Professional Documents
Culture Documents
Inspection Request Form
Inspection Request Form
Signature Signature
Name Name
Title Project Engineer (Contractor) Title PPMIU Resident Engineer
Date/Time
Result of Inspection
Inspected by:
Testing Needed Survey Needed
Signature Yes No Yes No
Name
Title PPMIU Resident Engineer
Date
Time
1 "Construction activity for which inspection is requested" shall be the activity defined in the Inspection and Test Plan (ITP) that
requires inspection. The reference pay item number shall be that stated in the BOQ which covers the activity subject to
inspection. The location shall define clearly the place/position of the item to be inspected. The date and time shall indicate the
expected inspection time. These shall be no less than 24hours before the time of receipt of the IRF by the PPMIU - RE.
2 The "Request by" box for the IRF shall be filled in and signed by the Contractor's personnel at the project manager level or that
equivalent to the level of the RE
3 The result of the Inspection shall be filled out by the inspector concerned. Additional tests or survey tick boxes shall also be
determined by the inspector, after which, he/she signs at the "Inspected by" box
4 Test/ Survey Results shall be filled in by the PPMIU - RE, after which he signs at the "Test/ Survey Witnessed by" box.
5 The "Request to Proceed" box is to be filled in by the PPMIU Engineer(Provincial Engineer), whether it is approved or
disapproved, based on the results of inspection/ test/ survey, after which, the PPMIU Engineer(Provincial Engineer) affixes
his/her signature, date and time of approval / disapproval.
Note:
1 Approval by the PPMIU Engineer of an IRF is not intended, nor is it to be so interpreted, as written acceptance of any of the
Contractor's previously completed work. In other words, throughout the duration of the construction of the project, all the
Contractor's work is subject at all times to the PSO/RPCO,NPCO Engineer's review.
Form No.
Signature Signature
Name KIMBERLY B. PRAIRE Name ELVIE MAE B. MURILLO
Title Project Engineer (Contractor) Title PPMIU Resident Engineer
Date/Time
Result of Inspection
Inspected by:
Testing Needed Survey Needed
Signature Yes No Yes No
Name ELVIE MAE B. MURILLO
Title PPMIU Resident Engineer
Date
Time
1 "Construction activity for which inspection is requested" shall be the activity defined in the Inspection and Test Plan (ITP) that requires
inspection. The reference pay item number shall be that stated in the BOQ which covers the activity subject to inspection. The location
shall define clearly the place/position of the item to be inspected. The date and time shall indicate the expected inspection time. These
shall be no less than 24hours before the time of receipt of the IRF by the PPMIU - RE.
2 The "Request by" box for the IRF shall be filled in and signed by the Contractor's personnel at the project manager level or that
equivalent to the level of the RE
3 The result of the Inspection shall be filled out by the inspector concerned. Additional tests or survey tick boxes shall also be determined
by the inspector, after which, he/she signs at the "Inspected by" box
4 Test/ Survey Results shall be filled in by the PPMIU - RE, after which he signs at the "Test/ Survey Witnessed by" box.
5 The "Request to Proceed" box is to be filled in by the PPMIU Engineer, whether it is approved or disapproved, based on the results of
inspection/ test/ survey, after which, the PPMIU Engineer affixes his/her signature, date and time of approval / disapproval.
Note:
1 Approval by the PPMIU Engineer of an IRF is not intended, nor is it to be so interpreted, as written acceptance of any of the Contractor's
previously completed work. In other words, throughout the duration of the construction of the subproject, all the Contractor's work is
subject at all times to the RPCO,PSO,NPCO Engineer's review