Professional Documents
Culture Documents
3341 - Baseline Time Schedule
3341 - Baseline Time Schedule
Duration
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
3341 - ABU DHABI LUXURY ISLAND DESIGN PROGRAMME - Baseline 296
with Budget
16-Jun-23 22-Aug-24
Remaining Level of Effort Actual Work Critical Remaining Work Summary Page 1 of 17
Actual Level of Effort Remaining Work Milestone
Activity Name Original Start Finish 2023 2024
Duration
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
Advise on roads geometry and coordinate with Master Plan 5 13-Jul-23 19-Jul-23
Available Tie-in Points 5 20-Jul-23 27-Jul-23
Estimate Utilities Load demands 5 16-Aug-23 22-Aug-23
Utilities Building size estimate 5 16-Aug-23 22-Aug-23
Early Scheme for Infra Networks (Brief BOD) and options studies 5 16-Aug-23 22-Aug-23
Prepare GIS Drawings 10 18-Aug-23 31-Aug-23
Pre-Concept Master Plan 18 19-Jun-23 17-Jul-23
Remaining Level of Effort Actual Work Critical Remaining Work Summary Page 2 of 17
Actual Level of Effort Remaining Work Milestone
Activity Name Original Start Finish 2023 2024
Duration
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
Key Milestones 63 08-Sep-23 08-Dec-23
Foundation Package Submission 0 08-Sep-23
MEP1st Fix Drawings 0 15-Sep-23
MEPMain Equipment Package 0 15-Sep-23
Internal Finishes Package Submission 0 24-Oct-23
External Facade Finishes Package Submission 0 31-Oct-23
Precast Design Package 0 06-Nov-23
100% Detailed Design Package Submission 0 22-Nov-23
IFC Package Submission 0 08-Dec-23
Gateway 1 36 10-Jul-23 29-Aug-23
Initial Concept Presentation 7 10-Jul-23 18-Jul-23
Fixed Floor Plans 7 19-Jul-23 28-Jul-23
Interior Design Mood Board 2 31-Jul-23 01-Aug-23
Structure Elements Coordination 3 31-Jul-23 02-Aug-23
MEPSpace Requirment Package 3 31-Jul-23 02-Aug-23
Facade Concept Design 2 03-Aug-23 04-Aug-23
Landscape Concept Package 7 31-Jul-23 08-Aug-23
Facade Engineering Review 7 07-Aug-23 15-Aug-23
Estidama Target Score Card 1 22-Aug-23 22-Aug-23
Facade Lighting Concept Design 5 16-Aug-23 22-Aug-23
Client Consent - Gateway 1 5 23-Aug-23 29-Aug-23
Gateway 2 33 28-Aug-23 12-Oct-23
BIM Verification 2 28-Aug-23 29-Aug-23
Structure Statical System Coordination - Revit Model 4 30-Aug-23 04-Sep-23
Facade Lighting Design&Coordination 1 06-Sep-23 06-Sep-23
Facade Engineering, Special Facade details 2 05-Sep-23 06-Sep-23
External Utilities, Coordinate Tie-in location & Capacity 1 07-Sep-23 07-Sep-23
ID Coordination Package & RCP( 50% ID Package) 3 06-Sep-23 08-Sep-23
Landscape Coordinate with the building Levels & materials 1 08-Sep-23 08-Sep-23
Foundation Package 4 05-Sep-23 08-Sep-23
50% Landscape Package 5 04-Sep-23 08-Sep-23
MEP1st Fix Drawings 10 04-Sep-23 15-Sep-23
MEPMain Equipment Package Preparation 10 04-Sep-23 15-Sep-23
50% Detailed Design Package 28 30-Aug-23 09-Oct-23
Estidama, Provide Energy Model 2 10-Oct-23 11-Oct-23
Client Consent - Gateway 2 5 06-Oct-23 12-Oct-23
