Revision History:
Rev. Remarks
Date Status TRSDC Reference No Description
No.
H10-New Assembly Facility -
Material Submittal for Square
R10-H10C02-GRR-MAT- Hollow Section, ASTM A500 Gr. B,
00 22-03-2022 Issued for Approval
ST-0023 Black, Cold Rolled (Manufacturer
– Ajmal Steel Tube & Pipe
Industries)
Material Submittal Form
TRS-CN-FRM-0018
General Information
R10-H10C02-GRR-
Contractor Grankraft Construction LLC Submittal No.
MAT-ST-0023
H10C02 GRR - OSM Shell & Core
Contract No. Date 9-Mar-22
works
Approved Subcontractor
To the Engineer The Red Sea Development Company NIL
(as applicable)
Material Information
Material Description
SQUARE HOLLOW SECTION , ASTM A500 Gr. B, Black, Cold Rolled
(One item only per Form)
Manufacturer/Supplier
Company Name Ajmal Steel Tube & Pipe Industries Locally Manufactured YES
Address UAE
Local Agent Other Details
Program Date Expected Arrival Date
(Material Required on Site) (on Site)
Contractor’s
Engineer’s - Comments
Comments:
Status Code
Page #
3. Compliance statement
6. Reference drawing
7. Trade license
9. Draft warranty
1. Material list / product description
Item Specification / Drawing Reference Material Manufacturer / Specification / Drawing Requirements Proposed Material / Compliance Remarks (Justify any
# (i.e. Part, Section & Page) Supplier Equipment (Yes, No, N/A) Deviations from Project
Specification)
Manufacturer:
2
M/s AJMAL STEEL TUBES & Tube ASTM A500 GrB Or Equivalent
Clause 4 Material Specification
PIPES INDUSTRIES LLC
1 Hollow Section with ASTM A500 Gr B Yes
No:2
Supplier: M/s AIC steel
.
* - min value of Cu & Al. / NA - Not Applicable. / BT - Bend Test / OD - Outside Dimenssion / Thick - Wall Thickness / R - Requied as per standard.
AJMAL STEEL
Dimenssion Mechanical Properties Flattening Test Pressure
SPEC SIZE Grade /Series BT Drift Weight
Yst Ts
OD Thick EL% weld Body Mpa
Mpa Mpa
Light
±7.5%
EN Medium AS per Standard EN10255 60%
½" - 6" Heavy Table -2 ,B.1,B.2,B.3 195 320-520 20% 25% < 2" R NA 50 bar
10255 Table -2 ,B.1,B.2,B.3 (90)
L1 ,+10%
L2 -8%
Light L -8 % / +NL
AS 60% ,+10%
½" - 6" Medium As per Standard Table M -10% / +NL 195 320-460 20% 25% < 2" R NA 50 bar
1074 (90) -8 %
Heavy H -10% / +NL
C250 /
250 320
C250L0
½" - 20"
AS C350/ ± 1% with minimum of ± 60%
50X20 - 250X250 ±10% 350 430 20% 25% < 2" R NA 50 bar ±7.5%
1163 C350L0 0.5mm (90)
20X20 - 250X150
C450 /
450 500
C450L0
AJMAL STEEL
Product Range Chart 1/2" - 6"
Out Side Diameter Wall Thickness
Inch 0.031 0.039 0.059 0.071 0.098 0.118 0.138 0.157 0.177 0.197 0.217 0.236 0.256 0.276 0.295 0.315
MADE IN UAE
AJMAL STEEL
Product Range Chart
Out Side Diameter Wall Thickness
Inch 0.157 0.197 0.217 0.236 0.256 0.276 0.295 0.315 0.335 0.354 0.374 0.394 0.413 0.433 0.453 0.472 0.492 0.512 0.531 0.551 0.571 0.591 0.610 0.630
mm 4 5 5.5 6 6.5 7 7.5 8 8.5 9 9.5 10 10.5 11 11.5 12 12.5 13 13.5 14 14.5 15 15.5 16
193.70 75/8
219.10 85/8
244.50 95/8
273.10 103/4
312.00 127/25
323.90 123/4
339.70 133/8
355.60 14
377.00 1421/25
406.40 16
426.00 163/4
445.00 171/2
457.20 18
473.00 185/8
508.00 20
PSL1 L245 or B L290 or X42 L320 or X46 L360 or X52 L390 or X56 L415 or X60 L450 or X65 L485 or X70
Grade API 5L :
PSL 2 L245M or BM L290M or X42M L320M or X46M L360M or X52M L390M or X56M L415M or X60M L450M or X65M L485M or X70M
MADE IN UAE
5. Test certificates or reports
APPROVAL DRAWINGS
KEY PLAN
GENERAL NOTES
1. GENERAL 2. DESIGN 5. CLEANING & PAINTING 8. FOUNDATIONS & EMBEDMENTS 9. ERECTION NOTES 10. LIST OF DRAWINGS
DWG. TITLE DATE REV.
