Professional Documents
Culture Documents
Mechanistic Model for the Prediction of Top-of-the-Line Corrosion Risk
Mechanistic Model for the Prediction of Top-of-the-Line Corrosion Risk
Mechanistic Model for the Prediction of Top-of-the-Line Corrosion Risk
EXPERIMENTAL PROCEDURES and outlet temperature of the gas bulk, the inside
wall temperature at a position close to where the cor-
Experimental Setup and Procedure rosion probe is installed, the total pressure, the gas
To reproduce the conditions encountered in the velocity, the temperature at the inlet and outlet of the
field during the production of wet gas, a full-scale cooling liquid, the cooling liquid flow rate, and the
flow loop was built in our laboratories. The schematic corrosion rate. Figure 2 shows the design of the heat
of the loop is given in Figure 1. The experimental pro- exchanger, the insertion ports for the flush-mounted
cedure is as follows: CO2 was injected first in the flow probes, and the position of the data acquisition for
loop up to a specific pressure. In a 1-m3 stainless temperatures and flow rates. The temperature of the
steel (SS) tank, water was then heated by electrical probe head was also continuously monitored using
heaters up to the temperature of interest. The total the Ceion† technology (resolution: ±0.5°C): the probe
pressure was recorded. The pump was then started head is made of two identical sensing elements with
and the mixture of CO2 and water vapor flowed in the the shape of two concentric spirals. One of the spi-
4-in. SS loop until steady-state conditions were rals, coated by a thin layer of epoxy, is immune to
reached in the gas phase inside the pipe. A counter- corrosion and serves both purposes of temperature
current double-pipe heat exchanger was used to cool compensation and temperature monitoring. Since
the gas mixture and control the condensation rate. both elements are physically very close and subject
The coolant used for this specific application was to the same external conditions, it can be assumed
water. The condensed water was collected in a pres- that they have the same temperature. Therefore, the
sure vessel; this configuration allows sampling temperature of the corroding element was known and
without disturbing the flow and the pressure in the could be set identical to the surrounding wall tem-
loop. The measured condensation rate was equal to perature by an air-cooling system built within the
the amount of water condensed in the heat ex- probe body.
changer divided by its surface area and by the time
of experimentation. Setup and Data Acquisition
The real-time measurement of the corrosion rate for Corrosion Measurement
starts once a steady state was attained. Data acquisi- During TLC, it is particularly important to know
tion devices are set to continuously measure the inlet the local wall temperature on the inner pipewall in
addition to the bulk gas temperature. There are two
†
Trade name. reasons for this:
—Because the fluid transported is gas, and be- used. For each experiment, the measurement ob-
cause significant heat exchanges occur at the tained with CWL was within ±40% of the correspond-
wall, an important temperature gradient can ing ER measurement.
occur between the bulk phase and the wall.
In such a case, the wall temperature is more RESULTS
adapted than the bulk temperature to predict
the kinetics of the electrochemical reaction of In some cases, the effect of some primary param-
corrosion. eters on the condensation rate and on the corrosion
—The condensation rate of water vapor will be rate could be isolated by keeping the other param-
dependent on the heat and mass transfer in eters of experimentation as constants. In other cases,
the gas phase. These transfers are related the parameters of interest were coupled and so is
to the gradient of temperature occurring be- their effect on the corrosion and condensation rates.
tween the gas bulk and the pipewall. Thus, All the following tests were run over a period of time
an accurate measurement and control of the from 48 h to 120 h. For each test, the corrosion rate
wall temperature is needed to set the local reported was the stabilized rate (the corrosion rate
condensation rate. was considered stable when no change >0.05 mm/y
For these reasons, the probe used for the mea- occurred during a period of time of at least 12 h). For
surement of the corrosion rate must be kept at the each experiment, which was repeated many times,
same temperature as the rest of the wall. A new the error bar shown in Figures 3 through 5 repre-
technology of “air-cooled” corrosion probe is used sents the standard error. However, some experiments
and validated for this specific project. By allowing a were not reproduced. For these experiments, the er-
flow of air through the body of the probe, the tem- ror bars reported correspond to the standard error as
perature of the sensing element can be kept identical calculated for the experiment: T = 50°C, PCO2 = 4 bar,
to the wall temperature. A data acquisition system gas velocity = 4 m/s, high cooling. These error bars
linked to a thermosensor in the probe head allows are given as a support of the quantitative description
such monitoring. of the phenomena observed and to validate the quan-
The electrical resistance (ER) measurement tech- titative conclusions that are drawn.
