1002.02
Shree Distillery Pvt. Ltd
Arun Khola, Nawalparasi
Fy: 2079-080
Abstract Of Cost
Date:2079/10/11
Name of project:-Construction of Water reservoir, Septic Tank and other Civil works at Factory Site.
Location: Arun Khola, Nawalparasi
S.No. Description of Work Unit Quantity Rate Amount
Earthwork in backfilling with oridinary soil
in 15 cm thick layer with compaction and
including supply of amterials at site
watering compaction and dressing all
1 complete work with all necessary lead and Cum 4018 803.71 3,229,306.78
lift as per drawing, specification &
approval of Engineer
Remarks
13275
Shree Distillery Pvt. Ltd
Arun Khola, Nawalparasi
Fy: 2079-080
Detail Estimate
Name of project:-Construction of Water reservoir, Septic Tank and other Civil works at Factory Site.
Location:-Arun Khola, Nawalparasi
S.N. Description of work No. Length Breath Height Qty Unit
1 Plum concrete retaining wall
section 1 1 18.56 1.5 4.5 125.28 cum
section 2 1 15 1.5 3.5 78.75 cum
section 3 1 16.5 1.5 3.2 79.2 cum
section 4 1 25 1.5 4 150 cum
section 5 1 27 1.5 4.3 174.15 cum
section 6 1 16 1.5 4.5 108 cum
section 7 1 14 1.5 4.5 94.5 cum
section 8 1 17.5 1.5 4.5 118.125 cum
Sub total 149.56 928.005 cum
Remarks
13.Description of item:-Pcc for RCC work 1:1.5:3 in beam,slab with Unit quantity:-1Cum.
approved material including laying,compactio and curring all complete lead upto 30m
Approved
S.N Description of labour & materials Quantity Units rate Amount Rs.
A Labour
1.Skilled labour 0.8 Md 1200 960
2.Unskilled labour 7" 700 4900
B Material
1.Cement 0.192 Mt 20051.00 3849.79
2.Stone 0.66 m3 1250.00 825.00
2.Aggregate 20mm 0.378 m3 3031.00 1145.72
3.Aggregate 10mm 0.132 m3 3858.00 509.26
4.Approved sand 0.255 " 2358.90 601.52
5.Water 120 litre 0.40 48.00
Sub Total 12839.29
15%contractor's overhead 1925.89
Total 14765.18