1.1 All the information on these drawings and on 2.1 This building has been designed to support its own 5.1 As a minimum, fabricated built-up and hot rolled 8.1 The Customer or his Consultant is responsible 9.1 This building must be erected according to the
their respective Design Calculations are based onAIC dead load plus all other loads specified in "Column members are shot blasted to Swedish Standard SA for designing the foundations which support the steel erection drawings and safe erection practices.AIC is not 0001 INDEX 00 MATERIAL SPECIFICATIONS
21-FEB.-22
latest accepted proposal offer/contract for this job. reaction (mostly drawing. no. "A02")" drawing. 2.0 or as mentioned in contract. structure of this building. responsible for any structural inadequacy or odd NO. MATERIALS GRADE & SPECIFICATION STRENGTH
5.2 All built-up and hot rolled sections are painted to appearance, if the above requirement is not followed. 0002 ANCHOR BOLT PLAN & DETAILS 21-FEB.-22 00
1.2 Every drawing containsAIC approval block that is 2.2 Design Codes: 8.2 Approval drawing numbers marked A01, A02 etc. ASTM F1554 Grade A36M, Hot
the specification that is described in Singned 0003 NODE LAYOUT PLAN dip galvanized to ASTM A153M, 2
shown below. AIC designs buildings in accordance with the following show column orientations, critical anchor bolts 9.2 Gusset plates for flange braces are welded on 21-FEB.-22 00 J-type Ft = 400 N/mm
contract. Heavy Hex Nuts A563M-10S
latest applicable U.S.A. Design Codes: dimensions, base plate details, anchor bolt both sides of the column and rafter, however flange Washers-ASTMF436
0004 NODE REACTIONS 21-FEB.-22 00
Issued by AIC "For Approval" by Customer arrangements and column base reactions resulting braces are required at one side (unless noted ANCHOR
· 2005 edition of “Steel Construction Manual”, by from different load cases, reactions from diagonal otherwise). For aesthetic reasons, it is preferable to 01 BOLTS ASTM F1554 Grade A36M, Hot
Not for Construction & Not to Scale 0005 TYPICAL FRAME 21-FEB.-22 00
American Institute of Steel Construction (AISC). bracing, portal bracing (if any), etc. All reactions and install them all at the same side of column and rafter. The dip galvanized to ASTM A153M,
6. PHASING OF SHIPMENTS
2
Heavy Hex Nuts A563M-10S Ft = 400 N/mm
Approved As Is loads are in Kilo-Newton (KN) and meter (m) units. side chosen depends on erection sequence. 0006 TYPICAL FRAME 21-FEB.-22 00
Customer is required to · 2002 edition of “Cold Formed Steel Design These reactions are required to design the Washers-ASTMF436
STRAIGHT
Approved As Noted Manual”, by American Iron and Steel Institute (AISI). foundations of the building. 9.3 It is extremely important to use temporary guy wires 0007 END FRAME 21-FEB.-22 00 -type
