space
(such as DP-level gauge);
• cold gas and liquid systems should be
5.7 Cool-down
operable. Cold liquid should be lined up to
5.7.1 General the cool-down liquid spray ring. Cold gas
should be lined up to the cold gas purge
During the cool-down operation, a full record piping system if present;
should be made of all temperatures, pressures and • line up the auxiliary systems;
levels relevant to the operation. • bottom heating should be put into operation;
• all hydrocarbon gas and liquid lines to/from
When the impurities present in the vent gas the tank should be connected and blinds
are acceptably low to prevent off specification removed; and
product in the tank and when the bottom • nitrogen supply to the tank should be
plate temperatures approach normal storage disconnected (except where used for
temperature, introduction of liquid product instrumentation).
through the normal inlet piping system can be
started.
5.7.3 Cool down rates
EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association 27
Recommendations for refigerated liquefied gas storage tanks Publication147
28 EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association
Publication147 Recommendations for refigerated liquefied gas storage tanks
6. Operations
EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association 29
Recommendations for refigerated liquefied gas storage tanks Publication147
Inner Tank
Level in
Annulus
30 EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association
Publication147 Recommendations for refigerated liquefied gas storage tanks
Suspended Roof
Drain Holes
Inner Tank
Liquid
Outer Tank
Due to the condensation the pressure in the system and should be carried out before each
tank will drop. All operating conditions are to be winter. During the winter period regular sampling
evaluated so that regular opening of the vacuum should be done to check the composition of the
relief valves is prevented. Gas injection into the gas in the space between inner suspended roof
dome may be considered as an active protection and outer roof.
EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association 31
Recommendations for refigerated liquefied gas storage tanks Publication147
32 EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association
Publication147 Recommendations for refigerated liquefied gas storage tanks
EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association 33
Recommendations for refigerated liquefied gas storage tanks Publication147
i) Check for frost or ice build up on thermal i) Check and test the condition of any fire
distance pieces. protection device on the tank.
ii) Check the condition of any expansion ii) Check and test that steam lances are
bellows regarding corrosion, unusual functional (where fitted).
distort-ions, ice build up or other damage. iii) Check sources of possible liquid escape
iii) Check for rotation of nozzles. Movement which could impinge on the tank and
would indicate frost heave on the inner tank check condition of any protection devices
or deterioration of the foundation. provided e.g. mats, catchtrays, etc.
iv) Check pipe supports connections to roof or
shell.
7.6 Maintenance planning
v) Check piping insulation.
vi) Check condition and settings of spring
Typically, a storage tank is designed to operate
supports and compare with data sheet
such that it remains in service for many years.
settings.
However, a plan should be in place to define,
vii) Check trace heated nozzles and adjacent
action and record where necessary routine
piping for localised corrosion.
inspections and maintenance activities during the
operating life of the tank.
7.5.2.5 Structures
Check condition of roof platforms, walkways and 7.7 Review of tank performance
handrails.
Prior to major maintenance or inspection of the
7.5.2.6 Pressure and Vacuum Relief Valves and tank, a review of the tank operation should be
Instrumentation conducted.
i) Check pressure and vacuum relief valves for Attention should be focused on the following
icing, mechanical damage, corrosion and areas:
leakage.
ii) Check and test that steam lances are • review of operational history of the tank
functional (where fitted). structure, surrounds and ancillaries;
iii) Check sources of possible liquid escape • review of maintenance records since the last
which could impinge on the tank, and major inspection; and
check condition of any protection devices • note any reported incidents, for example,
provided, e.g. mats, catchtrays, etc. spillages.
7.8 Foundations
In this Section, the foundations are defined as the
base slab up to the first wall construction joint and
includes the area immediately surrounding the
tank at ground level.
34 EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association
Publication147 Recommendations for refigerated liquefied gas storage tanks
The settlement measurements should be repeated Elevating tank base slabs generally avoids the
and recorded for comparison with previous use of base heaters. The airspace can become a
measurements, using both the targets and trap for wind borne material which, if allowed to
inclinometers. accumulate, can bridge the space. The thermal
insulating properties of this material may lead to
7.8.4 Foundation heaters a lowering of the slab temperature which may
eventually affect the strength of the concrete
Note: Check the correct isolation of electrical reinforcement.
equipment prior to carrying out electrical checks.
