Professional Documents
Culture Documents
10. PMP Risk Eng.M.raslan
10. PMP Risk Eng.M.raslan
10. PMP Risk Eng.M.raslan
Management
Waterfall Processes
Process Group
Knowledge Area
Initiating Planning Executing Monitoring & Controlling Closing
4.5. Monitor & Control
4.3.Direct & Manage Project 4.7. Close
4. Project Integration 4.1. Develop project 4.2. Develop project management Project Work
Work Project or
Management charter plan 4.6. Perform Integrated
4.4.Manage Project Knowledge Phase
Change Control
5.1. Plan Scope Management
5.Project Scope 5.2. Collect Requirements 5.5. Validate Scope
Management 5.3. Define Scope 5.6. Control Scope
5.4. Create WBS
2 24 10 12 1
Hazard
Each time we smoke, we
might get cancer.
Smoking is a Hazard.
PROBABILITY + IMPACT
Tolerance to risk is
proportional to the
amount of money at stake
Not likely to take a Prefers an uncertain
outcome and may be
risk that is considered willing to pay a penalty
a high risk to take a high risk
Monitor
Initiation Planning Executing Closing
&Control
Change Requests
Project Documents Updates
Risk Management Plan (1)
Project Risk Management aims to identify and manage risks that are not
addressed by the other project management processes.
How strategically important is the project? Is the level of risk increased for this
project because it aims to produce breakthrough opportunities, addresses
Project importance
significant blocks to organizational performance, or involves major product
innovation?
To address this, projects managed using adaptive approaches make use of frequent reviews of incremental work products
and cross-functional project teams to accelerate knowledge sharing and ensure that risk is understood and managed
Risk is considered when selecting the content of each iteration, and risks will also be identified, analyzed, and managed
during each iteration
Planning for physical and human resources is much less predictable in projects with high variability so agreements for fast
supply and lean methods are critical to controlling costs and achieving the schedule
Additionally, the requirements are kept as a living document that is updated regularly, and work may be reprioritized as the
project progresses, based on an improved understanding of current risk exposure
Plan Risk Management
Plan Risk Management (1)
Identify Risks (2)
Perform Qualitative RA (3)
Perform Quantitative RA (4)
Monitor Risks
Plan Risk Responses (5) Implement Risk Responses
Monitor
Initiation Planning Executing Closing
&Control
• The process of defining how to conduct risk management activities for a project.
• This process is performed once or at predefined points in the project.
Plan Risk Management
INPUTS
INPUTS T&T OUTPUTS
Ayman Response
Plan Response to Risks 2 week $6000
strategies
Very High
High
Moderate
Low
Very Low
“Clearly” define risk categories (RBS)
Identify Risks
Plan Risk Management (1)
Identify Risks (2)
Perform Qualitative RA (3)
Perform Quantitative RA (4)
Implement Risk Responses Monitor Risks
Plan Risk Responses (5)
Monitor
Initiation Planning Executing Closing
&Control
• Which Risks may affect the project and documenting their characteristics
• Participants include Project Manager, Project Team, customers, SME, users, stakeholders,
risk management experts
• Iterative process
Monitor
Initiation Planning Executing Closing
&Control
• Qualitative risk analysis is the process of assessing the likelihood and impact of
identified risks and prioritizing them according to their potential effect on project
objectives.
• Where risk approaches introduce bias attention should be paid to identifying bias
and correcting it
• Cost Effective
• Lays foundation for Quantitative risk Assessment
Perform Qualitative Risk Analysis
Proximity: The period before the risk might have impact on one or more objectives. A short period indicates high proximity.
Dormancy. The period that may elapse after a risk has occurred before its impact is discovered. Short period indicates low
dormancy.
Manageability: The ease with which the risk owner (or owning organization) can manage the occurrence or impact of a risk.
Where management is easy, manageability is high.
Controllability: The degree to which the risk owner (or owning organization) is able to control the risk’s outcome. Where
the outcome easily controlled, controllability is high.
Detectability: The ease with which the results of the risk occurring, or being about to occur, can be detected and
recognized. Where the risk occurrence can be detected easily, detectability is high.
Connectivity: The extent to which the risk is related to other individual project risks. Where a risk is connected to many
other risks, connectivity is high.
Strategic impact: The potential for the risk to have a positive or negative effect on the organization's strategic goals. Where
the risk has a major effect on strategic goals, strategic impact is high.
Propinquity: The degree to which a risk is perceived to matter by one or more stakeholders. Where a risk is perceived as
very significant, propinquity is high.
T&T: Data Representation
Probability Impact
1. Probability and Impact Matrix: A probability and impact
of Occurring on Project
matrix is a grid for mapping the probability of each risk
✓
High High
occurrence and its impact on project
Med
✓
Med
2. objectives if that risk occurs. This matrix specifies
combinations of probability and impact that allow Lo Low
w
individual project risks to be divided into priority groups.
Monitor
Initiation Planning Executing Closing
&Control
INPUTS
INPUTS T&T OUTPUTS
B 10% €2,000,000
C 50% € - 200,000
• Probability
Status Probability Payoff • x
Good Market – Good Quality 15% 80,000 • Consequence
Good Market – Poor Quality 45% 50,000 (€$)
Poor Market – Good Quality 25% 20,000 • Calculated for a
Poor Market – Poor Quality 15% -20,000 single task or a
group of tasks or
EMV (Good market) = 0.15*80,000 + 0.45*50,000 = 34,500 events.
51k
Main
Decision
????
18k
40,000 , 60%
28k
10,000 , 40%
Monte Carlo Technique
• A statistical method used in simulation of data.
• Establish a model
analysis.
schedule analysis.