check ( ) one box only BS EN ISO 898-1 GRDE 8.8,
6.1 AIC ships the PEB Steel Structure of large and install permanent bracing while erecting the frame.
Resubmit As Noted Hot dip galvanized to BS EN ISO1461 2 GENERAL NOTES
· 2006 edition of “Structural Welding Code-Steel buildings in phases of approximately 100 MT to 8.3 Anchor bolt plans for construction are normally Insufficient temporary guy wires during erection, or 0008 END FRAME 21-FEB.-22 00 Ft = 800 N/mm
enable the erectors to unload and erect a phase BS EN ISO 898-2 10 STYLE2
D1.1/1.1M”, by American Welding Society (AWS). submitted within 1-4 weeks (depending on building removal of permanent bracing could result in building
Customer Signature: prior to the arrival of a subsequent phase. Phases engineering complexity) from date of release of a failure. 0009 ROOF FRAMING PLAN 21-FEB.-22 00 WASHER-BS4320 1. All Dimension are in mm, angles in degree and
2.3 Building Codes: are normally shipped as stated inAIC latest building for production engineering byAIC Commercial FOR ANCHOR TYPE & GRADE ALWAYS REFER TO ANCHOR BOLT TABLE levels in meter unless noted otherwise (U.N.O.)
Date: accepted Signed contract / agreed schedules 0010 ROOF SHEETING PLAN 21-FEB.-22 00
AIC follows the guidelines of following building codes in Department.AIC Project Department will send the 4 9.4 Before the construction of block work (not 2. Drawings shall not be scaled, follows written
the design of buildings: withAIC Project department. sets of “Issued for Construction” anchor bolt plans to BUILT-UP SECTIONS ASTM A572M Grade 50 or equivalent Fy = 345 N/mm 2
byAIC), all the flange braces for the rigid frame columns 0011 CRANE LAYOUT PLAN 21-FEB.-22 00 dimension
Please return all drawings for the complete building, · 2005 edition of “Minimum Design Loads for Customer. Under no circumstance should the must be fixed to the sidewall girts.
6.2 Phase numbers generally apply to buildings Tubes ASTM A-500 GR.B Fy = 315 N/mm 2 3. All written dimension pertain Block to
signed and dated, toAIC's Head Office Buildings and Other Structures”, by American Society Customer or his Civil Contractor use these approval 0012 SIDE WALL & INTERIOR WALL FRAMING 21-FEB.-22 00
You are requested to select (tick the appropriate of Civil Engineers (ASCE/SEI 7-05).
and not to jobs. Thus a building weighs 300 MT drawings as guide for the placement of anchor bolts. 9.5 ERECTION GUIDELINES:- I-Sections ASTM A36 or equivalent Fy = 240 N/mm 2
Block or Concrete to Concrete.
