ACTION PLAN FOR THE WELFARE FACILITIES & THE

HSE REQUIREMENTS FOR THE GENERATOR/DIESEL


TANK AREA

HYATT PLACE HOTEL, AL UL


Action Plan

WELFARE FACILITIES:
We appreciate your inquiry regarding the welfare facilities for workers at the Hyatt Place
Hotel, Al Ula Project. Takween AlRajhi is committed to ensuring the well-being of our
workforce, and we are pleased to share our action plan for the provision of welfare facilities
at the project site.

Action Plan:
Mobilization Schedule:

Our mobilization is scheduled to commence at the end of next week, allowing us sufficient
time to implement the necessary welfare facilities before the arrival of our workforce.

Welfare Facility Setup:

We will establish designated areas for welfare facilities, including toilet, rest areas, dining
spaces, and sanitation facilities, ensuring compliance with local regulations and standards.

Accommodation:

Adequate accommodations will be arranged to provide a comfortable living environment for


our workers. This includes proper sleeping quarters, hygiene facilities, and recreation areas.

Health and Safety Measures:

Strict health and safety protocols will be implemented to safeguard the well-being of our
workforce. This includes regular health check-ups, first aid stations, and adherence to COVID-
19 guidelines.

Communication Channels:

We will establish effective communication channels to address any concerns or feedback


from the workers promptly. This ensures a transparent and responsive approach to their
needs.

Training and Awareness Programs:

We are committed to conducting training sessions and awareness programs on safety


measures, health protocols, and overall well-being to empower our workforce with the
knowledge they need.

Continuous Improvement:

Action Plan Page 2 of 5

Takween Alrajhi
Raden Commercial Canter, Olaya Street, Riyadh, Kingdom of Saudi Arabia
E-mail info@takweenalrajhi.com
Action Plan

Takween AlRajhi is dedicated to continuous improvement. We will regularly review and


enhance our welfare facilities based on feedback, changing circumstances, and evolving best
practices.

Assurance:

We assure you that all required welfare facilities will be in place for our workers at the Hyatt
Place Hotel, Al Ula Project, by the end of next week. Takween AlRajhi values the health and
happiness of its employees, and we are confident that our comprehensive action plan will
contribute to a positive and productive working environment.

HSE REQUIREMENTS IN GENERATOR/DIESEL TANK AREA


As of now, our generator is currently non-operational, and the diesel tank is empty, thereby
eliminating any immediate risks associated with these elements. however, we acknowledge
the significance of proactively addressing hse requirements in this area as part of our
commitment to safety.

in light of the above, we have formulated a comprehensive action plan to address the hse
requirements for the generator and diesel tank area:

Hazard Assessment:
conduct a thorough hazard assessment of the generator and diesel tank area to identify
potential risks and hazards associated with their operation.

Safety Signage:
implement clear and visible safety signage in and around the generator/diesel tank area to
highlight potential dangers and safety protocols.

Emergency Response Plan:


develop and communicate an emergency response plan specific to the generator and diesel
tank area. this plan should include evacuation procedures, emergency contacts, and the
location of emergency equipment.

Training and Awareness:


provide comprehensive training to all personnel involved in the operation and maintenance
of the generator and diesel tank. ensure that they are aware of the potential risks and are
well-equipped to handle any emergency situations.

Action Plan Page 3 of 5

Takween Alrajhi
Raden Commercial Canter, Olaya Street, Riyadh, Kingdom of Saudi Arabia
E-mail info@takweenalrajhi.com
Action Plan

Regular Inspections:
establish a schedule for regular inspections and maintenance of the generator and diesel
tank. this will help identify and address any issues before they escalate.

Fuel Management:
implement a strict fuel management plan to ensure that the diesel tank is adequately filled
when needed, minimizing downtime and potential disruptions.

Compliance With Regulatory Standards:


ensure that all activities related to the generator and diesel tank area comply with local and
international hse regulations and standards.

We would like to assure you that takween alrajhi is committed to prioritizing HSE
considerations at every stage of the project. our mobilization is scheduled to commence at
the end of next week, and we guarantee that all hse requirements for the generator and
diesel tank area will be in place before operational activities begin.

Action Plan Page 4 of 5

Takween Alrajhi
Raden Commercial Canter, Olaya Street, Riyadh, Kingdom of Saudi Arabia
E-mail info@takweenalrajhi.com
Action Plan

Action Plan Page 5 of 5

Takween Alrajhi
Raden Commercial Canter, Olaya Street, Riyadh, Kingdom of Saudi Arabia
E-mail info@takweenalrajhi.com