Professional Documents
Culture Documents
Lesson
Lesson
cost planning
Lesson
Lara Tookey
1
COST CONTROL
Pre-contract cost control Post-contract
cost control
COST PLANNING
Cost limit / Analysis to Cost
Indicative Outline Cost Detailed Cost Analysis of
Plan Plan check Cost Monitoring /
cost Final
Plan against Forecasting /
First Account
Cost priced SoQ Financial
estimate Checks Statements
1. Overall budget for the project. This is the total amount that the
project is expected to cost. This amount is based on the
current project scope and design and can be determined
through various types of estimates.
2. Allocation of costs over time. This involves predicting when
along the project schedule costs will be incurred and paid.
What if you decide NOT
to have a Cost Plan?
• Surprises from tender sums resulting in major
changes to the design to cut costs.
• Dissatisfied client due to the design changes
• If the client decides to return to the start to
redesign due to blow out in costs
• May not be possible or cost effective
• No guarantee new design will provide correct cost
solution
• Abandonment of project
• The tender sum is more likely to equate with the
approximate estimate
• Less less changes as you progress through the construction
stage
• Cost-effectiveness and a value-for-money design
Advantages of • A balanced distribution of expenditure produces a more
rational design
Cost Planning • Involvement of Quantity Surveyor at the design process
results in easier preparation of Bill of Quantities
• Involvement of both architect and quantity surveyor at pre-
tender analysis enable more decisions to be taken earlier,
resulting in a smoother running of project on site
• Provides a basis for comparing different projects
• It requires a lot of preparation in the early stage of the
design process.
Disadvantages • The designers may have some limitations in their work
style.
of Cost • The quantity surveyor needs to be equipped with vast
Planning experience and knowledge pertaining to cost and factors
influencing the cost.
• Both the designer and QS are involved with a lot more
works at the design stage compared to when no cost
planning is used.
1. Elemental cost plan
• Also know as Cast Target / Cost Limit (realistic)
• Used when “Designing to a Cost”.
Two • A cost limit is fixed or stated by the client
• Normally used in public sector
methods to
prepare a 2. Comparative cost plan
cost plan • Used when “Costing to a Design”
• Archi generally has several design alternatives
for the Client to provide value.
• Normally used in private sector
Three key terms
• Cost Control
• Cost Planning
• Cost Plan