Professional Documents
Culture Documents
3. PMP Project Charter Annotated
3. PMP Project Charter Annotated
2 24 10 12 1
Develop Project Charter
INPUTS T&T OUTPUTS
INPUTS
1. Expert Judgment
1. Business Case
2. Data Gathering • Project Charter
2. Agreements
• Brainstorming
3. Enterprise T&T • Project
OUTPUTSVision
• Focus Groups
Environmental Statement
• Interviews
Factors (EEF)
3. Interpersonal & Team
4. Organization Process
Skills
Assets (OPA) • Conflict Management
• Facilitation
• Meeting Management
4. Meetings
Input: Business Case Market
Demand
analysis.
The project manager does not update or modify the business documents since they are not
project documents; however, the project manager may make recommendations.
Input: Agreements
contracts
Memorandums of
Email understanding
(MOUs),
Agreements
service level
verbal
agreements
agreements
(SLA),
letters of letter of
intent agreements
Inputs:
• Enterprise Environmental Factors • Organisational Process Assets
• PMP
• Experiences based on
– Consultants
– Stakeholders
– Industry Groups
– SME/PMO
T&T: Meetings
Meetings to develop the project
Charter
A facilitator conducts a
brainstorming section
where group of
stakeholders brainstorm
about
data/solution/ideas.
T&T: Facilitation
As the name suggests a
facilitator is conducting a
group event where the
primary purpose is to reach
on an agreement/solution.
Facilitator makes sure that
everybody contributes to the
process
Output: Project Charter
• What it is
• Formally authorizes the existence
of the project • Purpose/justification
• Provides authority to the project • Measurable objectives
manager to spend money and • Assumptions and constraints
other corporate resources • High level risks
• Defines the high-level project • Boundaries and milestones
requirements
• Key Stakeholders
• It is issued by the project sponsor
• Project Approval req
• It is broad enough not to require
any changes during project • PM authority
execution • Sponsor authority
Output: Project Vision Statement
A project vision statement is a description
or declaration of what an
organization/project team wants to
obtain or accomplish upon the
completion of a project. While the vision is
the grand idea, the vision statement is a
clear and concise announcement and
description of the big picture. no one perfect fit for everyone
1) Project Title
2) Project Start and finish date
3) Name of sponsor or those authorizing the project
4) Assigned project manager and authority level.
5) Project purpose & justification.
6) Objectives and their success criteria
7) Summary milestone schedule.
8) Summary budget
9) Approval criteria and who signs off project
10)Organizational, & external assumptions & constrains.
QUESTIONS
A. Measurable Objectives
A. Any Stakeholder
B. Project Manager
C. Project Initiator
A. Project Charter
B. Business Case
D. Contract
Q4- You are holding a formal, approved document that defines how
the project is executed, monitored, and controlled. You are holding:
C. C. Stakeholder analysis
D. D. Product Analysis
Q8-The selection of life cycle for the project, the processes to be
applied to each phase, and the results of the tailoring by the
project management team are usually found in the:
C. Project schedule
D. Project Charter
Q9- When is the Project Charter created?