box), sign and date this block on all the drawings of will be shipped in 3 approximately equal phases of 0013 SIDE WALL SHEETING 21-FEB.-22 00
· SBC-301 SAUDI BUILDING CODE. 100 MT.AIC phase nos. are identified by a 3 digits 03 HOT ROLLED Channels
this buildings in order to make your approval of this 8.4 AIC supply scope includes the supply of anchor bolts a) Start erection at braced bay. ASTM A36 or equivalent Fy = 240 N/mm 2
no. Phase numbers for the PEB Steel Structure SECTIONS
building complete. 2.4 AIC uses MBS software for its design of the that are shipped to the site prior to the building
Pre-Engineered Steel Buildings. MBS software is begin with the number “1”. Thus the 3 phases of a structure and that should be embedded in the pedestal Angles ASTM A572M Grade 50 or equivalent Fy = 345 N/mm 2
b) Use temporary guy wires and ratchet pullers for
1.3 After returning all the drawings for this building developed by Metal Buildings Software, Inc. of Fargo, 300 MT building would be identified as phase nos. necks of foundations and set in the exact locations that stability of frames during erection. Pipes ASTM A53 Grade B or equivalent Fy = 240 N/mm 2
(either “approved as is” or “approved as noted”) North Dakota, U.S.A. It is the world's most recognized 101, 102 and 103. If this 300 MT building is are indicated onAIC “For Construction” Anchor Bolts
toAIC, and assuming that you have fulfilled all software for the design of Pre-Engineered Steel building 2 of job PB-AE1-504, the 3 phases would Setting Plans. The area and depth of pedestal necks c) Install permanent bracing i.e. portal, cables, rods, ASTM A325M TYPE-1; Fully threaded
financial requirements, our Engineering Department Buildings and is the most widely used software for the be identified as 504-02-101, 504-02-102 and must be large enough to accommodate the angles, and flange braces. 04 Primary Connection bolts Ft = 800 N/mm 2
will begin the preparation of production engineering 504-02-103. hot dip galvanized
design of Pre-Engineered Steel Buildings in the world. embedment length and the AIC straight anchor bolts.
output, which comprises of shop drawings, bills of More than 1000 structural engineers in over 120 d) Guy wires should be attached to an immovable object ASTM A475-Extra High Strength BREAKING LOAD
materials and erection drawings, for this building. companies in 6 continents use MBS software daily. 8.5 The setting up of anchor bolts is a very critical Cables
such as cast in anchor bolts. Class A, HDG pu= 119.7 kN
activity and must be made by professional. Civil DIAGONAL
1.4 Any changes received from you after our receipt 2.5 AIC guarantees the stability of the Steel Structure of Contractors who do not have prior experience in this e) Plumb & align the first bay before proceeding.
05
"X" BRACING Rods ASTM A36 or equivalent Fy = 240 N/mm 2
of these (returned) drawings will greatly delay the
delivery of this building. The preparation of
this building and warranties its design which has been
prepared using world recognized software in
7. PURPOSE OF THESE DRAWINGS activity must request the presence ofAIC Erection
Specialist to check the anchor bolts locations prior to f) Use high strength bolts (HSB) where indicated.
HR Angles ASTM A572M Grade 50 or equivalent Fy = 345 N/mm
2
production engineering output for a building with accordance with best engineering practices. casting the concrete. The final responsibility for the Cold formed ASTM A653M SS Grade 340 Class 1:
Fy = 344 N/mm 2
06
moderate complexity generally takes approximately 3 The reason for submitting these drawings to you is for accuracy of anchor bolts placement rests with the secondary members Coating Z275 (Grade 90)
g) Tighten all high strength bolts after final alignment of COORDINATION TRACKER
weeks. It is longer for buildings of high engineering you to do the following: Customer and his Civil Contractor. the building. Secondary Connection
complexity. 07
Grade 4.6 Fully threaded Ft = 400 N/mm 2
bolts (for purlins,girts hot dip galvanized REV VER DESCRIPTION DATE & TIME OF PRINT
7.1 Verify all the dimensions and clearances that we 8.6 All AIC anchor bolts are supplied assembled with
3. RAW MATERIALS
h) Frame alignment should be within the limits set forth by and flange braces)
1.5 Any clarifications shall be handled by have shown on these drawings against your building double nuts, one plate washer (with thickness not . 2016 edition of "code of standard practice for steel FORMAL ISSUE
ASTM Grade A36M Electro galvanized,
respectiveAIC Project Engineer at our head office. usage requirements. less than 6 mm) and one washer. buildings and bridges" (ANSI/AISC 303-16). 2
08 Sag Rods Fully threaded with 4 nuts Fy = 240 N/mm
Coating Z275 (Grade 90)
1.6 AIC Job No. is identified by a 4 digits number that 3.1 AIC usually uses high tensile, grade 50, raw 7.2 Verify the location of all roof accessories, if any.