Checks should be required to ensure that a safe
The seals at the external terminations of the base atmosphere is present in the airspace prior to entry.
heating conduits should be checked for signs of
water ingress and physical damage and the seal The underside of the tank slab should be inspected
repaired or replaced as necessary. for degradation of the concrete, particularly
cracking at the slab-to-pile cap junction.
EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association 35
Recommendations for refigerated liquefied gas storage tanks Publication147
In addition to a general visual inspection of the The roof surface should be examined for evidence
walls, particular attention should be paid to the of concrete cracking and spalling. In particular,
areas where the tank wall may be susceptible to attention should be paid to the following areas:
deterioration in preference to the main structure.
• roof surface below the pressure relief valve
These areas include: vents, where heat damage may occur; and
• closures following formwork tie-bar removal; • the surface below the pump platform where
• construction joints; and accidental product spillage may have caused
• closure joint for the construction temporary local spalling of the reinforced concrete.
opening.
7.10.2 Rain water drainage (where
7.9.2 Buttresses provided)
The grouting associated with the closure of the Where roof rain water drains have been provided
pre-tensioning cables should be inspected for they should be checked to ensure that a free flow
cracking, loss of material and water ingress. Loose of water to ground level can be maintained. Pipes
material should be removed, surfaces prepared and that cannot be fully visually inspected should be
made good with grout. proved to be clear by another mechanism, for
example by flushing.
36 EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association
Publication147 Recommendations for refigerated liquefied gas storage tanks
EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association 37
Recommendations for refigerated liquefied gas storage tanks Publication147
38 EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association
Publication147 Recommendations for refigerated liquefied gas storage tanks
EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association 39
Recommendations for refigerated liquefied gas storage tanks Publication147
7.13 Internal inspection From the roof manway, visually examine the
supporting rods of the suspended deck for any
7.13.1 General signs of distress. Any signs of deflection in the top
level of the insulation system located on the deck
The decommissioning and internal inspection of should be investigated further before access to the
RLG tanks is a potentially hazardous operation, suspended deck is provided.
especially for an open topped inner tank, and there
exists an associated risk of causing damage to the From the inner tank bottom examine the entire
tank and insulation system. Corrosion is known underside of the suspended deck for any unusual
not to occur in the dry, inert, low temperature distortion or potential problems. When it has been
conditions inside the tank. established that the suspended deck is intact the
full inspection of the deck may proceed.
No technical justification for conducting routine
internal inspections of RLG tanks can be provided 7.13.3 Inspection from suspended deck
so long as the tanks are operated within their
design/ operational limitations that should be The following checks should take place when
confirmed by the external inspection and the carrying out inspection from the suspended deck:
operating history.
• Check that support rods are not slack;
When the operating history of a certain liquefied • Examine roof structure visually for any
gas in refrigerated storage tanks indicates that the distortion or damage;
possibility of corrosion cannot be excluded, e.g. • Examine undersides of roof plates around
as stress corrosion has been experienced in some roof nozzles and other roof attachments;
refrigerated ammonia tanks, it is recommended • Examine the deck insulation for damage or
that the types of internal inspections and their depressed areas indicative of movement.
intervals are agreed between the user and the Measure depth and compare with original;
authorities. • Visually examine all piping between roof
and suspended deck. Particular attention
Where internal inspections are considered to be should be paid to distorted or bent pipes.
necessary, the following paragraphs suggest a Where pipe is insulated check the insulation
number of checks which may be carried out if so attachment to the pipe;
agreed. • Check perlite level in the annular space
between inner and outer shell for signs of
7.13.2 Initial inspection of suspended compacting (where relevant);
deck • Check the integrity of the seal between
suspended deck and inner shell; and
It is important for an initial inspection of the • Check all vent openings located in the deck
deck to be performed to ensure its integrity is to ensure that they are not blocked.
acceptable to permit a full inspection to proceed.
40 EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association
Publication147 Recommendations for refigerated liquefied gas storage tanks
EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association 41
Recommendations for refigerated liquefied gas storage tanks Publication147
8. De-commissioning
In general, decommissioning of refrigerated gas Total time required to carry out tank
storage tanks should be carried out only when decommissioning depends mainly on the size and
required by authorities, or for repairs, as there is type of tank concerned
always added risk associated with warm-up and
cool-down operations.