Cost Risk Simulation Results
Sensitivity Analysis
• Tornado Diagram
Escalate
Mitigation
(Corrective action)
Avoidance Acceptance
(Prevention) (Accept consequences)
Transference
(Shift Responsibility)
Risk Escalate
The product description for an elementary social sciences education • MIGHT involve
multimedia program references stock video clips of children riding bikes • Reduce/Change Scope
and roller skating without helmets or knee pads. During risk
• OR
identification , the project team reviewed the product description and
• Change way of
identified a potential risk of school administration not buying the program
meeting the
because it appears to advocate unsafe activities. Team avoided this risk
requirements
by changing the project scope so that it did not include the videos.
Risk Mitigation
• Reduce probability OR if
not possible, the impact of
a potential risk event to an
acceptable level.
Organizations often transfer responsibility for the risk of an employee • Typically is used in
getting injured on the job by paying a premium for worker’s connection with financial
compensation insurance. The insurance company assumes liability of risk exposure and most
the risk and is responsible for covering the injured worker’s medical often involves payment of
bills and / or partial wages depending on the circumstances.
a risk premium to the
Because the initial organization has transferred part of the financial
party assuming the risk.
liability to the insurance company and they now share the risk. This
would be an example of both risk sharing and risk transference.
Risk
Acceptance
• The decision not to change
the project plan to deal with
a risk.
• WHY
• Extremely low possibility of
occurrence
You own a business on a hill in an area that floods relatively often.
• No suitable risk response
Because of your location, you decide not to buy flood insurance.
strategy is identified.
Instead , you set aside money that is earmarked for the repair of
• HOW
water damage in case of flooding.
• Passive: do nothing!
Here, you are employing a risk acceptance strategy by establishing
• Actively: Plan B
a contingency reserve for an emergency . Although you aren’t
(contingency plan)
ignoring the risk , you will spend money only if the risk event occurs.
Other Strategies for Positive Risks …
Escalate sharing
Enhancement Exploitation
accept
Five Strategies dealing with Opportunities
- +
Escalate Escalate
Avoid Exploit
Transfer Share
Mitigate Enhance
Accept Accept
Contingent response strategy T&T
Risk responses identified using this technique are often called contingency
plans OR fallback plans and include identified triggering events that set the
plans in effect.
The response plan will be executed only under certain predefined conditions.
The response plan will be executed upon certain warning signs or triggers.
• How to deal with thins before things go wrong to reducing its overall impact.
• MIGHT include a Fallback Plans (Plan B )for risks with high impact. The fallback
plan is implemented if the primary response plan is ineffective in responding to
the risk event..
• Contingency reserve
• UKNOWN and ACCEPTABLE KNOWN
• The amount of the reserve is determined by the potential impact of the risk
“unknown-unknowns”
• The process of
implementing agreed-upon
risk response plans
• ( It is performed throughout
the project )
INPUTS
INPUTS T&T OUTPUTS
The process of monitoring the implementation of agreed-upon risk response plans, tracking
identified risks, identifying and analyzing new risks, & evaluating risk process effectiveness
throughout the project
• May be conducted by a third party, the project’s risk officer, or other qualified
personnel.
• Gather relevant project data regarding work results including risk database.
• Prepare a report of the findings and distribute to the project team and key
stakeholders.
• Workaround
– Unplanned responses to emerging risks that were previously unidentified or
unexpected.
Risk Register
Impact
Risk
T/O Risk description Risk Category Probability Score Risk Owner Response
ID Schedule Cost Scope
20 Min
Project Management Plan Vs Project Documents
Project Management Plan Project Documents
1. Scope management plan 1. Activity attributes 18. Quality control measurements
2. Requirements management plan 2. Activity list 19. Quality Metrics
3. Schedule management plan 3. Assumption log 20. Quality report
4. Cost management plan 4. Basis of estimates 21. Requirements documentation
5. Quality management plan 5. Change log 22. Requirements traceability matrix
6. Resource management plan 6. Cost estimates 23. Resource assignments
7. Communication management plan 7. Cost forecasts 24. Recourse breakdown structure
8. Risk management plan 8. Duration estimates 25. Resource calendars
9. Procurement management plan 9. Issue log 26. Resource requirements
10. Stakeholder engagement plan 10. Lessons learned register 27. Risk register
11. Change management plan 11. Milestone list 28. Risk report
12. Configuration management plan 12. Physical resource assignments 29. Schedule data
13. Scope baseline 13. Project Calendar 30. Schedule forecasts
14. Schedule baseline 14. Project communications 31. Stakeholder register
15. Cost baseline 15. Project schedule 32.Team Charter
16. Performance measurement baseline 16. Project schedule network diagram 33.Test and evaluation documents
17. Project life cycle description 17. Project scope statement
18.Development approach
QUESTIONS
Q1- If a project has a 60 percent chance of a US $100,000 profit
and a 40 percent chance of a US $100,000 loss, the expected
monetary value for the project is:
A. $100,000 profit.
B. $60,000 loss.
C. $20,000 profit.
D. $20,000 loss.
Q2-If a risk event has a 90 percent chance of occurring, and the
consequences will be US $10,000, what does US $9,000
represent?
A. Risk value.
B. Present value.
D. Contingency budget.
Q3- Purchasing insurance is BEST considered an
example of risk:
A. Mitigation.
B. Transfer.
C. Acceptance.
D. Avoidance.
Q4- Workarounds are determined during which risk
management process:
A. Identify Risks.
D. Monitor Risk.
Q5- During which risk management process is
a determination to transfer a risk made?
A. Identify Risks.
D. Monitor Risks.
Q6- Monte Carlo analysis is used to:
B. Risk score.