Boshra Hotel

A- Copper Pipe

Size Copper Pipe Isulation Installation Unit Price Total Price


Item Qty (m)
(inch) (USD/m) (USD/m) (USD/m) (USD) (USD)
1 1/4" 40 1.7 0.25 6 7.95 318
2 3/8" 90 2.3 0.27 6 8.57 771.3
3 1/2" 60 3.2 0.3 6 9.5 570
4 5/8" 95 5.7 0.39 6 12.09 1148.55
5 3/4" 75 7.3 0.46 6 13.76 1032
6 7/8" 1 9 0.5 6 15.5 15.5
7 1-1/8" 40 10.6 0.64 6 17.24 689.6
8 1-1/4" 3 12.3 0.98 6 19.28 57.84
9 1-3/8" 60 12.3 0.98 6 19.28 1156.8
464
Total (USD): 5759.59

Contractor Scope of work:


Supply,install and Welding copper pipe +Y branch with Nitrogen and all related accessory
Insulate copper pipe with Foam and tape it.
Hang and install copper pipe on ceiling every 1 meter with all related materials

Specification:
Copper pipe and connections shall be Muller made in Usa with hight thickness for VRF as blow table:

Insulated pipe foam shall be balck with thickness minimum 1/2"


B- Installation units

Unit Price Total Price


Item Desc QTY (USD) (USD)
1 Install Indoor units 25 65 1625
2 Install outdoor units 9 80 720
Total (USD): 2345

Contracot Scope of work:


Install indoor units on ceiling with all related materials
Connect copper pipe, Elec wire, transmision wire and remote control wire to indoor units
Covering indoor units by nylon
Install and connect remote controller on wall
Connect dranage to indoor units
Connect copper pipe, Elec wire and transmision wire to outdoor units
D- Miscellaneous

Unit Price
Item Desc QTY Unit (USD)
1 Crane 0 No. 0
2 Supply and install Remote wire with conduct 150 m 0.7
3 Supply and install transmition Wire with conduct 300 m 0.7
4 Supply and install Outdoor basement 0 No. 0
Supply and install galvanized tray for covering outdoor
5 40 m 25
piping
6 Testing by Nitrogen 3 No. 50
7 Vacuum 3 No. 50
8 Supply and add Gas R410 3 No. 120
9 Testing and Commisioing 3 - 100
10 Engineering service supervisor commissioning 1 - 1000
Total (USD):

Specification:
Transmition cable size and remote controller wire size shall be over 0.75mm shielded twist pair cable .
Testing by Nitrogen For checking gas leakage shall done at pressure 40 Bar for 24 hours.
Vacuum pumping work until the pressure reaches -0.1MPa (-756mmHg) or lower for min 20min.
Total Price
(USD)
0
105
210
0
1000
150
150
360
300
1000
3275

pair cable .

min.