8.1.3 Liquid removal
42 EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association
Publication147 Recommendations for refigerated liquefied gas storage tanks
The liquid level at the end of the pump-out phase During these operations the inner tank
should be as low as possible, since vaporising the temperatures should be monitored and controlled.
liquid is a time consuming process. Vaporisation may be considered completed when
all the TI s are 10°
C above the product boiling
8.1.3.2 Removal of liquid by vaporisation point.
EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association 43
Recommendations for refigerated liquefied gas storage tanks Publication147
The complete tank should be purged, including Table 4 Combustible gas and points for purging
the inner tank, outer tank, dome space and all Recommended percentage of combustible gas
insulation materials, e.g. perlite, glass wool, sand below which no mixture is flammable when air
etc. Since continued desorption of hydrocarbons is added in any amount
from the insulation materials can be expected
Purge medium CO2 N2
to take place over an extended period, sampling
Hydrocarbon % volume % volume
during the latter stages must be carried out
Methane * 11.0
carefully using appropriate safety procedures.
Ethane 9.0 5.0
Ethylene * 5.0
On LNG tanks, the purge operation has to be
Propane 9.0 5.0
carried out up to ambient temperature in order
Propene * 3.0
to achieve hydrocarbon desorption from the
Butane 7.0 4.0
perlite. As a guide, it is useful to predict an order
Butadiene * 4.0
of magnitude of the diffusion rate and of the time
Isobutane 7.0 4.0
required to purge the annular space into nitrogen.
Pentane 3.0 2.0
It is a suitable method to control the progress of the * Not applicable (no CO2 purge)
purge operation by determining the hydrocarbon To allow a higher degree of safety, it is
concentration in the tank. Representative samples recommended to apply a safety factor of 50% on
should be taken frequently from the vent pipes the allowable combustible concentration
and from a number of locations representative of
conditions in all parts of the tank. It should be noted that the recommended
endpoints in Table 4 are a percentage of the
In the latter stages, inert gas flow is stopped and theoretical value due to:
samples are taken after a soak period of one or two
days, in order to detect any further desorption and • the uncertainty of obtaining representative
possible migration of hydrocarbons. samples; and
• the risk of trapped hydrocarbon.
The hydrocarbon content can be determined by
laboratory analysis or by gas detectors. The gas 8.1.4.3 Purging tanks from an inert atmosphere into
detector devices should be of a type suitable to an air atmosphere
ensure accurate hydrocarbon detection in an
atmosphere without oxygen. The purpose of purging into air is to allow entry for
inspection and/or repair under normal atmospheric
At the end of purging, hydrocarbon content in conditions without the use of breathing apparatus.
inert gas should be such that during subsequent This purge should be extended to all spaces of the
purging with air, the tank atmosphere remains tank.
non-flammable. The maximum allowable levels of
hydrocarbons to ensure a non-flammable mixture,
as determined by the US Bureau of Mines are
given in Table 4. Hydrocarbon end points (20% of
theoretical value) are indicated, according to the
purge medium.
44 EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association
Publication147 Recommendations for refigerated liquefied gas storage tanks
EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association 45
Recommendations for refigerated liquefied gas storage tanks Publication147
46 EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association
Publication147 Recommendations for refigerated liquefied gas storage tanks
• the liquid level at the end of this pump-out The set point of the electrical heating system may
phase should be as low as possible since be adjusted to enhance vaporisation. Gradually
liquid vaporisation is a time consuming inject hot gas or nitrogen into the inner tank
process. A minimum level between 20 through the purge pipe or a pump well. Control
and 30 cm would generally be considered the gas flow so as to ensure that the specified
acceptable, i.e. down to approximately the rate of temperature increase is not exceeded.
foot valve opening. The boil-off gas is sent preferentially to the boil-
off compressor. The de superheater should be
8.2.4.3 Liquid in the annular space (abnormal) checked to see if it is working properly to allow
for the higher temperature of the boil-off gas.
