thickness ofoutlet base slab( T) 0.125 m Dia of outlet outer circular wall (d1) 1.45 m Dia of outlet inner circular wall ( d2) 1.2 m Dia of outlet after clearance 0.05m bothside for form work 1.55 (Dk) m thickness of circularwall( t) 0.125 m ht of wall (H) 0.5 m pipe dia at base slab (d3) 0.125 m dia of hdpe pipe (d4) 0.125 m opening dia at oulet 0.2 m
1) Earthwork excavation in all kinds of soil :
Base slab= (π/4*1.55^2*0.125) 0.24 cum total= 0.24 cum for 37 no.s outlet= 9.00 cum 2(a) R.C.C M25 with 20 mm down graded high chips for precast slab Base slab= (π/4*1.45^2*0.125) 0.21 cum Vertical wall= (π/4*((1.45^2)-(1.2^2))*0.5) 0.26 cum total= 0.466 (A) Deduction (b) Pipe hole= (1*π/4*0.14^2*0.125) (-) 0.002 (֒0.125+0.015(extra hole clearance)) = 0.14 opening on vertical wall= π/4*0.2^2*0.125*2 0.01 (B) Net Quantity= (A) - (B) 0.466 0.01 0.457 cum for 37 no.s outlet= 17.00 cum 3) Centring & shuttering for R.C.C work Base slab= (π*1.45*0.125) 0.57 sqm Vertical wall outside= (π*1.45*0.5) 2.28 sqm Vertical wall inside= (π*1.2*0.5) 1.88 sqm 4.73 (A) Deduction Opening Area= (4xπ/4*0.2^2) (-) 0.13 (B) Net Quantity= (A) - (B) 4.731 0.1256 4.6 sqm for 37 no.s outlet= 171.00 sqm 4) 8mm Ø HYSD Bar including cost of bars bending, binding & fixing with carraige & all taxes etc. a) Base slab in X-X direction (1400+(1385.64+1341.64+1264.9+1148.92+979.8+721.1)*2) 15084.00 mm in Y-Y direction (1400+(1385.64+1341.64+1264.9+1148.92+979.8+721.1)*2) 15084.00 mm b) Vertical wall i) Main reinforcement 45*800 36000.00 mm (length of one main reinforcemrnt = 600+200(for devlopmetlength) ii) Distribution reinforcement 6*3.14*1400 26376.00 mm total= 92544.00 mm Add 5% cutting ,binding,lapping etc: 4627.20 total= 97171.20 mm Say 97.18 m Weight of 8mm bar 38.88 kg Say 0.39 qntl for 37 no.s outlet= 15.00 qntl
Filling foundation and plinth with excavated soil:-
5) 1/3 x quantity item= 0.08 cum for 37 no.s outlet= 2.91 sqm Say 3.00 sqm ABSTRACT OF 2 HA OUTLET SL NO. Earthwork excavationPARTICULARS in all kinds of soil in UNIT QUANTITY RATE AMOUNT 1 foundation R.C.C M25 with 20 mm down graded High granaite cum 9.00 158.50 1426.5 2 chips cum 17.00 4542.00 77214 3 Centering Cutting and shuttering bending for Bar biding HYSD R.C.C work cost including sqm 171.00 675.20 115459.2 4 carraige etc complete Qntl 15.00 8609.40 129141 5 Filling foundation and plinth with excavated soil cum 3.00 31.30 93.9 TOTAL 323334.6 SAY ₹ 323,335.00 For 37 no. of Outlet = ₹ 323,335.00 For 1 no. of Outlet = ₹ 8,739.00 ABSTRACT OF 1 HA OUTLET SL NO. Earthwork excavationPARTICULARS in all kinds of soil in UNIT QUANTITY RATE AMOUNT 1 foundation R.C.C M25 with 20 mm down graded High granaite cum 6.00 158.50 951 2 chips cum 9.00 4542.00 40878 3 Centering and shuttering Cutting bending for Bar biding HYSD R.C.C work cost including sqm 106.00 675.20 71571.2 4 carraige etc complete Qntl 9.00 8609.40 77484.6 5 Filling foundation and plinth with excavated soil cum 2.20 31.30 68.86 TOTAL 190953.66 SAY ₹ 190,954.00 For 37 no. of Outlet = ₹ 190,954.00 For 1 no. of Outlet = ₹ 5,161.00 1 Ha OUTLET PRECAST CHAMBER Dia of outlet base slab (D) 0.95 m thickness ofoutlet base slab( T) 0.125 m Dia of outlet outer circular wall (d1) 0.95 m Dia of outlet inner circular wall ( d2) 0.7 m Dia of outlet after clearance 0.05m bothside for form work (Dk)1.05 m thickness of circularwall( t) 0.125 m ht of wall (H) 0.5 m hole pipe dia at base slab (d3) 0.125 m dia of hdpe pipe (d4) 0.125 m opening dia at oulet 0.2 m
1) Earthwork excavation in all kinds of soil :
Base slab= (π/4*1.05^2*0.2) 0.17 cum total= 0.17 cum for 37 no.s outlet= 6.00 cum 2(a) R.C.C M25 with 20 mm down graded high chips for precast slab Base slab= (π/4*0.95^2*0.125) 0.09 cum Vertical wall= (π/4*((0.95^2)-(0.7^2))*0.5) 0.16 cum total= 0.25 (A) Deduction (b) Pipe hole= (1*π/4*0.14^2*0.125) (-) 0.002 opening on vertical wall= π/4*0.2^2*0.125*2 0.01 (B) Net Quantity= (A) - (B) 0.251 0.01 0.24 cum for 37 no.s outlet= 9.00 cum 3) Centring & shuttering for R.C.C work Base slab= (π*0.95*0.125) 0.37 sqm Vertical wall outside= (π*0.95*0.5) 1.49 sqm Vertical wall inside= (π*0.7*0.5) 1.10 sqm 2.96 (A) Deduction Opening Area= (4xπ/4*0.2^2) (-) 0.13 (B) Net Quantity= (A) - (B) 2.964 0.1256 2.8 sqm for 37 no.s outlet= 106.00 sqm 4) 8mm Ø HYSD Bar including cost of bars bending, binding & fixing with carraige & all taxes etc. a) Base slab in X-X direction (900+(877.5+806.22+670.82+412.31)*2) 6433.70 mm in Y-Y direction (900+(877.5+806.22+670.82+412.31)*2) 6433.70 mm b) Vertical wall i) Main reinforcement 30*800 24000.00 mm (length of one main reinforcemrnt = 600+200(for devlopmetlength) ii) Distribution reinforcement 6*π*900 16961.40 mm total= 53828.80 mm Add 5% cutting ,binding,lapping etc: 2691.44 total= 56520.24 mm Say 56.53 m Weight of 8mm bar 22.62 kg Say 0.23 qntl for 37 no.s outlet= 9.00 qntl
5) Filling foundation and plinth with excavated soil:-
1/3 x quantity item= 0.06 cum for 37 no.s outlet= 2.14 sqm Say 2.20 sqm