Materials Installation costs
Materials Installation costs
A- Copper Pipe
Specification:
Copper pipe and connections shall be Muller made in Usa with hight thickness for VRF as blow table:
Unit Price
Item Desc QTY Unit (USD)
1 Crane 0 No. 0
2 Supply and install Remote wire with conduct 150 m 0.7
3 Supply and install transmition Wire with conduct 300 m 0.7
4 Supply and install Outdoor basement 0 No. 0
Supply and install galvanized tray for covering outdoor
5 40 m 25
piping
6 Testing by Nitrogen 3 No. 50
7 Vacuum 3 No. 50
8 Supply and add Gas R410 3 No. 120
9 Testing and Commisioing 3 - 100
10 Engineering service supervisor commissioning 1 - 1000
Total (USD):
Specification:
Transmition cable size and remote controller wire size shall be over 0.75mm shielded twist pair cable .
Testing by Nitrogen For checking gas leakage shall done at pressure 40 Bar for 24 hours.
Vacuum pumping work until the pressure reaches -0.1MPa (-756mmHg) or lower for min 20min.
Total Price
(USD)
0
105
210
0
1000
150
150
360
300
1000
3275
pair cable .
min.