Gateway 3 34 13-Oct-23 29-Nov-23
Acoustic Validation 4 13-Oct-23 18-Oct-23
Finalize Structure Coordination 7 13-Oct-23 23-Oct-23
100% ID Package & Materials Cut Sheets 0 24-Oct-23
Finishes Schedules 5 19-Oct-23 25-Oct-23
Finalize Coordinated RCP 3 24-Oct-23 26-Oct-23
Landscape Design & Coordination 2 26-Oct-23 27-Oct-23
External Lighting Landscape 2 30-Oct-23 31-Oct-23
Precast Design Drawings 7 27-Oct-23 06-Nov-23
Fire & Life Safety Drawings 5 01-Nov-23 07-Nov-23
Structure Third Party Stamp 3 07-Nov-23 09-Nov-23
FLS Third Party Stamp 3 08-Nov-23 10-Nov-23
Precast Fabrication Package 7 10-Nov-23 20-Nov-23
Estidama Final Score Card 2 21-Nov-23 22-Nov-23
Remaining Level of Effort Actual Work Critical Remaining Work Summary Page 3 of 17
Actual Level of Effort Remaining Work Milestone
Activity Name Original Start Finish 2023 2024
Duration
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
100% Detailed Design Submission 29 13-Oct-23 22-Nov-23
Client Consent - Gateway 3 5 23-Nov-23 29-Nov-23
Gateway 4 9 30-Nov-23 13-Dec-23
Architectural / Civil & MEPIFC Submission 6 30-Nov-23 08-Dec-23
Interior Design BOQ 4 05-Dec-23 08-Dec-23
Architectural / Civil & MEPBOQ 4 05-Dec-23 08-Dec-23
Landscape BOQ 4 05-Dec-23 08-Dec-23
Specifications 4 05-Dec-23 08-Dec-23
ECG Stamp ID & Landscape BOQ for Construction 2 11-Dec-23 12-Dec-23
ECG Stamp Landscape Design for Construction 2 11-Dec-23 12-Dec-23
ECGReview & Stamp ID Drawings for Construction 2 11-Dec-23 12-Dec-23
Client Consent - Gateway 4 1 13-Dec-23 13-Dec-23
Villa Type V2-SBA 110 10-Jul-23 13-Dec-23
Remaining Level of Effort Actual Work Critical Remaining Work Summary Page 4 of 17
Actual Level of Effort Remaining Work Milestone
Activity Name Original Start Finish 2023 2024
Duration
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
Gateway 3 34 13-Oct-23 29-Nov-23
Acoustic Validation 4 13-Oct-23 18-Oct-23
Finalize Structure Coordination 7 13-Oct-23 23-Oct-23
100% ID Package & Materials Cut Sheets 0 24-Oct-23
Finishes Schedules 5 19-Oct-23 25-Oct-23
Finalize Coordinated RCP 3 24-Oct-23 26-Oct-23
Landscape Design & Coordination 2 26-Oct-23 27-Oct-23
External Lighting Landscape 2 30-Oct-23 31-Oct-23
Precast Design Drawings 7 27-Oct-23 06-Nov-23
Fire & Life Safety Drawings 5 01-Nov-23 07-Nov-23
Structure Third Party Stamp 3 07-Nov-23 09-Nov-23
FLS Third Party Stamp 3 08-Nov-23 10-Nov-23
Precast Fabrication Package 7 10-Nov-23 20-Nov-23
Estidama Final Score Card 2 21-Nov-23 22-Nov-23
100% Detailed Design Submission 29 13-Oct-23 22-Nov-23
Client Consent - Gateway 3 5 23-Nov-23 29-Nov-23
Gateway 4 9 30-Nov-23 13-Dec-23
Architectural / Civil & MEPIFC Submission 6 30-Nov-23 08-Dec-23
Landscape BOQ 4 05-Dec-23 08-Dec-23
Interior Design BOQ 4 05-Dec-23 08-Dec-23
Architectural / Civil & MEPBOQ 4 05-Dec-23 08-Dec-23
Specifications 4 05-Dec-23 08-Dec-23
ECG Stamp ID & Landscape BOQ for Construction 2 11-Dec-23 12-Dec-23
ECG Stamp Landscape Design for Construction 2 11-Dec-23 12-Dec-23
