Professional Documents
Culture Documents
MP-0150-DEC-CCMA-EI-ITP-0001-INSPECTION AND TEST PLAN FOR EARTHWORKS AND BACKFILLING-3
MP-0150-DEC-CCMA-EI-ITP-0001-INSPECTION AND TEST PLAN FOR EARTHWORKS AND BACKFILLING-3
Approved Approved
Rev Date Reason for Issue Prepared Checked Approved
(Optional)
Reviewed Reviewed Approved
(Optional)
Notes:
Originator Checker Approver Approver CCMA DEC PMC OWNER
Main Subcontractor/EPCC
Subcontractor-Electro Industries
Contractor/OWNER; PMC
MP-0150-DEC-CCMA-EI- ITP-0001
Content
1. Scope of work……………………………………………………………………………………………………………………….2
2. Reference………………………………………………………………………………………………………………………….….2
4. Inspection Activity………………………………………….……………………………………………………………………..3
5. Attachment list……………………………………………………………………………………………………………………..5
1. Scope of work
This Project Quality Plan defines the organization, responsibilities, and controls, which will be applied to ensure
satisfactory execution and completion of the Gobustan (Area 60) Solar Power Project. This document covers all
information required in the Contract (Frame Agreement) and its attachments.
2. Reference
AZS standard
QOST standard
SNIP standard
BS standard
EN standard
ASTM standard
AASHTO standard
Project spec and Approved drawings
3. Definition and Abbreviation
3.1 Definition
CLIENT MASDAR
PROJECT 230 MWac Garadagh Solar PV Plant (Area 60)
PMC Mercados-Aries International
EPC Dongfang Electric AZ
SUBCONTRACTOR China Construction Midland Azerbaijan LLC
Independent verification party as an appointed Third Party Inspection
THIRD-PARTY
or Authority or Certification Agency
VENDOR Firm awarded with a Purchase Order by CONTRACTOR to supply
Equipment or Material for the PROJECT
Document №: MP0150-DEC-CCMA-ITP-001
230MWac Garadagh Solar PV Plant (Area 60) Date : 23-Dec-2022
Page: 2/3
INSPECTION TEST PLAN
3.2 Abbreviation
5.Attachment list
Page : 3 OF 11
INVOLVEMENT
4. Inspection Activity
Document
Item No. Reference/ QC Record OWNER / TP REMARKS
Acceptance Criteria Subcontractor Main Subcontractor EPC Contractor
Quality Control Activity PMC (Third Party)
1. BEFORE EXECUTION
MP-0150-DEC-CCMA-EI-
Third Party
1.2 Calibration of Measuring and Control Equipment QP-0001 H F.I F.I W H Contractor to maintain and provide a Calibration Log
Certificates
Approval Drawing
MP-0150-DEC-CCMA-EI- MAR
1.4 Backfilling Material Approval QP-0001 (inc. Third Party H F.I F.I W H
Approval Drawing Report)
MP-0150-DEC-CCMA-EI-
Backfilling Contractor QC to randomly check and verify with
1.5 Backfilling Maerial visual Inspection on Site /Delivery notes QP-0001 H F.I F.I W H
Material Register Contractor Construction
Approval Drawing
2. DURING EXECUTION
MP-0150-DEC-CCMA-EI-
Excavation performed according to Procedure / in accordance with
2.1 QP-0001 EI-CON-CIV-01 H F.I F.I W N/A Reported in EI-CON-CIV-01 Initiated in item 2.1
drawing latest revision
Approval Drawing
MP-0150-DEC-CCMA-EI- EI-CON-CIV-02
Excavation Dimensional Check / Excavation bottom surface Inspection
2.2 QP-0001 EI-CON-CIV-03 H F.I F.I W H Compaction testing when applicable
and compaction testing
Approval Drawing Third-Party Report
MP-0150-DEC-CCMA-EI-
Backfilling according to the Procedure, performed by layers/
2.3 QP-0001 Third-Party Report H F.I F.I W H Checked as part of item 3.1 reported in EI-CON-CIV-04
Compaction test for each layer of backfilling
Approval Drawing
3. AFTER EXECUTION
MP-0150-DEC-CCMA-EI-
Final grading inspection. Final inspection of filling/ backfilling / Final EI-CON-CIV-04
3.1 QP-0001 H F.I F.I W N/A
topographical survey check EI-CON-CIV-02
Approval Drawing
MP-0150-DEC-CCMA-EI-
3.2 Final Dimensional check QP-0001 See Remarks H F.I F.I W N/A All QC records from this ITP checked
Approval Drawing
PROJECT: CONTRACTOR:
DRAWING: RFI No:
DESCRIPTION:
REPORT No.:
REPORT Date:
This certificate does not exempt the Subcontractor from the Terms of the Contract, Project Specifications or Quality Procedures but confirms that all these Tests have been performed according to them.