8.7 Grouting is required under allAIC column base i) Use temporary supports to align girts before fixing ASTM A653M SS Grade 340 Class 1:
is preceded by a 2 or 3 digits prefix. The prefix refers material steel (having a minimum yield strength of 50 Roof accessories may include skylights, ridge sheets. 09 Mezzanine Deck Panels Fy = 344 N/mm 2
ventilators, framed openings, etc. plates. It is the responsibility of the Customer or his Coating Z275 (Grade 90)
to the territory in which the building will be erected. KSI or 34.5 KN/sq.cm.) for all its raw materials, unless
Civil Contractor to provide 50 mm of non shrinkable
Each country is given a prefix as per the International noted otherwise. j) Do not apply any live loads, collateral loads or other
7.3 Verify the location of all wall accessories, if any. grout below the base plates and to ensure that the
Standards Organization. additional loads to purlins before roof sheeting is
Wall accessories may include wall lights, framed grout is packed uniformly under column base plates.
3.2 For a list of the raw materials used to fabricate this completely fastened to purlins.
openings, sliding doors, roll-up doors, personnel walk Grouting must be injected before installing the roof &
SA1 - KSA - Central Province building, please refer to "Material specification" in A01
doors, sand trap louvers, windows, etc. wall cladding and prior to commissioning any
SA2 - KSA - Western Province of the attached drawing. 9.6 Bolts to be tightend by turn off nut method as
equipment (such as cranes) that are supported by the
SA3 - KSA - Eastern Province specified in AISC.
7.4 Furnish missing dimensions that have been shown structure.AIC will provide weep holes in very large
etc.
clouded in these drawings. base plates upon the request from client to facilitate
the application of the grout. Note that it is notAIC
1.7 All the dimensions in these drawings are in
millimeters unless noted otherwise. 4. FABRICATION 7.5 Verify assumed dimensions that have been shown general practice to provide the grout holes. Failure to
properly apply grouting below the base plates may
clouded in these drawings.
1.8 All dimensions to be read from drawings and represent a risk to the building structure for whichAIC is
4.1 Webs of built-up members are made of two or more web not responsible.
should not be measured. 7.6 Mark the location of roof & wall accessories that
plate segments that are butt welded using full 00 21-02-2022 ISSUED FOR APPROVAL 7069-7080-7001
may be listed in these drawings but may not have
penetration welds. 8.8 AIC recommends that the Civil Contractor construct REV DATE ISSUED TO DESCRIPTION DRW-CHK-APP
1.9 Abbrevations: been on these drawings because of the insufficient
information received from you at time of order entry. a 20cm x 20cm concrete column against each steel
4.2 Flanges of built-up members that are made of two column (and in between steel columns for very long
NGL - Natural Ground Level
or more plate segments are Connected by using full bay lengths) adding a concrete coping beam on the top
FFL - Finished Floor Level 7.7 If the building has one or more crane systems
penetration butt welds. of the blockwall (and intermediate horizontal concrete
GL - Grid Line please verify the relevant crane data such as wheel PLOT #: PLOT OWNER:
O/O - Out to Out base dimension, girder type, wheel load, center to beams if the blockwall is very high) to stabilize the R10 TRSDC
4.3 Built-up members are made of two flanges and blockwall.
C/C - Center to Center center dimension of crane beams, top of crane runway CLIENT:
one (tapered or constant depth) web that are
O/C - Out to Center beam dimensions, horizontal & vertical clearance
C/O - Center to Out
assembled and continuously fillet welded, on single side
dimensions of the crane bridge to the nearest 8.9 If the building is a roof system resting on concrete THE RED SEA DEVELOPMENT
only, in an Auto Welding Machine, using a Submerged columns, the stability of the reinforced concrete
CD - Critical Dimension
Arc Welding process to produce semi fabricated
obstruction, etc. You are strongly requested to inform
substructure is not the responsibility ofAIC.