ECGReview & Stamp ID Drawings for Construction 2 11-Dec-23 12-Dec-23
Client Consent - Gateway 4 1 13-Dec-23 13-Dec-23
Villa Type V3-SBA 110 10-Jul-23 13-Dec-23
Remaining Level of Effort Actual Work Critical Remaining Work Summary Page 5 of 17
Actual Level of Effort Remaining Work Milestone
Activity Name Original Start Finish 2023 2024
Duration
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
BIM Verification 2 28-Aug-23 29-Aug-23
Structure Statical System Coordination - Revit Model 4 30-Aug-23 04-Sep-23
Facade Engineering, Special Facade details 2 05-Sep-23 06-Sep-23
Facade Lighting Design&Coordination 1 06-Sep-23 06-Sep-23
External Utilities, Coordinate Tie-in location & Capacity 1 07-Sep-23 07-Sep-23
Landscape Coordinate with the building Levels & materials 1 08-Sep-23 08-Sep-23
Foundation Package 4 05-Sep-23 08-Sep-23
50% Landscape Package 5 04-Sep-23 08-Sep-23
ID Coordination Package & RCP( 50% ID Package) 3 06-Sep-23 08-Sep-23
MEP1st Fix Drawings 10 04-Sep-23 15-Sep-23
MEPMain Equipment Package Preparation 10 04-Sep-23 15-Sep-23
50% Detailed Design Package 28 30-Aug-23 09-Oct-23
Estidama, Provide Energy Model 2 10-Oct-23 11-Oct-23
Client Consent - Gateway 2 5 06-Oct-23 12-Oct-23
Gateway 3 34 13-Oct-23 29-Nov-23
Acoustic Validation 4 13-Oct-23 18-Oct-23
Finalize Structure Coordination 7 13-Oct-23 23-Oct-23
100% ID Package & Materials Cut Sheets 0 24-Oct-23
Finishes Schedules 5 19-Oct-23 25-Oct-23
Finalize Coordinated RCP 3 24-Oct-23 26-Oct-23
Landscape Design & Coordination 2 26-Oct-23 27-Oct-23
External Lighting Landscape 2 30-Oct-23 31-Oct-23
Precast Design Drawings 7 27-Oct-23 06-Nov-23
Fire & Life Safety Drawings 5 01-Nov-23 07-Nov-23
Structure Third Party Stamp 3 07-Nov-23 09-Nov-23
FLS Third Party Stamp 3 08-Nov-23 10-Nov-23
Precast Fabrication Package 7 10-Nov-23 20-Nov-23
100% Detailed Design Submission 29 13-Oct-23 22-Nov-23
Estidama Final Score Card 2 21-Nov-23 22-Nov-23
Client Consent - Gateway 3 5 23-Nov-23 29-Nov-23
Gateway 4 9 30-Nov-23 13-Dec-23
Landscape BOQ 4 05-Dec-23 08-Dec-23
Interior Design BOQ 4 05-Dec-23 08-Dec-23
Architectural / Civil & MEPBOQ 4 05-Dec-23 08-Dec-23
Specifications 4 05-Dec-23 08-Dec-23
Architectural / Civil & MEPIFC Submission 6 30-Nov-23 08-Dec-23
ECG Stamp ID & Landscape BOQ for Construction 2 11-Dec-23 12-Dec-23
ECG Stamp Landscape Design for Construction 2 11-Dec-23 12-Dec-23
ECGReview & Stamp ID Drawings for Construction 2 11-Dec-23 12-Dec-23
Client Consent - Gateway 4 1 13-Dec-23 13-Dec-23
Villa Type (T2) - ECG 68 21-Jun-23 28-Sep-23
Remaining Level of Effort Actual Work Critical Remaining Work Summary Page 6 of 17
Actual Level of Effort Remaining Work Milestone
Activity Name Original Start Finish 2023 2024
Duration
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
Gateway 1 31 21-Jun-23 08-Aug-23
Initial Concept Presentation 7 21-Jun-23 04-Jul-23
Fixed Floor Plans 7 05-Jul-23 13-Jul-23
Interior Design Mood Board 2 14-Jul-23 17-Jul-23