In order to prevent lifting of the inner tank, The tank pressure is controlled by the pressure
the liquid level in the annular space must be control system to the boil-off compressor and to
maintained lower than that of the inner tank. On the flare. Vaporisation is complete when all TIs of
LPG tanks, a pump well is normally provided in the inner tank bottom plates are 10° C above the
the annular space. After installation of a pump, product boiling point, although some small liquid
liquid removal from the annular space and possibly pockets can still remain. All outer tank bottom
the inner tank may start. No pumping facilities temperatures should be above 0° C to ensure there
are provided in the annular space of LNG tanks. is no liquid remaining underneath the inner tank.
Vaporisation is the primary means of removal.
8.2.7 Tank isolation (Stage 2)
8.2.5 Tank isolation (Stage 1)
During this operation, the tank pressure remains
The following steps should be taken: controlled by a PCV to the flare, and the relief
system to atmosphere. The flare is still in service.
• close all block valves of the rundown line,
warm product line, unloading line, circulation The following steps should be taken:
line, pump discharge line;
• relevant valves should be locked closed and/ • spade-off all liquid lines at the tie-in point
or MOV (Metal Oxide Varistor) fuses taken out; at the main pipe track
and Note: those lines previously spaded in Stage
• the pumps should be electrically 1 of tank isolation should be thoroughly
disconnected. rechecked;
• purge with nitrogen the part of these lines
8.2.6 Vaporisation of remaining liquid downstream of the blinds into the tank.
Ensure that control valves are open initially
The remaining liquid in the tank and in the and then closed so that all bypass lines are
attached lines can only be removed by purged; and
vaporisation which is a time consuming process. • close the block valves at the connection to
During this operation, the TI s of the inner tank the tank after purging.
shell and bottom, and the temperatures of the
concrete wall and bottom slab should be recorded
on an hourly basis. The tank should be still
protected against overpressure and vacuum.
EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association 47
Recommendations for refigerated liquefied gas storage tanks Publication147
8.2.8 Inerting and warm-up of tank • periodically stop nitrogen injection and
analyse the hydrocarbon content in the
8.2.8.1 Monitoring annular space after a soak period of about six
hours. Control the flow of nitrogen according
During this phase, TIs of the inner should be to the purging efficiency.
controlled within the limits specified.
Purging should continue until the required end-
The following measurements should be monitored points are obtained.
and recorded:
Purge all tank piping systems, process pipes,
• the temperature indicators of the inner instrumentation pipes, dead ends, etc., and pump
tank shell and bottom (hourly) and the wells.
temperatures of the concrete bottom slab
(per shift); Inerting is completed when, after a soak period
• the vapour temperature (hourly); of one or two days at ambient temperature, the
• the pressure in the different parts of the tank hydrocarbon content of all samples remain below
(hourly); the LFL (Lower Flammability Limit).
• the pressure differential between spaces
above and below the inner tank bottom plate 8.2.9 Simultaneous decommissioning of
and the bottom liner (hourly); and submerged pumps
• the hydrocarbon content in the purged
vapour and inside the tank (once per shift). Before the tank is purged into air, submerged
pumps should be removed according to the
8.2.8.2 Procedure following steps:
During this step, i.e. inerting with nitrogen, install • ensure the pump is electrically disconnected
all necessary temporary connections. from the supply (switchgear house);
• disconnect the pump from the electrical
The following steps should be taken for inerting system at the junction box;
with nitrogen and warm-up: • raise the pump, thereby closing the foot
valve;
• nitrogen is injected into the bottom of the • remove the cover plate;
inner tank via the purge pipe. The nitrogen • remove the pump from the well; and
flow should be controlled manually to • close the well gain.
meet the boil-off compressor capacity and
temperature constraint; All pumps should be prepared for storage in the
• the boil-off compressor should be stopped, workshop, i.e. they should be dried and cleaned.
the tank isolated and the hydrocarbon/ Replacement of the bearings before re-installing
nitrogen mixture sent to the flare; the pumps in the tank should be considered.
