Professional Documents
Culture Documents
002-BW-IM 418-MSS-002-MSS for Lighting Control system
002-BW-IM 418-MSS-002-MSS for Lighting Control system
002-BW-IM 418-MSS-002-MSS for Lighting Control system
Submittal type:
SM Sample GT Guarantees MD Manufacturer’s Data CA Calculations
MS Method Statement CT Certificate TT Test Results OT Others
As Specified Alternative
We are sending herewith below listed:
Received by BW Interiors
Name:
Date:
Signature:
METHOD OF STATEMENT
har
PROJECT:
Mckinsey Office
Page 1 of 20
METHOD OF STATEMENT LIGHTING CONTROLS
This document has been prepared by Lightlink Electrical Trading LLC to describe the methods, extent,
format and standards to be employed for Testing and Commissioning.
• Description of methods and equipment to be used for each operation and sequence of
operations.
• Safety precautions to ensure safety of workers and users of adjacent facilities.
• Co-ordination with any existing facility operations.
Risk assessment, Method Statement & Site Safety Inspection to be completed and approved prior
to job start. Findings to be presented as Toolbox talk prior to Job Start.
Permit to work to be obtained from project safety team prior to activity.
Project Charge hand/ Supervisor to carry out Site Health & Safety Inspection and brief the activity
to work force prior to any work commencing.
Exclusion zone, necessary signage & watch person (if required) have to be provided before start
the activity.
Only when permit to work are available for the location and job is deemed safe should work
commence.
The following equipment / tools will be deployed on site to carry out the activity.
Description Quantity
Laptop 1
Screwdriver 1
Multimeter 1
Tester 1
Responsibilities
• Responsible for controlling the project’s entire activities & for the
overall coordination with the consultant/client.
• Will make sure that all the works mentioned in this method
statement will carry out in approved shop drawing and as per
the project specification.
• Will make sure WIR for all these activities are raised and
approved by the consultant and recording those documents
for testing, commissioning, and for handing over the procedure.
Safety Manager
• Will ensure that the worksite has been examined, and all
precautions specified to be taken in the PTW before work
commences have in fact been taken.
Electrical Foreman
• Electrical Technician/Electrician
19
Workforce
• Carry out their work in such a way that they don’t create for
themselves or any other person risk to health safety, and don’t
impact the environment to the maximum extent possible or
affect the quality of work.
• Carry out their work in such a way that they don’t create for
themselves or any other person risk to health safety, and don’t
impact the environment to the maximum extent possible or
affect the quality of work.
• Helmet
• Safety Boots
• Safety Jacket
20
METHOD OF STATEMENT LIGHTING FIXTURES
The scope of this document includes, but not limited to the following:
• Quality Control
Sequence Of Works For The Method Statement Of Lighting Fixtures and Wirings System
The following are the step-by-step procedure for the installation of light fixtures & wiring
devices and accessories.
• Materials found not suitable for site use will be removed from
the site immediately. While unloading, shifting, and storage, it
will be ensured that there are no damages. All delivered
materials will be inspected on arrival at the site.
• Materials found not suitable for site use will be removed from
the site immediately and moves to the quarantine zone.
• Where fixtures are suspended from the structure, they will utilize
self-aligning box covers with an additional ground wire from
the outlet through the hanger for continuity of ground.
Wiring Termination
• Will make sure all the wiring installations are completed and
the wires will be tested for insulation and continuity test before
termination.
• Wires will be cut according to the proper length and fix the
necessary lugs for the proper termination to the ceiling rose as
per the approved shop drawing.
• Prior to terminations, it will be ensured that all wires are
provided with proper identification ferrule/labels.
• A-Type ladder
The foremen and engineers on-site will ensure that all necessary
equipment is available as well as fit and safe prior to commencement
of work.
Project Manager
• Responsible for controlling the project’s entire activities & for the
overall coordination with the consultant/client.
• Will make sure that all the works mentioned in this method
statement will carry out in approved shop drawing and as per
the project specification.
• Will make sure WIR for all these activities are raised and
approved by the consultant and recording those documents
for testing, commissioning, and for handing over the procedure.
Safety Manager
• Will ensure that the worksite has been examined, and all
precautions specified to be taken in the PTW before work
commences have in fact been taken.
Electrical Foreman
• Electrical Technician/Electrician
• Carry out their work in such a way that they don’t create for
themselves or any other person risk to health safety, and don’t
impact the environment to the maximum extent possible or
affect the quality of work.
• Carry out their work in such a way that they don’t create for
themselves or any other person risk to health safety, and don’t
impact the environment to the maximum extent possible or
affect the quality of work.
Quality Controls For Method Statement Of Lighting Fixtures And Wirings System
The Inspection and Test Plan (ITP) for this Method Statement of Lighting
Fixtures and Wirings System summarize various characteristics to be
checked. The concerned Site Engineer or Site Supervisor will be
responsible to ensure compliance for these operations and the site
QA/QC Engineer will carry out quality control checks and report the
inspection results.
Quality Records