CONSTRUCTION AGREEMENT-II
CONSTRUCTION AGREEMENT-II
CONSTRUCTION AGREEMENT
WHEREAS:-
4. The SOCIETY had called for a Special General Body Meeting for
considering the Offers received from the CONTRACTORS and in it’s
Special General Body Meeting held on 23/12/2012 considered the
Rates offered by the CONTRACTORS, Experience of the CONTRACTORS,
4
1. That the SOCIETY shall get the plans sanctioned from CIDCO
LTD.
3. The Society shall pay the amount of Rs. 1,400/- (Rupees One
Thousand Four Hundred Only) per sq. ft. for 23000 Sq. Ft. Salable
area totally amounting to Rs. 3,22,00,000/- ( Rupees Three Crores
Twenty Two Lakhs Only ) to the CONTRACTOR as per the terms and
conditions of these presents..
1) Advance mobilization 5%
2) Excavation/Foundation/Plinth 5%
3) Completion of 1st Slab 5%
4) Completion of 2nd Slab 5%
5) Completion of 3rd Slab 5%
6) Completion of 4th Slab 5%
7) Completion of 5th Slab 5%
8) Completion of 6th Slab 5%
9) Completion of 7th Slab 5%
10) Completion of 8th Slab 5%
11) Brick work with door frame Internal Plaster, 10%
External Plaster
12) Flooring /Dado/Kit Platform /Electricity & 10%
Lift, Plumbing
13) Internal & External Painting, Compound wall 10%
& Finishing
14) Aluminum Window & Doors, Water Proofing 5%
15) Over head Tank, Under Ground Tank 5%
16) Camera Fitting, Fitness Centre, Generator, 5%
installation, Society office
17) Retention 5%
_____
100%
6
10. That the total contract price has been worked out and agreed
upon as per the plans of the Building contained in Schedule A
thereof the CONTRACTORS shall not claim any further payment from
the Owner excluding the escalation upto 10%.
12. That the CONTRACTORS has deposited Rs. 6,00,000/- (Rupees Six
Lakhs Only) as Refundable Security Deposit with the SOCIETY i.e.
Rs. 4,00,000/- (Rupees Four Lakhs Only ) by RTGS No.
UTIBH12359089134 on 24.12.2012from Axis Bank Ltd. Vashi and Rs.
2,00,000/- (Rupees Two Lakhs Only) by cash deposited in the Bank
Account of the SOCIETY on 26.12.2012 and the SOCIETY has agreed
to release this amount along with payment of final bill of the
CONTRACTORS.
13. The Parties hereto agree that the TERMS AND CONDITIONS
MENTIONED IN SCHEDULE A hereunder shall be deemed to be a part
and parcel of these presents and read as part and parcel of these
presents for all purposes and are to be strictly adhered to by
the CONTRACTOR.
14. The Parties hereto declare that the CONTRACTORS shall provide
the General Amenities mentioned in SCHEDULE B written hereunder
and the same shall be deemed to be a part and parcel of these
presents and read as part and parcel of these presents for all
purposes
17. The CONTRACTOR shall be liable to pay the Service Tax if and
wherever applicable.
22. That CONTRACTOR only with the written consent of the SOCIETY
shall be at liberty to assign any part of the construction work
to any person or agency, but it shall be absolutely necessary
that such person or agency has the necessary skill and experience
to perform the work as an expert and the Contract Value agreed
upon herein is not exceeded.
23. That the Final Bill shall be drawn by the CONTRACTOR soon
after the completion of the work and the SOCIETY shall be duty
bond to pay the same within a month of receipt thereof after
being satisfied regarding correctness of the bill.
24. That in case the CONTRACTOR fails to perform his part of the
contract, the SOCIETY shall give Notice to the CONTRACTOR and
even then if the construction work shall be assigned to any other
person as decided by the SOCIETY and in that event the CONTRACTOR
shall be entitled to receive payment on the part of the contract
executed by him but shall forfeit the amount of
11
SCHEDULE A
Terms and Conditions
GENERAL CONDITIONS:
SPECIAL CONDITIONS
SPECIFICATIONS OF WORK
A: GENERAL
cement, lime, steel, and such other materials, which are likely
to deteriorate by the action of sun, wind, rain or other natural
causes, either in compounds or in store in such a manner that all
such materials, tools etc. shall be duly protected from damage.
All such stores shall be cleared away and the whole left in good
order on completion of the work. All materials, which are stored
on site, shall be stocked in such manner as to facilitate rapid
and easy checking of the quantities of such materials.
4. LATRINES
The Contractor shall provide at his cost for the use of workers
and the staff adequate temporary latrines and sanitary
accommodations to the satisfaction of local authorities, and keep
them in perfectly sanitary conditions, at the location specified
by the E-in-C/ Consultant
5. WORK PROGRAM
The Contractor, before starting the work shall furnish and get
approved from the E-in-C/ Consultant of bar chart for carrying
out the work stage by stage in stipulated time. These charts
shall be maintained, at site, showing progress of the work week
by week.
6. INCLEMENT WEATHER
The Contractor shall take necessary steps at his own expenses to
protect all work from the effects of inclement weather
7. LOADING TO FLOORS
Particular care shall be taken by the Contractor to see that the
33
8. MEASURES OF MATERIALS
Sand and metals for concrete and mortars shall be measured in
boxes, the sizes of which are approved by the Architect and/or
Consulting Engineer. The measuring of sand and metal by any other
mode shall not be permitted.