Structure Elements Coordination 3 14-Jul-23 18-Jul-23
MEPSpace Requirment Package 3 14-Jul-23 18-Jul-23
Facade Concept Design 2 19-Jul-23 20-Jul-23
Landscape Concept Package 5 14-Jul-23 20-Jul-23
Facade Engineering Review 5 24-Jul-23 28-Jul-23
Estidama Target Score Card 1 04-Aug-23 04-Aug-23
Facade Lighting Concept Design 5 31-Jul-23 04-Aug-23
Client Consent - Gateway 1 2 07-Aug-23 08-Aug-23
Gateway 2 14 07-Aug-23 24-Aug-23
BIM Verification 2 07-Aug-23 08-Aug-23
Structure Statical System Coordination - Revit Model 4 09-Aug-23 14-Aug-23
Facade Lighting Design&Coordination 1 16-Aug-23 16-Aug-23
Facade Engineering, Special Facade details 2 15-Aug-23 16-Aug-23
External Utilities, Coordinate Tie-in location & Capacity 1 17-Aug-23 17-Aug-23
ID Coordination Package & RCP( 50% ID Package) 3 16-Aug-23 18-Aug-23
Landscape Coordinate with the building Levels & materials 1 18-Aug-23 18-Aug-23
Foundation Package 4 15-Aug-23 18-Aug-23
50% Landscape Package 5 14-Aug-23 18-Aug-23
MEP1st Fix Drawings 6 14-Aug-23 21-Aug-23
MEPMain Equipment Package Preparation 6 14-Aug-23 21-Aug-23
50% Detailed Design Package 10 09-Aug-23 22-Aug-23
Estidama, Provide Energy Model 2 23-Aug-23 24-Aug-23
Client Consent - Gateway 2 2 23-Aug-23 24-Aug-23
Gateway 3 16 25-Aug-23 15-Sep-23
Finalize Structure Coordination 3 25-Aug-23 29-Aug-23
Acoustic Validation 3 25-Aug-23 29-Aug-23
100% ID Package & Materials Cut Sheets 0 30-Aug-23
Finalize Coordinated RCP 2 30-Aug-23 31-Aug-23
Finishes Schedules 2 30-Aug-23 31-Aug-23
Landscape Design & Coordination 2 01-Sep-23 04-Sep-23
External Lighting Landscape 2 05-Sep-23 06-Sep-23
Precast Design Drawings 5 01-Sep-23 07-Sep-23
Fire & Life Safety Drawings 2 07-Sep-23 08-Sep-23
FLS Third Party Stamp 2 11-Sep-23 12-Sep-23
Structure Third Party Stamp 3 08-Sep-23 12-Sep-23
Estidama Final Score Card 2 13-Sep-23 14-Sep-23
Precast Fabrication Package 2 13-Sep-23 14-Sep-23
100% Detailed Design Submission 15 25-Aug-23 14-Sep-23
Client Consent - Gateway 3 1 15-Sep-23 15-Sep-23
Gateway 4 9 18-Sep-23 28-Sep-23
Architectural / Civil & MEPIFC Submission 6 18-Sep-23 25-Sep-23
Landscape BOQ 4 20-Sep-23 25-Sep-23
Interior Design BOQ 4 20-Sep-23 25-Sep-23
Architectural / Civil & MEPBOQ 4 20-Sep-23 25-Sep-23
Specifications 4 20-Sep-23 25-Sep-23
ECG Stamp ID & Landscape BOQ for Construction 2 26-Sep-23 27-Sep-23
Remaining Level of Effort Actual Work Critical Remaining Work Summary Page 7 of 17
Actual Level of Effort Remaining Work Milestone
Activity Name Original Start Finish 2023 2024
Duration
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
ECG Stamp Landscape Design for Construction 2 26-Sep-23 27-Sep-23
ECGReview & Stamp ID Drawings for Construction 2 26-Sep-23 27-Sep-23
Client Consent - Gateway 4 1 28-Sep-23 28-Sep-23
Villa Type (T2 - 2) - ECG 68 21-Jun-23 28-Sep-23
Remaining Level of Effort Actual Work Critical Remaining Work Summary Page 8 of 17
Actual Level of Effort Remaining Work Milestone