COMPANY
BW - Block Wall (Brick wall) us of the name of your crane manufacturer including a The Red Sea DMO,BLDG No: IN01, 3rd Floor, ITCC Compound
members. Gate No 04, Al Nakheel, Riyadh
CL - Center line contact person in order to ensure that actual crane Riyadh Saudi Arabia 11452
induced loads are accurate and sufficient. 8.10 Guides for sliding doors, which need to be
UNO - Unless Noted Otherwise 4.4 The desired lengths of hot rolled sections are TEL: +966 11 212 0000
embedded in the concrete, are normally shipped with
BAL - Balance achieved by cutting 12m long pieces or by perpetually EMAIL: trsdc@theredsea.sa
7.8 If the building has a mezzanine please verify the Sliding doors. They should be fixed as per the “For
DIA / Ø - Diameter welding pieces. Perpetual welds are full penetration WEB: www.theredsea.sa
clear height dimension below the mezzanine beam, Construction” Sliding door drawings. The final
THK. - Thickness butt welds.
the dimension from top of concrete slab to the lowest responsibility for ensuring the accuracy of the location
No. - Number LEAD CONSULTANT:
vertical obstruction above the slab and the different of door guide angles rests with the customer and his
H.S. Bolt - High Strength Bolt 4.5 Hot Rolled members are cut to length and holes in
FO - Framed Opening them are punched or drilled using an automatic beam
loads acting on the mezzanine. civil contractor. KILLA ARCHITECTURAL DESIGN
SPD - Single Personal Door Office 3103, Burj Al Salam Tower,
processor to produce semi fabricated members. 8.11 Expansion bolts for framed openings or staircases Sheikh Zayed Road, PO Box 26642, Dubai, UAE
DPD - Double Personal Door 7.9 We normally provide you with two sets of approval
drawings for each non-identical building in your job. shall be shipped with framed opening or staircase
SSD - Single Sliding Door 4.6 Semi-fabricated built-up or hot rolled members are
You are requested to mark your comments in red ink materials respectively. Expansion bolts shall be fixed
DSD - Double Sliding Door then fitted with end plates, stiffener plates, gusset
on both sets of drawings, retain one set for your on concrete floor slab based on Final erection TEL: +971 4 3554447
RUD - Roll up Door
Typ - Typical
plates etc. (as required) and then manually welded to
records and return one set toAIC. drawings. desi gn EMAIL: info@killadesign.com
WEB: www.killadesign.com
produce fabricated members.
TOC - Top of Concrete.
TOS - Top of Steel. 7.10 Your notes on each drawing must be very specific
4.7 Secondary members (“Z” purlins & girts, “C” MAIN CONTRACTOR:
LVL - Level such as “increase eave height to 6.6m”, “reduce clear
channels and angles) are cold roll formed using
NTS - Not To Scale height to 5.6m“, etc. Notes such as “should be longer”,
galvanized coils.
GRANKRAFT
“make shorter”, “why not”, etc. must be avoided as
they do not constitute approval and will delay the KRAFTELL
further processing of this building. GROUPE
P. O. Box 23282, Sharjah, U.A.E.,
Tel: 5440366, Fax: 5440388
Web: www.grankraft.com
SUB CONTRACTOR :
PROJECT:
Warehouse in Al Hamriyah
DRAWING NAME :
INDEX
1 1' 2 3 4 5 6 7 8 9 10 11' 11
88140 OUT TO OUT OF STEEL LINE
8814 8814 8814 8814 8814 8814 8814 8814 8814 8814
300 O/C
716 C/O
KEY PLAN
A' S.W. BRACING 300 C/O A'
716 C/O
DIAGONAL
A A
AS.W. BRACING A A A A A A A A A S.W. BRACING A
A1 A1
DIAGONAL DIAGONAL
GENERAL NOTES
BRACED BAY
BRACED BAY
BRACED BAY
2. Drawings shall not be scaled, follows written
dimension
48000
48000
3. All written dimension pertain Block to
Block or Concrete to Concrete.
