MT. PB BOONNADA 29 June 2024
Duration Sea water FW consumed Distillated water
No. Description Remark
(Minuted) (Cu.M.) (Cu.M.) consumed (Drum)
1 Prepare tank cleaning and pipe system. (COT. 1W-5W) 120 Maximum Temperature can be operate at 60˚C
Butterworth with Hot Sea water at 40˚C to 70˚C for 60 minutes per Tanks is cleaned by Butterworthing each piar tanks that
3 tank. (Washing each pair tanks) 360 188.00 5W>4W>3W>2W>1W
Taking FW. For Re-Circulation at 40˚C to 70˚C for 15 minutes per Tanks is cleaned by Butterworthing each piar tanks that
4 tank. (Washing each pair tanks) 50 47.00 5W>4W>3W>2W>1W
Re-Circulation FW+Detergent/ Solvent cleaner water at 40˚C to Tanks is cleaned by Butterworthing each piar tanks that
5 70˚C for 240 minutes per tank. (Washing each pair tanks) 1,200 5W>4W>3W>2W>1W
Butterworth with Fresh water at at ambient temperature for 20 Tanks is cleaned by Butterworthing each piar tanks that
6 minutes per tank. (Washing each pair tanks) 100 62.60 5W>4W>3W>2W>1W
7 Draining of tanks, lines and pumps. 90
8 De-Slop to Sloap Barge at India 360
9 Tank cleaning SL. W 18.8 12.53 After De-Slop (Seq. No. 9), Ship can departure.
10 Prepare gas freeing-fan and pipe system. 90
8 Ventilation for 9 hours/Tank (each that 5 tanks as per operation) 1,080
9 Rinse Distilled water to Cargo tanks's Wall 720 2.00 Additional operation./ DI-water through into Underwater
10 Mopping tanks to dry and clean. 360
11 Ventilation for 9 hours/Tank (each that 5 tanks as per operation) 1,080 Additional operation.
12 Prepare pipe system for loading next voage cargo and Wall wash test 360
Remark :
A. Tank cleaning time = 2,140/60 mins.= 36 hrs or 1 day 12 hours.
B. Fresh water consumed = 114.0 m3
C. Distilled water consumed = - Drums.
D.Detergent consumed = 1 Drums.
E. Slop Annex I = 114.0 m3
Total
1. Fresh water consumed = 114.0 m3
2. Distilled water consumed = - Drums.
3.Detergent consumed = 2 Drums.
4. Slop Annex I = 114.0 m3 + 1P Slop = 47.0 m3 = Total 161.0 m3
5. Duration Slop barge alongside = 280/60 mins.= 4 hrs 40 mins.