• when the hydrocarbon content in the purged Pumps and electrical/support cables should be
gas from the inner tank is below 5% volume, kept clean and dry by storing in plastic bags
purging of the annular and insulation bottom (vapour tight) with desiccant inside.
space may start; and
48 EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association
Publication147 Recommendations for refigerated liquefied gas storage tanks
8.2.10 Tank isolation (final stage) reaches an acceptable level, gradually open
the annular space purge line and insulation
All lines are to be isolated from the tank by a bottom space to atmosphere;
physical air gap or positive isolation. The tank • regularly check the oxygen content of the
remains protected against overpressure by the annular space by stopping air purging for
relief system and against vacuum by the vacuum about six hours and test for drop in oxygen
breakers. level;
• when the oxygen content of all samples
The following steps should be taken: is above an acceptable level, close all the
purge lines and isolate the temporary relief
• install a temporary PRV with a setting in valve. The tank remains protected against
the range of 30 to 50 mbarg on the spare overpressure by the process relief valves to
vacuum breaker nozzle or other nozzle atmosphere;
connected to the dome space; • slowly increase the tank pressure to value just
• slowly reduce the pressure in the tank to (to below the relief valve setting by injecting air;
prevent lifting of the bottom plates) in order • purge to atmosphere all tank piping, process
to allow spading; pipes, instrumentation pipes, dead ends etc.;
• close all block valves in the vapour lines at • air purging is completed when after a soak
the tie-in point with the main pipe track and period of one or two days, the oxygen
on the top of the tank; purge these lines with content of all samples is at an acceptable
nitrogen; and level;
• space-off all lines as close as possible to the • upon completion of air purging and before
tank roof. Ensure there is good ventilation first entrance, gradually decrease the pressure
with air during this operation in order after which the manholes can be opened;
to avoid suffocation risks. Gas masks or and
breathing apparatus should be worn. • the first entrance into the tank is then
possible.
8.2.11 Purging into air
Note: Hydrocarbons may still be trapped in the
Dry air is required for this operation. In order to bottom insulation space.
enhance the piston effect the air temperature
should be as low as possible. During the period that the LNG tank is out of
operation, dry air must be supplied continuously to
Purging into air should entail the following steps: the annular space in order to dilute and purge any
desorbed hydrocarbons and keep the perlite dry.
• all purge lines from the annular space and the Depending on the work and the time involved in
insulation bottom space are closed; the activities to be carried out, it may be decided to
• inject air gradually into the inner tank change the supply of dry air to ambient air in this
through the purge line. Nitrogen/air is part of the tank, providing the insulation can be
vented through the temporary pressure relief kept dry.
valve;
• when the oxygen content of the purged gas
vented through the temporary relief valve
EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association 49
Recommendations for refigerated liquefied gas storage tanks Publication147
50 EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association
Publication147 Recommendations for refigerated liquefied gas storage tanks
EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association 51
Recommendations for refigerated liquefied gas storage tanks Publication147
Codes, Standards and Reference Documents API 620: Appendix L Seismic design of storage
for Pre-stressed Concrete Tanks and Reinforced tanks
Concrete Tanks with External Earth Embankment: EN 1998: Eurocode 8: Design of structures for
earthquake resistance
EN 1994-1 Eurocode 7. Geotechnical design. PD 7777: Alternative steel selection and its effect
General rules on design and testing of tanks to BS
BS 4449 Steel for the reinforcement of 7777
concrete. Weldable reinforcing
steel. Bar, coil and decoiled General:
product. Specification
BS 4482 Steel wire for the reinforcement of Energy Institute, Liquefied Petroleum Gas, Volume
concrete products. Specification 1 : Large Bulk Pressure Storage & Refrigerated LPG,
BS 4486: 1980 Specification for hot rolled and hot Model Code of Safe Practice, Part 9 ISBN 0 471
rolled and processed high tensile 91612 9
alloy steel bars for the prestressing
of concrete CIA Code of Practice for large scale storage of fully
FIP/3/2. 1978* Recommendations for the design refrigerated anhydrous Ammonia in the United
of pre-stressed concrete oil storage Kingdom, ISBN 10 0900623101
tanks, ISBN 978-0-7210-1084-7
Fédération internationale de la NFPA 59** Standard for the storage
précontrainte. and handling of liquefied
FIP/3/6 1982* Preliminary recommendations for petroleum gas (LPG)
the design of pre-stressed concrete NFPA 59A: 1985** Standard for the production,
containment structures for the storage and handling of
storage of refrigerated liquefied liquefied natural gas (LNG)
gases (RLG), ISBN 978-0-907862-17- The American Federal Safety Standard 49 Code of
8 Federal Regulations, Part 193, 1980
CPUC GD-112D ̶ The state of California Public
Proceedings of the First International Conference Utilities Commission Code
on Cryogenic Concrete (1981) and Second
International Conference on Cryogenic Concrete CEGB (1982) Earthquake Hazard . Civil Eng. Branch
(1983), published by the Concrete Society (UK). Ref:- C/JI/SD/152.0/R019 Seed H.B. and Idriss I.M.
