CONTRACT STATUS REPORT


For the Period of 3/24/2023 to 10/12/2023

CONTRACT DESCRIPTION: Convergence and Special Support Program: Sustainable Infrastructure Projects Alleviating
Gaps (SIPAG) – Access Roads and/or Bridges from the National Road/s leading to
Major/Strategic Public Buildings/Facilities: Construction of Clark-Mabalacat Access Road,
Mabalacat City, Pampanga
CONTRACT PROFILE: CONTRACT SCHEDULE: CONTRACT STATUS
Funding Agreement : FY 2023 Contract Effectivity Date : 3/24/2023 PHYSICAL STATUS
Mode of Procurement : Competitive Bidding Original Contract Duration : 150 C.D. Previous Accomp. (%) :
Project Component (s) : P00740126LZ Original Contract Expiry Date : 8/20/2023 Sched. Accomp. (%): 100
Original Contract Cost : 33,296,919.18 Actual Accomp. (%): 100
Province : Pampanga Revised Contract Cost : 34,284,963.94 Slippage to Date (%): 0
Region : Region III Revised Contract Duration : 210 Time Elapsed to Date (%): 100
Program Type : Revised Expiry Date : 10/19/23
Project Category : Road and Drainage
Contractor : PRIME PAVE
CONSTRUCTION AND
ASPHALT CORPORATION

Note : Include additional information on any revision


on the contractual data if necessary

CONTRACT UPDATE:
Project Completed

ACTIVITIES THIS PERIOD:


Inauguration on May 10, 2024

ISSUES AND PROBLEMS ENCOUNTERED: RECOMMENDATIONS AND ACTIONS TAKEN:


Illegal Settlers along the Project Alignment. Settlement of illegal structures.

REMARKS:
Project Length : 394.40m
Project Width : Sta. 0+000 - 0+315 - 13.46m; Two-Lanes Road with Curb and Gutter, and Drainage (Brgy. San Joaquin Side)
Sta. 0+315 - 0+394.40 - 24.80m; Four-Lanes Road With Shoulder, Curb and Gutter, Drainage, and Sidewalk (CMAR Side)
Construction of road and drainange connecting Clark Mabalacat Access Road with provision of Solar Studs, Solar Street Lights, Road Signages, Pedestrian
Crossings, Intersection Box, Rumble Strips, and Grouted Rip rap.

Prepared by Checked and Submitted by:

FRANZ DOMINIC S. ARCEO EDWARD D. GARCIA


Project Engineer Chief, Construcition Section

Concurred :

PRIME PAVE CONSTRUCTION AND ASPHALT CORPORATION


Contractor

Note : Report on Contract Profile and Status may also be generated from the PCMA