TYPE OF WORK
ZONE / AREA:
(slab, well, trench,…)
EXCAVATION DIMENSIONS
GROUND CONDITIONS
(width, length, depth)
ELECTRICAL SYSTEM
GAS PIPING
FIRE WATER
DRAIN SYSTEM
PROCESS PIPING
OTHERS
ACTIVITY YES NO
OTHERS
WITNESSED /
SUBCONTRACTOR MAIN SUBCONTRACTOR EPC CONTRACTOR OWNER/PMC
REVIEWED BY:
SIGNATURE:
PRINT NAME:
DATE:
0
TOPOGRAPHIC SURVEY REPORT
No: EI-CON-CIV-02 Rev: 0 Date 23.01.2023 Sheet 1 of 1
PROJECT: CONTRACTOR:
DESCRIPTION:
REPORT No.:
REPORT Date:
This certificate does not exempt the Subcontractor from the Terms of the Contract, Project Specifications or Quality Procedures but confirms that all these Tests have been performed according to them.
SURVETING EQUIPMENT
MAKE / MODEL / TUPE:
SERIAL No.:
CALIBRATION CERTIFICATE No.:
MEASURMENTS
THEORETICAL REAL DEVIATION
POINT
XT YT ZT XR YR ZR ΔX ΔY ΔZ
1
2
3
4
5
6
7
8
9
10
11
12
REMARKS: AREA /
WITNESSED /
SUBCONTRACTOR MAIN SUBCONTRACTOR EPC CONTRACTOR OWNER/PMC
REVIEWED BY:
SIGNATURE:
PRINT NAME:
DATE:
INSPECTION REPORT FOR EXCAVATION
PROJECT: CONTRACTOR:
DRAWING: RFI No:
DESCRIPTION:
REPORT No.:
REPORT Date:
This certificate does not exempt the Subcontractor from the Terms of the Contract, Project Specifications or Quality Procedures but confirms that all these Tests have been performed according to them.
LOCATION / AREA:
Dewatering
REMARKS:
WITNESSED / MAIN
SUBCONTRACTOR EPC CONTRACTOR OWNER/PMC
REVIEWED BY: SUBCONTRACTOR
SIGNATURE:
PRINT NAME:
DATE:
FINAL INSPECTION OF FILLING / BACKFILLING
PROJECT: CONTRACTOR:
DRAWING: RFI No:
DESCRIPTION:
REPORT No.:
REPORT Date:
This certificate does not exempt the Subcontractor from the Terms of the Contract, Project Specifications or Quality Procedures but confirms that all these Tests have been performed according to them.
LOCATION / AREA:
Alignment / level approved and released for backfill (all release reports are available)
REMARKS:
WITNESSED / MAIN
SUBCONTRACTOR EPC CONTRACTOR OWNER/PMC
REVIEWED BY: SUBCONTRACTOR
SIGNATURE:
PRINT NAME:
DATE:
BACKFILLING MATERIAL REGISTER REV:0 Gobustan Solar Power Project (Area 60)
10
11
12
13
14
15
16