9. MIXING OF MATERIALS
The mixing of materials shall be done on closely constructed
platforms approved by the Architect/Consultants as that there
will be no leakage of any of the material through the platforms
and also that no foreign materials can get incorporated during
the mixing.
15. SCAFFOLDING
The Contractor shall provide all the shuttering, scaffolding
needed for any item of work as is required.
(iii) Miscellaneous works: not covered under Item (i) & (ii)
above IS Specifications
37
NOTE: THE CONTRACTOR SHALL NOT BE GIVEN ANY EXTRA CLAIM FOR
LENGTH AND BREADTH MEASUREMENT ON ACCOUNT OF CONTRACTOR EXCEEDING
THIS SIZE ON HIS OWN. IT SHALL ALSO BE NOTED THAT THIS ITEM ALSO
INCLUDES BACKFILLING OF THE TRENCHES AFTER THE FOUNDATION WORK IS
OVER.
2 EARTH FILLING
The measurement shall be only for the murum supplied by
SOCIETY and approved by the E-in-C /Consultant and shall be
calculated after taking the joint levels before and after
the consolidation and filling.
3 CONCRETE
FORM WORK.
Contractor should submit for the Consultant's approval
design and drawing for all formwork showing sizes of member
including props and its foundation .Only steel and new
plywood shuttering shall be permitted for its first use at
site, and its number of uses will be solely with discretion
of Consultant. A mock-up of formwork for columns, typical
column-beam junction, beams should be made and only after
obtaining approval of the mock-up, the contractor will be
allowed to proceed with the work Providing cut-outs, holes,
slits, depression etc. for electrical fixtures shall not be
paid separately. Size of the panels used for exposed
concrete finish areas shall be approved by the Engineer-in-
charge/ consultants. For quick erection of shuttering and
staging the system should have suitable arrangement for
moving entire set in transverse as well as in longitudinal
directions and rails/wheels on any suitable arrangement
which will be approved by the consultant.
39
CONCRETE:
Concrete mix shall be M-20, as specified. Material and
workmanship shall confirm to the relevant IS code
standards. Mixing shall be done with power driven mixture
thoroughly and shall be for at least 2 minutes. Quantity of
water shall be sufficient to ensure the workability of the
concrete and also as per the water cement ratio required
for the desired strength of the concrete. The Contractor is
entirely responsible for the design of concrete mixes. The
design is however, to be approved by the Engineer. The
mixed concrete shall be tamped and vibrated in all parts of
the mould and between the reinforcement. Architect’s and/or
Consulting Engineer’s instructions if any in this regard
shall be followed very strictly. The Contractor shall not
use hand mixed concrete without prior permission of the
Architect and/or Consulting Engineer. No concrete shall be
40
5 STEEL REINFORCEMENT
The lengths of all types of round bars shall be calculated
from the relevant drawings of Architect and/or Consulting
Engineer. The quantity for the item shall be arrived at by
multiplying the unit weight of the bars, as specified in
relevant IS code, and the length as measured above. For the
44
8 PLASTER
In all plaster works H-frame formwork shall be provided so
that the scaffolding is independent of walls. If required,
ceiling plaster shall be completed before wall plasterwork
is commenced with. Wall plaster shall be done from top to
bottom and the plastering of each wall shall be done within
a single day. If for reasons of wall being long the
Contractor feels he has to the plastering of each of the
walls will have to be done on different days, then he shall
take a prior permission from the E-in-C/Consulting
Engineer. All the corners shall be straight in vertical or
horizontal or curved alignment as the case may be. But
these corners shall be sharp wherever required. Junctions
wherever required shall be done without extra payment. Any
cracks visible on the surface, or any portion or patch that
will be found hollow by the E-in-C/Consulting Engineer, the
same shall be rectified by the method suggested by the E-
in-C/Consulting Engineer, by the Contractor without
claiming any extra payments. Curing shall be started as
soon as the plaster has hardened sufficiently not to be
damaged when watered. The internal plaster of 12mm
thickness(1:4) shall be cured least for seven days and the
external plaster shall be cured for least fifteen days.
9 POINTING
The raked joints of the stone wall or the brick wall to be
pointed shall be kept wetted for the pointing to be done.
The mortar for pointing shall consist of 1 part by cement
and 3 parts by sand. This mortar shall be applied to the
wetted joints uniformly. The joints of the pointed work
shall be neatly defined by pointing lines being regular and
uniform in breadth. The edges of the pointing shall be cut
off parallel so that well defined lines are seen at 19 mm
apart. The pointing shall be kept well-wetted least for 5
days after pointing is finished. The rate of pointing shall
be paid on the area of the wall on which the pointing is
done.
Hinges
Note: Any other make can be also used only with prior written
approval of Engineer-in-charge/ Consultant/ Managing Committee of
CHS.
Note: Any other make can be also used only with prior written
approval of Engineer-in-charge/ Consultant/SOCIETY
51
SCHEDULE B
AARTI GAURAV
Plot No. 128, Sector-19, Ulwe, Navi Mumbai.
GENERAL AND OTHER AMENITIES
GENERAL AMENITIES :
1. Enhanced structures earthquake safety for high rise
buildings. Earthquake resistant structural design with
latest technology.
12. Staircase& Passage: Full Italian marble upto Ist Floor and
kota with mirror polish in staircase till terrace and passage
area, Lift walls decorative stone finish
22. Sign boards like 1st Floor, fire Duct, parking, society
office etc…
OTHER AMENITIES:
R E C E I P T
WE SAY RECEIVED