Activity Name Original Start Finish 2023 2024
Duration
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
FLS Third Party Stamp 2 11-Sep-23 12-Sep-23
Structure Third Party Stamp 3 08-Sep-23 12-Sep-23
Precast Fabrication Package 2 13-Sep-23 14-Sep-23
100% Detailed Design Submission 15 25-Aug-23 14-Sep-23
Estidama Final Score Card 2 13-Sep-23 14-Sep-23
Client Consent - Gateway 3 1 15-Sep-23 15-Sep-23
Gateway 4 9 18-Sep-23 28-Sep-23
Interior Design BOQ 4 20-Sep-23 25-Sep-23
Architectural / Civil & MEPBOQ 4 20-Sep-23 25-Sep-23
Landscape BOQ 4 20-Sep-23 25-Sep-23
Specifications 4 20-Sep-23 25-Sep-23
Architectural / Civil & MEPIFC Submission 6 18-Sep-23 25-Sep-23
ECG Stamp ID & Landscape BOQ for Construction 2 26-Sep-23 27-Sep-23
ECG Stamp Landscape Design for Construction 2 26-Sep-23 27-Sep-23
ECGReview & Stamp ID Drawings for Construction 2 26-Sep-23 27-Sep-23
Client Consent - Gateway 4 1 28-Sep-23 28-Sep-23
Villa Type V2G - UNI 82 27-Jun-23 25-Oct-23
Remaining Level of Effort Actual Work Critical Remaining Work Summary Page 9 of 17
Actual Level of Effort Remaining Work Milestone
Activity Name Original Start Finish 2023 2024
Duration
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
50% Detailed Design Package 23 15-Aug-23 14-Sep-23
Estidama, Provide Energy Model 2 15-Sep-23 18-Sep-23
Client Consent - Gateway 2 5 12-Sep-23 18-Sep-23
Gateway 3 17 19-Sep-23 12-Oct-23
Finalize Structure Coordination 2 19-Sep-23 20-Sep-23
Acoustic Validation 2 19-Sep-23 20-Sep-23
100% ID Package & Materials Cut Sheets 0 21-Sep-23
Finalize Coordinated RCP 2 21-Sep-23 22-Sep-23
Finishes Schedules 2 21-Sep-23 22-Sep-23
Landscape Design & Coordination 2 25-Sep-23 26-Sep-23
External Lighting Landscape 2 27-Sep-23 28-Sep-23
Precast Design Drawings 4 25-Sep-23 28-Sep-23
Fire & Life Safety Drawings 2 02-Oct-23 03-Oct-23
Structure Third Party Stamp 2 02-Oct-23 03-Oct-23
FLS Third Party Stamp 2 04-Oct-23 05-Oct-23
Estidama Final Score Card 2 04-Oct-23 05-Oct-23
Precast Fabrication Package 2 04-Oct-23 05-Oct-23
100% Detailed Design Submission 12 19-Sep-23 05-Oct-23
Client Consent - Gateway 3 5 06-Oct-23 12-Oct-23
Gateway 4 9 13-Oct-23 25-Oct-23
Architectural / Civil & MEPIFC Submission 6 13-Oct-23 20-Oct-23
Landscape BOQ 4 17-Oct-23 20-Oct-23
Interior Design BOQ 4 17-Oct-23 20-Oct-23
Architectural / Civil & MEPBOQ 4 17-Oct-23 20-Oct-23
Specifications 4 17-Oct-23 20-Oct-23
ECG Stamp ID & Landscape BOQ for Construction 2 23-Oct-23 24-Oct-23
ECG Stamp Landscape Design for Construction 2 23-Oct-23 24-Oct-23
ECGReview & Stamp ID Drawings for Construction 2 23-Oct-23 24-Oct-23
Client Consent - Gateway 4 1 25-Oct-23 25-Oct-23
Villa Type V2GN - UNI 94 26-Jun-23 09-Nov-23
Remaining Level of Effort Actual Work Critical Remaining Work Summary Page 10 of 17
Actual Level of Effort Remaining Work Milestone
Activity Name Original Start Finish 2023 2024
Duration
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
Client Consent - Gateway 1 2 15-Aug-23 16-Aug-23
