If we get each weekly update of both the Mitigation and Contract Baseline and we add in
the additional columns:
We will be able to track the resource planned and actual and address how we change
our resource manning from the plan (Baseline and Mitigation Programme update).
How It Works
CONSTRUCTION WORKS NORTH SPINE TUNNEL BRANCH - 4 (NORTH SPINE UTILITY TUNNEL) Electrical Works
CONSTRUCTION WORKS NORTH SPINE TUNNEL BRANCH - 4 (NORTH SPINE UTILITY TUNNEL) Electrical Works
CONSTRUCTION WORKS NORTH SPINE TUNNEL BRANCH - 4 (NORTH SPINE UTILITY TUNNEL) Electrical Works
CONSTRUCTION WORKS NORTH SPINE TUNNEL BRANCH - 4 (NORTH SPINE UTILITY TUNNEL) Electrical Works
CONSTRUCTION WORKS NORTH SPINE TUNNEL BRANCH - 4 (NORTH SPINE UTILITY TUNNEL) Electrical Works
CONSTRUCTION WORKS NORTH SPINE TUNNEL BRANCH - 4 (NORTH SPINE UTILITY TUNNEL) Electrical Works
CONSTRUCTION WORKS NORTH SPINE TUNNEL BRANCH - 4 (NORTH SPINE UTILITY TUNNEL) Electrical Works
CONSTRUCTION WORKS NORTH SPINE TUNNEL BRANCH - 4 (NORTH SPINE UTILITY TUNNEL) Electrical Works
1
RESOURCE MONITORING TRACKER
By running the filter for both the mitigation programme ( in this instance 21 June 2024)
and applying the same filter for the baseline on “sheet 2 – titled: “BASELINE
RESOURCE” you can get to see the resource to be applied to each.
RESOURCE KPI's 102 2496 31228 0 0 31228 0 102 0
BASELINE
3 6 7 8 9 10 11 12 13 14 15 16 17
17/03/24
18/03/24
19/03/24
20/03/24
21/03/24
22/03/24
23/03/24
24/03/24
25/03/24
26/03/24
27/03/24
28/03/24
WBS7 Resource (*)Resou (*)Start (*)Finish Original (*)Budgeted Budgeted Budget Actual Remaining (*)Actual Remaining Units
ID rce Duration( Units / Units(h) ed Cost Units(h) Early Duration(d Duration(d) %
Type d) Time(h/d) ($) Units(h) ) Comple
te(%)
0 MAN-1 Labor 25-Aug-24 09-Sep-24 14 274 3841 0 0 3841 0 14 0
0 MAN-1 Labor 17-Sep-24 01-Oct-24 12 395 4738 0 0 4738 0 12 0
0 MAN-1 Labor 02-Oct-24 17-Oct-24 14 259 3625 0 0 3625 0 14 0
0 MAN-1 Labor 19-Oct-24 31-Oct-24 12 256 3069 0 0 3069 0 12 0
0 MAN-1 Labor 02-Nov-24 12-Nov-24 10 474 4738 0 0 4738 0 10 0
0 MAN-1 Labor 18-Nov-24 02-Dec-24 12 256 3069 0 0 3069 0 12 0
0 MAN-1 Labor 04-Dec-24 21-Dec-24 14 291 4074 0 0 4074 0 14 0
0 MAN-1 Labor 21-Dec-24 06-Jan-25 14 291 4074 0 0 4074 0 14 0
Take the filter o and the resource situation for the whole of the works is known
comparing the Mitigation programme (21 June 2024) to the Baseline.
2
RESOURCE MONITORING TRACKER
3 6 7 8 9 10 11 12 13 14 15 16 17
17/03/24
18/03/24
19/03/24
20/03/24
21/03/24
22/03/24
23/03/24
24/03/24
25/03/24
26/03/24
27/03/24
28/03/24
WBS7 Resource (*)Resou (*)Start (*)Finish Original (*)Budgeted Budgeted Budget Actual Remaining (*)Actual Remaining Units
ID rce Duration( Units / Units(h) ed Cost Units(h) Early Duration(d Duration(d) %
Type d) Time(h/d) ($) Units(h) ) Comple
te(%)
3 6 7 8 9 10 11 12 13 14 15 16 17
17/03/24
18/03/24
19/03/24
20/03/24
21/03/24
22/03/24
23/03/24
24/03/24
25/03/24
26/03/24
27/03/24
28/03/24
29/03/24
30/03/24
WBS7 Resource (*)Resou (*)Start (*)Finish Original (*)Budgeted Budgeted Budget Actual Remaining (*)Actual Remaining Units Planned After Actual Before DATA
ID rce Duration( Units / Units(h) ed Cost Units(h) Early Duration(d Duration(d) % DATA DATE DATE
Type d) Time(h/d) ($) Units(h) ) Comple
te(%)
If we put in Planned for location and actual we actually committed we will have a good
analysis of the resource we planned and the actual we committed. If we just rely on the
Baseline and the Mitigation programme Update, all we will know is the planned resource
we were going to commit and the actual of the planned resource we did commit.
The resource in either the Baseline or Mitigation is FEMCO’s best estimate based on
productivity rates. The question is can we achieve these rates. WE WILL ONLY FIND
OUT BY PUTTING IN ACTUALS AND PLANNED INCREASE IF THE PLAN IS NOT
WORKING.
3
RESOURCE MONITORING TRACKER
Finally, the resource tracker is easy to produce. What is important is that actuals and changes
to planned manning levels are entered.
All the information on the tracker came from P6. We just need the latest updates and changes
we have made to logic and then basically do a copy/paste dump of the activities (filter for
construction only).
4
RESOURCE MONITORING TRACKER
Delete Columns
Do not use Activity Status, Role ID and Cost Account ID. Filter out under Resource ID: Man-
hr and then under Resource TYPE = Labour.
Do a Vlookup against the activity ID and then you will have all the resource matching the
WBS.
Regards,
Jeremy.