75 110 60 60 110 75
250
COORDINATION TRACKER
(PROJ)
150
REV VER DESCRIPTION DATE & TIME OF PRINT
96000 OUT TO OUT OF COLUMN FLG.
50
96500 OUT TO OUT OF STEEL LINE
LEAD CONSULTANT:
BRACED BAY
BRACED BAY
Office 3103, Burj Al Salam Tower,
48000
48000
Sheikh Zayed Road, PO Box 26642, Dubai, UAE
250
TEL: +971 4 3554447
desi gn EMAIL: info@killadesign.com
(PROJ)
WEB: www.killadesign.com
150
50
MAIN CONTRACTOR:
GRANKRAFT KRAFTELL
GROUPE
P. O. Box 23282, Sharjah, U.A.E.,
Tel: 5440366, Fax: 5440388
Web: www.grankraft.com
SUB CONTRACTOR :
PROJECT:
Warehouse in Al Hamriyah
DRAWING NAME :
C C
716 O/C
S.W. BRACING S.W. BRACING S.W. BRACING SCALE @ A1: DRAWN: CHECKED: APPROVED:
C' C'
DIAGONAL DIAGONAL DIAGONAL 7069 7080 7001
PROJECT No: DESIGNED BY: DATE OF ISSUE:
1 1' 2 3 4 5 6 7 8 9 10 11' 11
88140 OUT TO OUT OF STEEL LINE
X
8814 8814 8814 8814 8814 8814 8814 8814 8814 8814
300 O/C
716 C/O
A' S.W. BRACING 300 C/O A' Z
Y
716 C/O
DIAGONAL KEY PLAN
A A
A1 S.W.
4 BRACING 1 7 10 13 16 19 22 25 28S.W. BRACING31 A1
DIAGONAL DIAGONAL
GENERAL NOTES
48000
2. Drawings shall not be scaled, follows written
dimension
3. All written dimension pertain Block to
Block or Concrete to Concrete.
COORDINATION TRACKER
96000 OUT TO OUT OF COLUMN FLG.
LEAD CONSULTANT:
48000
Office 3103, Burj Al Salam Tower,
Sheikh Zayed Road, PO Box 26642, Dubai, UAE
MAIN CONTRACTOR:
GRANKRAFT KRAFTELL
GROUPE
P. O. Box 23282, Sharjah, U.A.E.,
Tel: 5440366, Fax: 5440388
Web: www.grankraft.com
SUB CONTRACTOR :
PROJECT:
Warehouse in Al Hamriyah
DRAWING NAME :
C C
C'
S.W. BRACING S.W. BRACING S.W. BRACING 716 O/C C'
SCALE @ A1: DRAWN: CHECKED: APPROVED:
LOADS LEGEND
NOTES FOR REACTIONS
DL Denotes dead load
Building reactions are based on KEY PLAN
the following building data: CL Denotes collateral load
LR Denotes floor live load
ROOF LOADS
LL Denotes live load
DEAD LOAD (kN/m2) = 0.20
WL1 Denotes wind load from left to right with internal pressure
ROOF LIVE LOAD (kN/m2) = 0.6
WR1 Denotes wind load from right to left with internal pressure
COLLATERAL LOAD (kN/m2) = 0.15
BASIC LOADS WL2 Denotes wind load from left to right with internal suction
Wind Speed (3 sec) = 162 (Km/Hr) WR2 Denotes wind load from right to left with internal suction
Wind Code = MBMA 2006 WE1 Denotes wind load parallel to ridge from end wall with internal pressure
IMP0RTANCE FACTOR = 1.00 WE2 Denotes wind load parallel to ridge from end wall with internal suction
GENERAL NOTES
COORDINATION TRACKER
FORMAL ISSUE
LEAD CONSULTANT:
MAIN CONTRACTOR:
GRANKRAFT KRAFTELL
GROUPE
P. O. Box 23282, Sharjah, U.A.E.,
Tel: 5440366, Fax: 5440388
Web: www.grankraft.com
SUB CONTRACTOR :
PROJECT:
Warehouse in Al Hamriyah
DRAWING NAME :
NODE REACTIONS
KEY PLAN
DL50 DL50
DL50
DL50
DL50
DL50
DL50
LEN GTH DL50
DL50
DL50
E DL50
OU TER FLA NG DL50
DL50
DL50 SP02 SP06
DL50
WE B DL50
DL50
DL50
E DL50
INNER FLA NG DL50 SP04
DL50
DL50
ng DL50
Purlins Sp aci DL50
DL50
DL50 SP04
SP02
SP01
DL50
CRANE-2 CRANE-3 CRANE-4
±11828
2. Drawings shall not be scaled, follows written
11922
±10970
DL50
11422
dimension
3. All written dimension pertain Block to
Block or Concrete to Concrete.