Gateway 2 36 15-Aug-23 04-Oct-23
BIM Verification 2 15-Aug-23 16-Aug-23
Structure Statical System Coordination - Revit Model 4 17-Aug-23 22-Aug-23
Facade Lighting Design&Coordination 1 24-Aug-23 24-Aug-23
Facade Engineering, Special Facade details 2 23-Aug-23 24-Aug-23
External Utilities, Coordinate Tie-in location & Capacity 1 25-Aug-23 25-Aug-23
ID Coordination Package & RCP( 50% ID Package) 3 24-Aug-23 28-Aug-23
Landscape Coordinate with the building Levels & materials 1 28-Aug-23 28-Aug-23
Foundation Package 4 23-Aug-23 28-Aug-23
50% Landscape Package 5 22-Aug-23 28-Aug-23
MEP1st Fix Drawings 10 22-Aug-23 04-Sep-23
MEPMain Equipment Package Preparation 10 22-Aug-23 04-Sep-23
50% Detailed Design Package 32 17-Aug-23 02-Oct-23
Estidama, Provide Energy Model 2 03-Oct-23 04-Oct-23
Client Consent - Gateway 2 5 27-Sep-23 04-Oct-23
Gateway 3 17 05-Oct-23 27-Oct-23
Finalize Structure Coordination 2 05-Oct-23 06-Oct-23
Acoustic Validation 2 05-Oct-23 06-Oct-23
100% ID Package & Materials Cut Sheets 0 09-Oct-23
Finalize Coordinated RCP 2 09-Oct-23 10-Oct-23
Finishes Schedules 2 09-Oct-23 10-Oct-23
Landscape Design & Coordination 2 11-Oct-23 12-Oct-23
External Lighting Landscape 2 13-Oct-23 16-Oct-23
Precast Design Drawings 4 11-Oct-23 16-Oct-23
Fire & Life Safety Drawings 2 17-Oct-23 18-Oct-23
Structure Third Party Stamp 2 17-Oct-23 18-Oct-23
FLS Third Party Stamp 2 19-Oct-23 20-Oct-23
Estidama Final Score Card 2 19-Oct-23 20-Oct-23
Precast Fabrication Package 2 19-Oct-23 20-Oct-23
100% Detailed Design Submission 12 05-Oct-23 20-Oct-23
Client Consent - Gateway 3 5 23-Oct-23 27-Oct-23
Gateway 4 9 30-Oct-23 09-Nov-23
Architectural / Civil & MEPIFC Submission 6 30-Oct-23 06-Nov-23
Landscape BOQ 4 01-Nov-23 06-Nov-23
Interior Design BOQ 4 01-Nov-23 06-Nov-23
Architectural / Civil & MEPBOQ 4 01-Nov-23 06-Nov-23
Specifications 4 01-Nov-23 06-Nov-23
ECG Stamp ID & Landscape BOQ for Construction 2 07-Nov-23 08-Nov-23
ECG Stamp Landscape Design for Construction 2 07-Nov-23 08-Nov-23
ECGReview & Stamp ID Drawings for Construction 2 07-Nov-23 08-Nov-23
Client Consent - Gateway 4 1 09-Nov-23 09-Nov-23
Villa Type V4P - UNI 95 21-Aug-23 03-Jan-24
Remaining Level of Effort Actual Work Critical Remaining Work Summary Page 11 of 17
Actual Level of Effort Remaining Work Milestone
Activity Name Original Start Finish 2023 2024
Duration
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
100% Detailed Design Package Submission 0 13-Dec-23
IFC Package Submission 0 28-Dec-23
Gateway 1 27 21-Aug-23 26-Sep-23
Initial Concept Presentation 7 21-Aug-23 29-Aug-23
Fixed Floor Plans 7 30-Aug-23 07-Sep-23
Interior Design Mood Board 2 08-Sep-23 11-Sep-23
MEPSpace Requirment Package 3 08-Sep-23 12-Sep-23
Structure Elements Coordination 3 08-Sep-23 12-Sep-23
Landscape Concept Package 5 08-Sep-23 14-Sep-23
Facade Concept Design 2 13-Sep-23 14-Sep-23
Facade Engineering Review 3 15-Sep-23 19-Sep-23
Estidama Target Score Card 1 22-Sep-23 22-Sep-23