(1982) Ground Motions and Soil Liquefaction
List of publications on pre-stressed concrete Japan M.I.T.1. (1981) The Japanese Ministry of
(Technical Paper No. 103), available from the International Trade and Industry standard for
Concrete Society (UK). aboveground L.N.G. Storage
52 EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association
Publication147 Recommendations for refigerated liquefied gas storage tanks
Codes and Standards applicable to Insulation BS 5241: 1975 Rigid urethane foam when
dispensed or sprayed on a
BS 476: Fire tests on building construction site
materials and structures BS 5422: 1977 (1978) Specification for the use of
: Part 4: 1970 Non-combustibility test for thermal insulating materials
materials BS 5608: 1978 Specification for preformed
: Part 5: 1979 (1980) Method of test for ignitability rigid urethane and
: Part 7: 1971 Surface spread of flame tests isocyanurate foam for
for materials thermal insulation of
BS 874: 1973 (1980) Methods for determining pipework and equipment
thermal insulating properties, BS 5970: 1981 Code of practice for thermal
with definitions of thermal insulation of pipework
insulating terms and equipment (in the
BS 2972: 1975 (1984) Methods of test for inorganic temperature range of ‒100° C
thermal insulating materials to +87° C)
BS 2989: 1982 Specification for continuously ASTM E 96 Water vapour transmission of
hot-dip zinc coated and iron materials
zinc alloy coated steel: wide ANSI C 165 Compressive properties of
strip, sheet/plate and slit thermal insulations
wide strip ANSI C 177 Steady-state thermal
BS 3177: 1959 (1969) Method of determining the transmission properties by
permeability to water vapour means of a guarded hot plate
of flexible sheet materials ANSI C 203 Breaking load and
used for packaging calculated flexural strength
BS 3533: 1981 Glossary of thermal insulating of preformed block-type
terms thermal insulation
BS 3927: 1965 (1967) Phenolic foam materials ASTM C 240 Cellular glass insulating block
for thermal insulations and ASTM C 303 Density of preformed block-
building applications type thermal insulation
BS 3958: Specification for thermal ANSI/ASTM C 547 Mineral fibre preformed pipe
insulating materials insulation
Part 1 to Part 6 ASTM C 548 Dimensional stability of low-
BS 4370: Methods of tests for rigid temperature thermal block
cellular materials and pipe insulation
Part 1 to Part 3 ANSI/ASTM C 552 Cellular glass block and pipe
BS 5111: (Part 1) Laboratory methods of test thermal insulation
for determination of smoke ANSI C 591 Rigid preformed cellular
generation characteristics of urethane thermal insulation
cellular plastics and cellular ANSI C 592 Mineral fibre blanket
rubber materials insulation and blanket type
pipe insulation (metal-mesh
covered) (industrial type)
EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association 53
Recommendations for refigerated liquefied gas storage tanks Publication147
54 EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association
Publication147 Recommendations for refigerated liquefied gas storage tanks
Date feedback provided: EEMUA Publication: 147 Specifying, produring & managing 3rd party
(dd/mm/yyyy) inspection services
Feedback provided by: Feedback provided on behalf of which organisation?
Contact name:
Phone: Organisation name:
E-mail: Location:
EEMUA ref Page no. Paragraph Type of COMMENTS Proposed change OBSERVATIONS OF
(EEMUA use Figure/ comment (Please provide THE EXECUTIVE
only) Table (General/ alternative wording, (EEMUA use only)
concerned Technical/ or propose removal on each comment
Editorial) of, or addition to, submitted
existing wording.)
