Ct Cases 18114-19 982-20 2936-20 7723-20 29-2021 73-21

1741-21 4062-21
SHIV KUMAR SHARMA Vs. BLUE COAST
INFRASTRUCTURE DEVELOPMENT PVT. LTD.
(Connaught Place)
10.04.2024

Present: Mr. Gulwant Singh, Ld. Counsel for complainant


with complainant.
Mr. Neeraj Tiwari and Mr. Abhishek Chhabra, ld.
counsel for accused alongwith AR of accused no.1.

Mediation order dated 05.02.2024 received back as


settled.
It is submitted by counsel for accused that the first
two installments in terms of mediation settlement has already
been paid.
At request, put up for verification of remaining
payment on 30.11.2024.

(Neha Garg)
MM (NI Act)-02-PHC