Facade Lighting Concept Design 3 20-Sep-23 22-Sep-23
Client Consent - Gateway 1 2 25-Sep-23 26-Sep-23
Gateway 2 19 25-Sep-23 20-Oct-23
BIM Verification 2 25-Sep-23 26-Sep-23
Structure Statical System Coordination - Revit Model 4 27-Sep-23 03-Oct-23
Facade Lighting Design&Coordination 1 05-Oct-23 05-Oct-23
Facade Engineering, Special Facade details 2 04-Oct-23 05-Oct-23
External Utilities, Coordinate Tie-in location & Capacity 1 06-Oct-23 06-Oct-23
50% Landscape Package 5 03-Oct-23 09-Oct-23
ID Coordination Package & RCP( 50% ID Package) 3 05-Oct-23 09-Oct-23
Landscape Coordinate with the building Levels & materials 1 09-Oct-23 09-Oct-23
MEP1st Fix Drawings 5 03-Oct-23 09-Oct-23
MEPMain Equipment Package Preparation 5 03-Oct-23 09-Oct-23
Foundation Package 4 04-Oct-23 09-Oct-23
50% Detailed Design Package 15 27-Sep-23 18-Oct-23
Estidama, Provide Energy Model 2 19-Oct-23 20-Oct-23
Client Consent - Gateway 2 5 16-Oct-23 20-Oct-23
Gateway 3 42 23-Oct-23 20-Dec-23
Remaining Level of Effort Actual Work Critical Remaining Work Summary Page 12 of 17
Actual Level of Effort Remaining Work Milestone
Activity Name Original Start Finish 2023 2024
Duration
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
Architectural / Civil & MEPIFC Submission 6 21-Dec-23 28-Dec-23
ECGReview & Stamp ID Drawings for Construction 2 29-Dec-23 02-Jan-24
ECG Stamp ID & Landscape BOQ for Construction 2 29-Dec-23 02-Jan-24
ECG Stamp Landscape Design for Construction 2 29-Dec-23 02-Jan-24
Client Consent - Gateway 4 1 03-Jan-24 03-Jan-24
Villa Type V1S - UNI 107 10-Jul-23 08-Dec-23
Remaining Level of Effort Actual Work Critical Remaining Work Summary Page 13 of 17
Actual Level of Effort Remaining Work Milestone
Activity Name Original Start Finish 2023 2024
Duration
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
Precast Design Drawings 4 08-Nov-23 13-Nov-23
Fire & Life Safety Drawings 2 14-Nov-23 15-Nov-23
Structure Third Party Stamp 2 14-Nov-23 15-Nov-23
FLS Third Party Stamp 2 16-Nov-23 17-Nov-23
Estidama Final Score Card 2 16-Nov-23 17-Nov-23
Precast Fabrication Package 2 16-Nov-23 17-Nov-23
100% Detailed Design Submission 12 02-Nov-23 17-Nov-23
Client Consent - Gateway 3 5 20-Nov-23 24-Nov-23
Gateway 4 9 27-Nov-23 08-Dec-23
Architectural / Civil & MEPIFC Submission 6 27-Nov-23 05-Dec-23
Landscape BOQ 4 29-Nov-23 05-Dec-23
Interior Design BOQ 4 29-Nov-23 05-Dec-23
Architectural / Civil & MEPBOQ 4 29-Nov-23 05-Dec-23
Specifications 4 29-Nov-23 05-Dec-23
ECG Stamp ID & Landscape BOQ for Construction 2 06-Dec-23 07-Dec-23
ECG Stamp Landscape Design for Construction 2 06-Dec-23 07-Dec-23
ECGReview & Stamp ID Drawings for Construction 2 06-Dec-23 07-Dec-23
Client Consent - Gateway 4 1 08-Dec-23 08-Dec-23
Villa Type V4B - UNI 99 04-Sep-23 23-Jan-24
Remaining Level of Effort Actual Work Critical Remaining Work Summary Page 14 of 17
Actual Level of Effort Remaining Work Milestone
Activity Name Original Start Finish 2023 2024
