Professional Documents
Culture Documents
ITP-INSTALLATION OF SWITCHGEARS, MOTOR CONTROL CENTERS AND BUS DUCTS
ITP-INSTALLATION OF SWITCHGEARS, MOTOR CONTROL CENTERS AND BUS DUCTS
Document Title :
ITP-INSTALLATION OF SWITCHGEARS, MOTOR CONTROL CENTERS AND BUS
DUCTS Document Number: Rev.
ENG052-20ERW-000-QA-ITP-2019-000 01
Contract No. ENG052-20ERW Project No. JI-2047 Date 22/10/2022
Company Transmittal No.: ZLOG-PFML-TRE-01419
CONTRACTOR’s RESPONSE SHEET
Digitally signed
by Nijin
CONTRACTOR – RESPONSE
DN: cn=Nijin, o,
ou,
COMPANY - REVIEW
email=nijin.kari
mbil@petrofac.c
om, c=US
Date: 2022.11.02 Ajaykum Digitally signed by
Ajaykumar Burade Name :
12:47:32 +04'00'
ar Burade Date: 2022.11.02
15:17:12 +04'00'
Nijin .K – Quality VS-
Engineer QUALITY MANAGER 22-10-2022
Page 1 of 1
INSPECTION & TEST PLAN
PROJECT: NC 200 ERAWIN FIELD EPF PHASE I (PLAN B)
DOCUMENT TITLE:
INSPECTION & TEST PLAN (ITP FOR
INSTALLATION OF SWITCHGEARS, MOTOR
CONTROL CENTERS AND BUS DUCTS
Ajayku
Digitally signed by Nijin
DN: cn=Nijin, o, ou,
email=nijin.karimbil@petr Digitally signed
ofac.com, c=US by Ajaykumar
Date: 2022.11.02 12:47:50
+04'00' mar Burade
Date: 2022.11.02
Ajayku Digitally signed
by Ajaykumar
HOLD LIST
Hold
Para. Description of Hold
No.
INSTALLATION OF SWITCHGEARS, MOTOR
CONTROL CENTERS AND BUS DUCTS Rev. 02
Date:
NC 200 ERAWIN FIELD EPF PHASE I (PLAN B) 22/10/2022
ENG-052-20-ERW
Page 3 of 13
Reference Documents:
Page 5 of 13
Page 6 of 13
Page 7 of 13
Page 8 of 13
Page 9 of 13
Page 10 of 13
Page 11 of 13
Page 12 of 13
Page 13 of 13
E-0501A Page
1 of 2
E-0501A Page
2 of 2
1b- MV/HV SWITCHGEAR AND MCC (Test Voltage: 5000V for 1min)
QC Signature
Test Configuration R-YBE Y-RBE B-RYE
SC Petrofac
IR value before hi-pot test (MΩ)
IR value after hi-pot test (MΩ)
2-MAIN BUS BAR HIPOT TEST RESULTS (MV/HV Switchgear & MCC)
Y-RBE
B-RYE
Test Equipment Type Make Model Sl. No. Cal Due Date
Remarks:
E-0502A Page
1 of 1
Project No.: JI2047 Record No: Date:
Tag No:
Sub-System No: RFI #
Test Equipment Type Make Model Sl. No. Cal Due Date
Name
Signature
Date
Page 1 of 1
NC 200 ERAWIN FIELD EPF PHASE I (PLAN B)
Contract No ENG052-20ERW Rev: 01
INSPECTION & TEST RECORD-ELECTRICAL
ITR No: E-0503X
INSPECTION RECORD FOR CURRENT Date:
TRANSFORMER 30/05/22
E-0503X Page
1 of 1
Project No.: JI2047 Record No: Date:
Tag No:
Sub-System No: Sub contractor:
Visual Inspection
4 Verify that adequate clearances exist between bus bars and CTs.
5 Verify that size of the CT wiring and terminal lugs are of correct type.
6 Verify that all required grounding and shorting connections are provided.
Remarks:
Name
Signature
Date
Page 1 of 1
NC 200 ERAWIN FIELD EPF PHASE I (PLAN B)
Contract No ENG052-20ERW Rev:01
INSPECTION & TEST RECORD-ELECTRICAL
ITR No: E-0504X
INSPECTION RECORD FOR VOLTAGE Date:
TRANSFORMER 30/05/22
E-0504X Page:
1 of 1
Project No.: JI2047 Record No: Date:
Tag No:
Sub-System No: Sub contractor:
VISUAL INSPECTION
Sl. No Checks to be performed Result
1 Verify name plate details against drawings/data sheets.
Verify location against GA drawing, inspect physical and mechanical condition and ensure no
2
damages.
3 Verify that adequate clearances exist between primary and secondary circuit wiring.
Remarks:
Name
Signature
Date
Page 1 of 1
NC 200 ERAWIN FIELD EPF PHASE I (PLAN B)
Contract No ENG052-20ERW Rev:01
INSPECTION & TEST RECORD-ELECTRICAL
ITR No: E-0505X
INSPECTION RECORD FOR PROTECTIVE RELAYS
AND MEASURING/METERING DEVICES Date:
30/05/22
E-0505X Page 1 of 1
Voltage: V Frequency: Hz
VISUAL INSPECTION
Compartment No:
Function:
Code No:
Type:
Serial No:
Model No:
6 Clean cover glass, inspect shorting hardware, connection paddles, and knife switches.
Name
Signature
Date
Page 1 of 1
NC 200 ERAWIN FIELD EPF PHASE I (PLAN B)
Contract No ENG052-20ERW Rev:01
INSPECTION & TEST RECORD-ELECTRICAL
ITR No: E-0509X
SWITCHGEAR AND MOTOR CONTROL CENTER Date:
CUBICLE CHECKS 30/05/22
E-0509X Page:
1 of 1
Name
Signature
Date
Page 1 of 1
NC 200 ERAWIN FIELD EPF PHASE I (PLAN B)
Contract No ENG052-20ERW Rev: 01
INSPECTION & TEST RECORD-ELECTRICAL
ITR No: E-0510A
INSPECTION AND TESTING OF METAL Date:
ENCLOSED BUS DUCTS 30/05/22
E-0510A Page:
1 of 2
Name
Signature
Date
Page 1 of 2
NC 200 ERAWIN FIELD EPF PHASE I (PLAN B)
Contract No ENG052-20ERW Rev: 01
INSPECTION & TEST RECORD-ELECTRICAL
ITR No: E-0510A
INSPECTION AND TESTING OF METAL Date:
ENCLOSED BUS DUCTS 30/05/22
E-0510A Page:
2 of 2
Result (MΩ)
QC Signature
Test Configuration R-YBE Y-RBE B-RYE
SC Petrofac
IR value before hi-
pot test (MΩ)
IR value after hi-pot
test (MΩ)
R-YBE
Y-RBE
B-RYE
Test Equipment Type Make Model Sl. No: Cal Due Date:
Name
Signature
Date
Page 2 of 2