08-Dec-22

Sub:- Contract DM/CN/COR-OF/027: Construction of elevated viaduct including RRTS stations from end of
Ghaziabad RRTS station till EPE Crossing incl. 2 station Guldhar & Duhai.

HANDING OVER STATUS -LIFT, ESCALATOR,FOB, DG ROOM & PUMP ROOM


Handing Over to
Status of Handing Over by Civil Back Handover
S.no Activity Description E&M after Finishing
Contractor Date from E&M
Work
I. GULDHAR RRTS STATION
1 LIFT SHAFT incl. SERVICE SHAFT
a LIFT -01 (Pkt-B)-( G-C) Handed over to E&M Handed Over
b LIFT -02 (Pkt-A)-( G-C) Possession of LAND is pending D+60
c LIFT-03 (Grid-4-4')-(C-P) LHS Handed over to E&M Handed Over
d LIFT-04 (Grid-4-4')-(C-P) RHS Handed over to E&M Handed Over
e LIFT-05 (Grid-6-7)-(C-P) Future Provisions -
f LIFT-06 (Grid-6-7) -(C-P) Future Provisions -

2 ESCALATOR PIT
a Escalator-1 (Pkt-B)-( G-C) Handed over to E&M Handed Over
b Escalator-2 (Pkt-A)-( G-C) NO LAND D+60
c Escalator-3 (Grid-5'-6)-(C-P) Handed over to E&M Handed Over
d Escalator-4 (Grid-5'-6)-(C-P) Handed over to E&M Handed Over

3 DG ROOM Blockwork in Progress 15-Dec-22

4 PUMP ROOM Handed Over for E&M & Finishing Works Handed Over

5 FOB Connection Pkt-A Possession of LAND is pending D+90


FOB Connection completed & Handed over for
6 FOB Connection Pkt-B PEB works
Handed Over

II. DUHAI RRTS STATION

1 LIFT SHAFT incl. SERVICE SHAFT


To be handed over to finishing Contractor by 05-
LIFT -01 (Grid-2'-3)-( C-P)-LHS 10-Jan-23
a Dec-22
To be handed over to finishing Contractor by 05-
LIFT-02 (Grid-2'-3)-( C-P)-LHS 10-Jan-23
b Dec-22
Reinf. Work is in Progress, To be handed over
LIFT-03 (Grid-6-6') -( C-P)-LHS 30-Dec-22
c to finishing Contractor by 25-Nov-22
Reinf. Work is in Progress, To be handed over
LIFT-03 (Grid-6-6') -( C-P)-RHS 30-Dec-22
d to finishing Contractor by 25-Nov-22
ENTRY-EXITS

ENTRY-EXITS-POCKET-A 31-Jan-23
e No Land
Casting of Footing in progress. To be handed
ENTRY-EXITS-POCKET-B 20-Dec-22
f over to finishing Contractor by 15-Dec-22

ENTRY-EXITS-POCKET-C D+60
g No Land

ENTRY-EXITS-POCKET-D Handed over to E&M Handed Over


h

2 ESCALATOR PIT
a Escalator-1 (Grid 3-3')-C-P LHS Handed over to E&M Handed Over

b Escalator-2 (Grid 3-3')-C-P LHS Handed over to E&M Handed Over

c Escalator-3 (Grid 5'-6)-C-P-LHS Handed over to E&M Handed Over

d Escalator-4 (Grid 5'-6)-C-P-RHS Handed over to E&M Handed Over


08-Dec-22
Sub:- Contract DM/CN/COR-OF/027: Construction of elevated viaduct including RRTS stations from end of
Ghaziabad RRTS station till EPE Crossing incl. 2 station Guldhar & Duhai.

HANDING OVER STATUS -LIFT, ESCALATOR,FOB, DG ROOM & PUMP ROOM


Handing Over to
Status of Handing Over by Civil Back Handover
S.no Activity Description E&M after Finishing
Contractor Date from E&M
Work
ENTRY-EXITS

e ENTRY-EXITS-POCKET-A Excavation is in progress 31-Jan-23

f ENTRY-EXITS-POCKET-B Work In Progress 10-Jan-23

g ENTRY-EXITS-POCKET-C No Land D+60

h ENTRY-EXITS-POCKET-D Handed over to E&M Handed Over

To be handed over to finishing Contractor by 20-


3 DG ROOM Dec-22
25-Jan-23
Wall Casting in progress. To be handed over to
4 PUMP ROOM finishing Contractor by 05-Dec-22
15-Jan-23

5 FOB Connection Pkt-A No Land of Entry Exit 31-Jan-23

6 FOB Connection Pkt-B 31-Jan-23

7 FOB Connection Pkt-C No Land of Entry Exit D+90

8 FOB Connection Pkt-D 20-Dec-22