Duration
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
50% Detailed Design Package 15 06-Oct-23 26-Oct-23
MEP1st Fix Drawings 12 11-Oct-23 26-Oct-23
MEPMain Equipment Package Preparation 12 11-Oct-23 26-Oct-23
Estidama, Provide Energy Model 2 27-Oct-23 30-Oct-23
Client Consent - Gateway 2 5 24-Oct-23 30-Oct-23
Gateway 3 50 31-Oct-23 10-Jan-24
Finalize Structure Coordination 10 31-Oct-23 13-Nov-23
Acoustic Validation 10 31-Oct-23 13-Nov-23
100% ID Package & Materials Cut Sheets 0 14-Nov-23
Finalize Coordinated RCP 2 14-Nov-23 15-Nov-23
Finishes Schedules 2 14-Nov-23 15-Nov-23
Landscape Design & Coordination 2 16-Nov-23 17-Nov-23
External Lighting Landscape 2 20-Nov-23 21-Nov-23
Precast Design Drawings 4 16-Nov-23 21-Nov-23
Fire & Life Safety Drawings 5 22-Nov-23 28-Nov-23
Structure Third Party Stamp 5 22-Nov-23 28-Nov-23
FLS Third Party Stamp 2 29-Nov-23 30-Nov-23
Precast Fabrication Package 15 29-Nov-23 20-Dec-23
Estidama Final Score Card 2 02-Jan-24 03-Jan-24
100% Detailed Design Submission 45 31-Oct-23 03-Jan-24
Client Consent - Gateway 3 5 04-Jan-24 10-Jan-24
Gateway 4 9 11-Jan-24 23-Jan-24
Architectural / Civil & MEPIFC Submission 6 11-Jan-24 18-Jan-24
Landscape BOQ 4 15-Jan-24 18-Jan-24
Interior Design BOQ 4 15-Jan-24 18-Jan-24
Architectural / Civil & MEPBOQ 4 15-Jan-24 18-Jan-24
Specifications 4 15-Jan-24 18-Jan-24
ECG Stamp ID & Landscape BOQ for Construction 2 19-Jan-24 22-Jan-24
ECG Stamp Landscape Design for Construction 2 19-Jan-24 22-Jan-24
ECGReview & Stamp ID Drawings for Construction 2 19-Jan-24 22-Jan-24
Client Consent - Gateway 4 1 23-Jan-24 23-Jan-24
Hotel 105 26-Jul-23 21-Dec-23
Remaining Level of Effort Actual Work Critical Remaining Work Summary Page 15 of 17
Actual Level of Effort Remaining Work Milestone
Activity Name Original Start Finish 2023 2024
Duration
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
Submission of Detailed Design by ECG ( Borgo ) 25 12-Oct-23 15-Nov-23
Review andApproval of Detailed Design ( Borgo) 5 16-Nov-23 22-Nov-23
Mosque - Jame'e 50 15-Aug-23 24-Oct-23
Remaining Level of Effort Actual Work Critical Remaining Work Summary Page 16 of 17
Actual Level of Effort Remaining Work Milestone
Activity Name Original Start Finish 2023 2024
Duration
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
General 40 23-Aug-23 18-Oct-23
Appoint Specialist Consultant - Signage and Wayfinding - Landscape & Exterior 5 23-Aug-23 29-Aug-23
Submission of Concept Design ( Signage and Wayfinding ) 10 30-Aug-23 12-Sep-23
Review andApproval of Concept Design ( Signage and Wayfinding ) 5 13-Sep-23 19-Sep-23
Submission of Schematic Design ( Signage and Wayfinding ) 15 20-Sep-23 11-Oct-23
Review andApproval of Schematic Design ( Signage and Wayfinding ) 5 12-Oct-23 18-Oct-23
Water Features and Pools 40 23-Aug-23 18-Oct-23
Remaining Level of Effort Actual Work Critical Remaining Work Summary Page 17 of 17
Actual Level of Effort Remaining Work Milestone