nique is used during experimentation on TLC. The
air-cooled probe used for this specific application Influence of the Bulk Temperature
had a 1-mm-thick sensor; the resolution for such a and the Wall Temperature on the Corrosion Rate
thickness was 5 nanometers.4 Electrochemical tech- The influence of temperature was studied over a
niques were avoided for several reasons: the conduc- range from 40°C to 100°C. First, as the temperature
tivity of condensed water may be too low to give a increased up to 70°C to 80°C, the corrosion rate in-
reasonable reading. Also, at low condensation rates, creased as well. Then, the trend is reversed and the
the condensed water film on the probe head may not corrosion rate decreases as the temperature in-
be continuous, preventing the current from flowing creases to 90°C. The condensation rate, however,
between the working and the counter electrodes. keeps increasing as the temperature increases
Some additional coupon weight loss measure- (Figure 5). As can be seen from Figure 3, the same
ments (CWL) were run simultaneously to ER to trend showing a maximum corrosion rate between
validate the experimental results. For CWL measure- 70°C and 80°C was observed depending on the CO2
ments, the same type probe body (air-cooled) was partial pressure.
FIGURE 10. Comparison of the experimental and theoretical FIGURE 11. Comparison of the experimental and theoretical
corrosion rates. Influence of temperature. PCO2 = 8 bar. corrosion rates. Influence of the partial pressure of carbon dioxide.
Tgas = 80°C.
∆t
[Fe2 + ]t + dt = [Fe2 + ]t + ×
δ
. 2+ (10)
FIGURE 12. Comparison of the experimental and theoretical Φ c ( t ) – Φ p ( t ) – m × [Fe ]t
corrosion rates. Influence of the condensation rate. Tgas = 50°C,
PCO2 = 4 bar.
The computational procedure, which solves Equa-
tions (2) through (6) and (10) simultaneously,
determines the change in pH and the ferrous ion
d( V × [Fe2 + ]) concentration with time. The corresponding corrosion
= Φc × A c – Φ p × A p
dt rate was calculated and allowed for the prediction of
. (8) the new concentration of ferrous ions at the next
– m × A cond × [Fe2 + ]
time step. The iteration was continued until no addi-
tional change in the ferrous ion concentration was
V is volume of condensed water (m3), [Fe2+] is concen- computed.
tration of ferrous ions in solution (kmol/m3), Φc is Experimental and theoretical corrosion rates, as
corrosion rate (kmol/m2/s), Ac is the area where well as the corrosion rate according to de Waard’s
corrosion takes place (m2), Φp is precipitation rate model (presently modified to take into consideration
(kmol/m2/s), Ap is the area where precipitation takes the mass transfer in the condensed film as described
•
place (m2), m is condensation rate (m3/m2/s), and previously), are also plotted against the temperature,
Acond is the area where condensation takes place (m2). the partial pressure, and the condensation rate in
If one assumes that the area of corrosion, precipita- Figures 10 through 12, respectively. In general, the
tion, and condensation are equal and if it is further corrosion rate was overpredicted by both of the mod-
assumed that the condensed film thickness, δ, is els. Moreover, the present model showed an increase
known, Equation (8) becomes: in the corrosion rate as the temperature increaseed
above 80°C whereas the experimental corrosion rate
decreased above such temperature. The overpredic-
(
d [Fe2 + ] ) = 1 × Φ .
– Φ p – m × [Fe2 + ] (9) tion of the corrosion rate is due to the fact that fur-
dt δ c
ther protection of the depositing FeCO3 scale on the
or ✜
technology
And much more!
covers? Professionally printed reprints and photocopied reprints are available
of all CORROSION ads, articles, and covers. Reprints can be customized
with your company’s logo, additional product information, or the
magazine cover—with no limits on creativity!
CORROSION
THE JOURNAL OF SCIENCE AND ENGINEERING