Estimate of 2Ha & 1 Ha Outlet

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 6

2 Ha OUTLET PRECAST CHAMBER

Dia of outlet base slab (D) 1.45 m


thickness ofoutlet base slab( T) 0.125 m
Dia of outlet outer circular wall (d1) 1.45 m
Dia of outlet inner circular wall ( d2) 1.2 m
Dia of outlet after clearance 0.05m bothside for form work 1.55
(Dk) m
thickness of circularwall( t) 0.125 m
ht of wall (H) 0.5 m
pipe dia at base slab (d3) 0.125 m
dia of hdpe pipe (d4) 0.125 m
opening dia at oulet 0.2 m

1) Earthwork excavation in all kinds of soil :


Base slab= (π/4*1.55^2*0.125) 0.24 cum
total= 0.24 cum
for 37 no.s outlet= 9.00 cum
2(a) R.C.C M25 with 20 mm down graded high chips for precast slab
Base slab= (π/4*1.45^2*0.125) 0.21 cum
Vertical wall= (π/4*((1.45^2)-(1.2^2))*0.5) 0.26 cum
total= 0.466 (A)
Deduction
(b) Pipe hole= (1*π/4*0.14^2*0.125) (-) 0.002
(֒0.125+0.015(extra hole clearance)) = 0.14
opening on vertical wall= π/4*0.2^2*0.125*2 0.01 (B)
Net Quantity= (A) - (B)
0.466 0.01 0.457 cum
for 37 no.s outlet= 17.00 cum
3) Centring & shuttering for R.C.C work
Base slab= (π*1.45*0.125) 0.57 sqm
Vertical wall outside= (π*1.45*0.5) 2.28 sqm
Vertical wall inside= (π*1.2*0.5) 1.88 sqm
4.73 (A)
Deduction
Opening Area= (4xπ/4*0.2^2) (-) 0.13 (B)
Net Quantity= (A) - (B)
4.731 0.1256 4.6 sqm
for 37 no.s outlet= 171.00 sqm
4) 8mm Ø HYSD Bar including cost of bars bending, binding & fixing with carraige & all taxes etc.
a) Base slab
in X-X direction (1400+(1385.64+1341.64+1264.9+1148.92+979.8+721.1)*2) 15084.00 mm
in Y-Y direction (1400+(1385.64+1341.64+1264.9+1148.92+979.8+721.1)*2) 15084.00 mm
b) Vertical wall
i) Main reinforcement 45*800 36000.00 mm
(length of one main reinforcemrnt = 600+200(for devlopmetlength)
ii) Distribution reinforcement 6*3.14*1400 26376.00 mm
total= 92544.00 mm
Add 5% cutting ,binding,lapping etc: 4627.20
total= 97171.20 mm
Say 97.18 m
Weight of 8mm bar 38.88 kg
Say 0.39 qntl
for 37 no.s outlet= 15.00 qntl

Filling foundation and plinth with excavated soil:-


5) 1/3 x quantity item= 0.08 cum
for 37 no.s outlet= 2.91 sqm
Say 3.00 sqm
ABSTRACT OF 2 HA OUTLET
SL NO. Earthwork excavationPARTICULARS
in all kinds of soil in UNIT QUANTITY RATE AMOUNT
1 foundation
R.C.C M25 with 20 mm down graded High granaite cum 9.00 158.50 1426.5
2 chips cum 17.00 4542.00 77214
3 Centering
Cutting and shuttering
bending for Bar
biding HYSD R.C.C work cost
including sqm 171.00 675.20 115459.2
4 carraige etc complete Qntl 15.00 8609.40 129141
5 Filling foundation and plinth with excavated soil cum 3.00 31.30 93.9
TOTAL 323334.6
SAY ₹ 323,335.00
For 37 no. of Outlet = ₹ 323,335.00
For 1 no. of Outlet = ₹ 8,739.00
ABSTRACT OF 1 HA OUTLET
SL NO. Earthwork excavationPARTICULARS
in all kinds of soil in UNIT QUANTITY RATE AMOUNT
1 foundation
R.C.C M25 with 20 mm down graded High granaite cum 6.00 158.50 951
2 chips cum 9.00 4542.00 40878
3 Centering and shuttering
Cutting bending for Bar
biding HYSD R.C.C work cost
including sqm 106.00 675.20 71571.2
4 carraige etc complete Qntl 9.00 8609.40 77484.6
5 Filling foundation and plinth with excavated soil cum 2.20 31.30 68.86
TOTAL 190953.66
SAY ₹ 190,954.00
For 37 no. of Outlet = ₹ 190,954.00
For 1 no. of Outlet = ₹ 5,161.00
1 Ha OUTLET PRECAST CHAMBER
Dia of outlet base slab (D) 0.95 m
thickness ofoutlet base slab( T) 0.125 m
Dia of outlet outer circular wall (d1) 0.95 m
Dia of outlet inner circular wall ( d2) 0.7 m
Dia of outlet after clearance 0.05m bothside for form work (Dk)1.05 m
thickness of circularwall( t) 0.125 m
ht of wall (H) 0.5 m
hole pipe dia at base slab (d3) 0.125 m
dia of hdpe pipe (d4) 0.125 m
opening dia at oulet 0.2 m

1) Earthwork excavation in all kinds of soil :


Base slab= (π/4*1.05^2*0.2) 0.17 cum
total= 0.17 cum
for 37 no.s outlet= 6.00 cum
2(a) R.C.C M25 with 20 mm down graded high chips for precast slab
Base slab= (π/4*0.95^2*0.125) 0.09 cum
Vertical wall= (π/4*((0.95^2)-(0.7^2))*0.5) 0.16 cum
total= 0.25 (A)
Deduction
(b) Pipe hole= (1*π/4*0.14^2*0.125) (-) 0.002
opening on vertical wall= π/4*0.2^2*0.125*2 0.01 (B)
Net Quantity= (A) - (B)
0.251 0.01 0.24 cum
for 37 no.s outlet= 9.00 cum
3) Centring & shuttering for R.C.C work
Base slab= (π*0.95*0.125) 0.37 sqm
Vertical wall outside= (π*0.95*0.5) 1.49 sqm
Vertical wall inside= (π*0.7*0.5) 1.10 sqm
2.96 (A)
Deduction
Opening Area= (4xπ/4*0.2^2) (-) 0.13 (B)
Net Quantity= (A) - (B)
2.964 0.1256 2.8 sqm
for 37 no.s outlet= 106.00 sqm
4) 8mm Ø HYSD Bar including cost of bars bending, binding & fixing with carraige & all taxes etc.
a) Base slab
in X-X direction (900+(877.5+806.22+670.82+412.31)*2) 6433.70 mm
in Y-Y direction (900+(877.5+806.22+670.82+412.31)*2) 6433.70 mm
b) Vertical wall
i) Main reinforcement 30*800 24000.00 mm
(length of one main reinforcemrnt = 600+200(for devlopmetlength)
ii) Distribution reinforcement 6*π*900 16961.40 mm
total= 53828.80 mm
Add 5% cutting ,binding,lapping etc: 2691.44
total= 56520.24 mm
Say 56.53 m
Weight of 8mm bar 22.62 kg
Say 0.23 qntl
for 37 no.s outlet= 9.00 qntl

5) Filling foundation and plinth with excavated soil:-


1/3 x quantity item= 0.06 cum
for 37 no.s outlet= 2.14 sqm
Say 2.20 sqm

You might also like