0.1 Offer Price Amdal
0.1 Offer Price Amdal
A. Expert Personnel
1 Team Leader - Environmental Engineering Expert 120 Person.Days Rp 390,000,000.00 $ 24,192.57
2 Physical Expert - Chemistry 60 Person.Days Rp 195,000,000.00 $ 12,096.29
3 Biological Expert 60 Person.Days Rp 195,000,000.00 $ 12,096.29
4 Social - Economic - Cultural Expert 60 Person.Days Rp 195,000,000.00 $ 12,096.29
5 Public Health Expert 60 Person.Days Rp 195,000,000.00 $ 12,096.29
6 Civil Engineer 60 Person.Days Rp 195,000,000.00 $ 12,096.29
Total A Rp 1,365,000,000.00 $ 84,674.01
C. Support Personnel
1 Secretary/General Administration 1.5 Person.Month Rp 3,000,000.00 $ 186.10
2 Computer Operator 1.5 Person.Month Rp 3,000,000.00 $ 186.10
3 Surveyor 2 Person.Month Rp 5,000,000.00 $ 310.16
Total C Rp 11,000,000.00 $ 682.35
D Office Costs
1 Project Location Office Rental including Furniture (@50m2) 18 m2/Month Rp 13,500,000.00 $ 837.44
2 Field Office Stationery Costs 18 Month Rp 5,400,000.00 $ 334.97
3 Office Equipment Rental Costs
a. Desktop Computer 18 Month Rp 6,300,000.00 $ 390.80
b. Printer Color A-3 18 Month Rp 4,500,000.00 $ 279.15
4 Field Office Operational Costs (@50m2) 18 m2/Month Rp 9,000,000.00 $ 558.29
F Reporting Costs
1 Preliminary Report 5 Book Rp 500,000.00 $ 31.02
2 Monthly/Progress Reports 24 Book.Month Rp 3,000,000.00 $ 186.10
3 Draft Environmental Impact Assessment (AMDAL) 10 Book Rp 4,500,000.00 $ 279.15
4 Final Environmental Impact Assessment (AMDAL) 10 Book Rp 7,000,000.00 $ 434.23
5 Draft Reports for Environmental Impact Assessment, RKL 10 Book Rp 6,250,000.00 $ 387.70
6 Final Reports for Environmental Impact Assessment, RKL 10 Book Rp 7,000,000.00 $ 434.23
7 Master Documents in FD 5 Item Rp 612,500.00 $ 37.99
Rp 28,862,500.00 $ 1,790.41
Total II
Total Direct Non- Personnel Costs (A+B+C+D+E+F) Rp 233,362,500.00 $ 14,476.00
TOTAL SUB I & II Rp 1,714,362,500.00 $ 106,345.74
VAT 11% Rp 188,579,875.00 $ 11,698.03
GRAND TOTAL Rp 1,902,942,375.00 $ 118,043.77
BUDGET PLAN SUPPLIER WANAYUDI
PREPARATION OF THE AMDAL DOCUMENT FOR CUBE
SUPPLIER 1 WANAYUDI
No DESCRIPTION COMMANS COMMANS
Unit Volume Price (Rp) Price (Dollars) Unit Volume Price (Rp) Price (Dollars)
ENVIRONMENTAL APPROVAL DELH
A
(Environmental Evaluation Document)
I PERSONAL COST
2.1 Data Collection & Analysis Cost Ls 1 Rp 20,000,000.00 $ 1,235.79 This Cost Data Collection
a Air & Noise Ambiance Points 3 Rp 10,500,000.00 $ 648.79 detailed cost details of what is no details of the costs involved
b Flora & Fauna Points 3 Rp 10,500,000.00 $ 648.79 included in it
c Transportation Ls 1 Rp 3,000,000.00 $ 185.37
d Ls = Prices are fixed and
Hydrology Ls 3 Rp 9,000,000.00 $ 556.10 there are no price changes
or additional costs
e Social, Economic, & Cultural Ls 1 Rp 3,000,000.00 $ 185.37
f Secondary Data Ls 1 Rp 2,000,000.00 $ 123.58
g Sampling Officer Cost Day 1 Rp 5,000,000.00 $ 308.95
TOTAL I,II,and III Rp 1,714,362,500.00 $ 105,929.47 TOTAL I,II,and III Rp 1,300,250,000.00 $ 80,341.70
VE 11% Rp 188,579,875.00 $ 11,652.24 PPH 2% Rp 26,005,000.00 $ 1,606.83
GRAND TOTAL Rp 1,902,942,375.00 $ 117,581.71 GRAND TOTAL Rp 1,326,255,000.00 $ 81,948.53