7 TIMELINE PEKERJAAN
7 TIMELINE PEKERJAAN
SCHEDULE PLAN
CUSTOMER PT. PLN - NPS JUNI 2024 JULI 2024 AGUSTUS 2024
PROJECT PENGADAAN MATERIAL DAN INSTALASI PIPA DEMIN AREA ENGINE DALAM TOTAL
RANGKA JASA RELOKASI PLTG UNTUK PENYEDIAAN ENERGI LISTRIK PABRIK BOBOT
PEKERJAAN
27 - 30 JUNI 2024 01 - 07 JULI 2024 08 - 14 JULI 2024 15 - 21 JULI 2024 22 - 28 JULI 2024 29 JULI - 04 AGT 2024 05 - 11 AGUSTUS 2024 12 - 18 AGUSTUS 2024 QTY PERCENTAGE OF
WORK
FERONICKEL PT ANTAM HALTIM PROGRESS
PERCENT
DESKRIPSI Qty Unit (%) Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8
NO. TOTAL
A PEKERJAAN PERSIAPAN
RATA-RATA TOTAL
Progress Planning 10.00 15.00 2.50 2.50 20.00 20.00 20.00 10.00
Planning Progress Accumulation 10.00 25.00 27.50 30.00 50.00 70.00 90.00 100.00
Progress Actual 5.00 11.30
-5.00
Behind
PROGRESS PLANNING
PROGRESS ACTUAL
MANPOWER
STAFF 1 PERSONS
SUPERVISOR 1 PERSONS
WORKER 6 PERSONS
TOTAL 8 PERSONS