4 Fig 2 E This is an No change to Example only
example only wording required
When you have completed this form with all your comments, please save and e-mail to info@eemua.org or
post a paper copy to: Publications Department, EEMUA, 63 Mark Lane, London EC3R 7NQ.
EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association 55
Recommendations for refigerated liquefied gas storage tanks Publication147
206 Risk Based Inspection: A Guide to Effective 186 A Practitioner s Handbook - Electrical
Use of the RBI Process Installation, Inspection and Maintenance in
Potentially Explosive Atmospheres
193 Recommendations for the Training,
Development and Competency Assessment 178 A Design Guide for the Electrical Safety
of Inspection Personnel of Instruments, Instrument/Control Panels
and Control Systems
181 A Guide to Risk Based Assessments of In-situ
Large Ex e and Ex N Machines 175 Code of Practice for Calibration and
Validation of Process Analysers
161 Guide to the Selection and Assessment of
Silencers and Acoustic Enclosures 155 Standard Test Method for Comparative
Performance of Flammable Gas Detectors
159 Users Guide to the Inspection, Maintenance against Poisoning
and Repair of Above-ground Vertical
Cylindrical Steel Storage Tanks 138 Design and Installation of On-Line Analyser
Systems
148 Reliability Specification - Model clauses
for inclusion in purchasing Specifications for Materials selection, plant
equipment items and packages
design and construction
Automation and electrical 224 Quality assurance of safety-critical
equipment engineering equipment and materials:
A guide to risk-based procurement
226 Design and installation of on-line analyser
systems - a guide to technical enquiry and 218 Quality requirements for the manufacture/
bid evaluation supply of duplex stainless steels
56 EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association
Publication147 Recommendations for refigerated liquefied gas storage tanks
197 Specification for the Fabrication of 105 Factory Stairways, Ladders and Handrails
Non-Primary Structural Steelwork for (incl: Access Platforms/Ramps)
Offshore Installations
104 Noise: A Guide to Information required from
194 Guidelines for Materials Selection and Equipment Vendors
Corrosion Control for Subsea Oil and Gas
Production Equipment 101 Lifting Points - A Design Guide
182 Specification for Integral Block and Bleed 223 Pressure equipment testing after repair,
Valve Manifolds for Direct Connection to modifications or re-rating: a guide to the
Pipework pressure test waiver
179 A Working Guide for Carbon Steel 211 Guidance on the Specification of pressure
Equipment in Wet H2S Service vessels
176 Specification for Structural Castings for Use 208 Guide to life-cycle management of
Offshore Pressure
158 Construction Specification for Fixed 204 Piping and the European Pressure
Offshore Structures in the North Sea Equipment Directive: Guidance for Plant
Owners/Operators
154 Guidance to Owners on Demolition of
Vertical Cylindrical Steel Storage Tanks and 196 Valve Purchasers Guide to the European
Storage Spheres Pressure Equipment Directive
149 Code of Practice for the Identification and 184 Guide to the Isolation of Pressure Relieving
Checking of Materials of Construction in Devices
Pressure Systems in Process Plants
177 Guide to the UK Pressure Systems Safety
147 Recommendations for the Design and Regulations (2000)
Construction of Refrigerated Liquefied Gas
Storage Tanks 168 A Guide to the Pressure Testing of In-Service
Pressurised Equipment
234 90/10 copper nickel alloy piping for offshore
applications (Incorporating EEMUA 144, 145 149 Code of Practice for the Identification and
and 146) Checking of Materials of Construction in
Pressure Systems in Process Plants
141 Guide to the Use of Noise Procedure
Specification
EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association 57
Recommendations for refigerated liquefied gas storage tanks Publication147
192 Guide for the Procurement of Valves for Low 154 Guidance to Owners on Demolition of
Temperature (non-cryogenic) Service Vertical Cylindrical Steel Storage Tanks and
Storage Spheres
188 Guide for Establishing Operating Periods of
Safety Valves 147 Recommendations for the Design and
Construction of Refrigerated Liquefied Gas
185 Guide for Hot Tapping on Piping and other Storage Tank
Equipment
58 EEMUA Copyright © 2016 The Engineering Equipment and Materials Users Association