Sub:- Contract DM/CN/COR-OF/049: Construction of elevated viaduct from start of elevated ramp near Sahibabad RRTS
Station upto end of Ghaziabad RRTS Station, including all special spans and two nos. of elevated RRTS Stations viz., Sahibabad and
Ghaziabad [excluding Architectural Finishing & Roof structure of Stations] of Delhi – Meerut Regional Rapid Transit System (RRTS)
Corridor.
HANDING OVER STATUS -LIFT, ESCALATOR,FOB, DG ROOM & PUMP ROOM
Status of Handing Over by Civil Handing Over to E&M after Back Handover Date from
S.no Activity Description
Contractor Finishing Work E&M
I. SAHIBABABD RRTS STATUS
1 LIFT SHAFT incl. SERVICE SHAFT
a LIFT -01 (Pkt-A)-( G-C) Handed over to E&M Handed Over
2 ESCALATOR PIT
a Escalator-1 (Grid 5-6 LHS)- (C-P-02nos) Handed over to E&M Handed Over
b Escalator-2 (Grid 5-6 RHS)- (C-P-02nos) Handed over to E&M Handed Over
c Escalator (EE-3) Pkt-A (LHS1) Handed over to E&M Handed Over
d Escalator (EE-4) Pkt-B (LHS2) Work In Progress 25-Dec-22
e Escalator (EE-1) Pkt-C (RHS1) Work In Progress 25-Dec-22
4 PUMP ROOM Handed over to E&M & Finishing Contractor Handed Over
To be Handed over to PEB Contractor on 15-
5 FOB Connection Pkt-A Nov-22
Handed Over
2 ESCALATOR PIT
Escalator-1
a Handed over to E&M Handed Over
(Grid 4-5 LHS)-C-P-01nos
Escalator-2
b Handed over to E&M Handed Over
(Grid 4-5 RHS)-C-P-01nos
Escalator-3
c Handed over to E&M Handed Over
(Grid 4-5 CNTR)-C-P-01nos
Escalator-4
d Handed over to E&M Handed Over
(Grid 5-6 LHS)-C-P-01nos
Escalator-5
e Handed over to E&M Handed Over
(Grid 5-6 RHS)-C-P-01nos
Escalator-6
f Handed over to E&M Handed Over
(Grid 5-6 CNTR)-C-P-01nos
ENTRY-EXITS
g Escalator (EE 3-1nos) Pkt-A (LHS1)-G-LPD D+90
h Escalator (EE 4-1nos) Pkt-B (LHS1)-G-LPD Possession of LAND pending D+90
i Escalator (EE 5-1nos) Pkt-C (RHS3)-G-LPD Excavation in progress 10-Feb-23
ENTRY-EXITS-POCKET-D
j Escalator Pit (G-C) Grid 1'-2' Pit work is in Progress 10-Jan-23
k Escalator Grid 6-7' (RHS2) -LPD- C 10-Jan-23
Status of Handing Over by Civil Handing Over to E&M after Back Handover Date from
S.no Activity Description
Contractor Finishing Work E&M
3 DG ROOM Slab Casting in progress 15-Dec-22