08-Dec-22

Sub:- Contract DM/CN/COR-OF/049: Construction of elevated viaduct from start of elevated ramp near Sahibabad RRTS
Station upto end of Ghaziabad RRTS Station, including all special spans and two nos. of elevated RRTS Stations viz., Sahibabad and
Ghaziabad [excluding Architectural Finishing & Roof structure of Stations] of Delhi – Meerut Regional Rapid Transit System (RRTS)
Corridor.
HANDING OVER STATUS -LIFT, ESCALATOR,FOB, DG ROOM & PUMP ROOM
Status of Handing Over by Civil Handing Over to E&M after Back Handover Date from
S.no Activity Description
Contractor Finishing Work E&M
I. SAHIBABABD RRTS STATUS
1 LIFT SHAFT incl. SERVICE SHAFT
a LIFT -01 (Pkt-A)-( G-C) Handed over to E&M Handed Over

b LIFT-02 (Pkt-B)-(G-C) Foundation Work in progress 31-Dec-22

c LIFT-03 (Pkt-C)-(G-C) Work in Progress 25-Dec-22

d LIFT-04 (Grid-3)-(C-P) Handed over to E&M Handed Over

e LIFT-05 (Grid-3) -(C-P) Handed over to E&M Handed Over

2 ESCALATOR PIT
a Escalator-1 (Grid 5-6 LHS)- (C-P-02nos) Handed over to E&M Handed Over
b Escalator-2 (Grid 5-6 RHS)- (C-P-02nos) Handed over to E&M Handed Over
c Escalator (EE-3) Pkt-A (LHS1) Handed over to E&M Handed Over
d Escalator (EE-4) Pkt-B (LHS2) Work In Progress 25-Dec-22
e Escalator (EE-1) Pkt-C (RHS1) Work In Progress 25-Dec-22

3 DG ROOM Handed over to E&M for Conduting etc. Handed Over

4 PUMP ROOM Handed over to E&M & Finishing Contractor Handed Over
To be Handed over to PEB Contractor on 15-
5 FOB Connection Pkt-A Nov-22
Handed Over

6 FOB Connection Pkt-B 06-Jan-23

7 FOB Connection Pkt-C Work in progress 10-Jan-23

II. GHAZIABAD RRTS STATUS


1 LIFT SHAFT incl. SERVICE SHAFT
a LIFT -01 (Grid-3)-( C-P)-LHS Slab casting Done. Preparing for Handover. 09-Dec-22
b LIFT-02 (Grid-3) -( C-P)-CENTRE Slab casting Done. Work in Progress. 12-Dec-22
c LIFT-03 (Grid-3) -( C-P)-RHS Wall casting complete. MS work in progress 19-Dec-22
ENTRY-EXITS
d ENTRY-EXITS-POCKET-A D+90
e ENTRY-EXITS-POCKET-B Possession of LAND pending D+90
f ENTRY-EXITS-POCKET-C Excavation in progress 20-Feb-23
g ENTRY-EXITS-POCKET-D
Lift Shaft-11& 12 (G-C) Grid-3-01 no. Wall casting in progress 05-Jan-23

Lift Shaft-13 (UPD-Concourse) Grid-1-1'-01no. Wall casting in progress 05-Jan-23

2 ESCALATOR PIT
Escalator-1
a Handed over to E&M Handed Over
(Grid 4-5 LHS)-C-P-01nos
Escalator-2
b Handed over to E&M Handed Over
(Grid 4-5 RHS)-C-P-01nos
Escalator-3
c Handed over to E&M Handed Over
(Grid 4-5 CNTR)-C-P-01nos
Escalator-4
d Handed over to E&M Handed Over
(Grid 5-6 LHS)-C-P-01nos
Escalator-5
e Handed over to E&M Handed Over
(Grid 5-6 RHS)-C-P-01nos
Escalator-6
f Handed over to E&M Handed Over
(Grid 5-6 CNTR)-C-P-01nos
ENTRY-EXITS
g Escalator (EE 3-1nos) Pkt-A (LHS1)-G-LPD D+90
h Escalator (EE 4-1nos) Pkt-B (LHS1)-G-LPD Possession of LAND pending D+90
i Escalator (EE 5-1nos) Pkt-C (RHS3)-G-LPD Excavation in progress 10-Feb-23
ENTRY-EXITS-POCKET-D
j Escalator Pit (G-C) Grid 1'-2' Pit work is in Progress 10-Jan-23
k Escalator Grid 6-7' (RHS2) -LPD- C 10-Jan-23
Status of Handing Over by Civil Handing Over to E&M after Back Handover Date from
S.no Activity Description
Contractor Finishing Work E&M
3 DG ROOM Slab Casting in progress 15-Dec-22

4 PUMP ROOM Work in progress 31-Dec-22

5 FOB Connection Pkt-A D+90

6 FOB Connection Pkt-B Possession of LAND pending D+90

7 FOB Connection Pkt-C Excavation in progress 20-Feb-23