DL50
DL50
F.F.L (+0.30)
COORDINATION TRACKER
OUTER FLANGE
INNER FLANGE
EAVE HEIGHT
Girts Spacing
FORMAL ISSUE
WEB
A' A1 B
A
00 21-02-2022 ISSUED FOR APPROVAL 7069-7080-7001
LEAD CONSULTANT:
MAIN CONTRACTOR:
GRANKRAFT KRAFTELL
GROUPE
P. O. Box 23282, Sharjah, U.A.E.,
Tel: 5440366, Fax: 5440388
Web: www.grankraft.com
SUB CONTRACTOR :
PROJECT:
Warehouse in Al Hamriyah
DRAWING NAME :
TYPICAL FRAME
KEY PLAN
DL50 DL50
DL50
DL50
DL50
DL50
DL50 LE NG TH
DL50
DL50
DL50
DL50 OU TE R FLA NG
DL50 E
SP06 SP02 DL50
DL50
DL50 WE B
DL50
DL50
DL50
DL50 INNER FLA NG
SP04 DL50 E
DL50
DL50
DL50 Purlins Sp acin
DL50 g
DL50 DL50
SP04
SP02
CRANE-5
1 TON 1 TON CRANE-8
1 TON
1 TON DL50
GENERAL NOTES
±12078
12180
dimension
±11193
11680
DL50
3. All written dimension pertain Block to
Block or Concrete to Concrete.
DL50
DL50
OUTER FLANGE
INNER FLANGE
REV VER DESCRIPTION DATE & TIME OF PRINT
EAVE HEIGHT
Girts Spacing
FORMAL ISSUE
LENGTH
WEB
B C1 C'
C
00 21-02-2022 ISSUED FOR APPROVAL 7069-7080-7001
TYP FRAME @ GL 2 TO GL 10
* HATCHED AREA DENOTES CHANGE IN WEB THICKNESS FOR WEB PANEL ZONE. PLOT #:
R10
PLOT OWNER:
TRSDC
* 50mm OF NON-SHRINKAGE GROUT WILL BE PROVIDED UNDER COLUMN BASES. CLIENT:
* DL50 : DENOTES FLANGE BRACE L50X3 IN TWO SIDE THE RED SEA DEVELOPMENT
COMPANY
The Red Sea DMO,BLDG No: IN01, 3rd Floor, ITCC Compound
Gate No 04, Al Nakheel, Riyadh
Riyadh Saudi Arabia 11452
TEL: +966 11 212 0000
EMAIL: trsdc@theredsea.sa
WEB: www.theredsea.sa
LEAD CONSULTANT:
MAIN CONTRACTOR:
GRANKRAFT KRAFTELL
GROUPE
P. O. Box 23282, Sharjah, U.A.E.,
Tel: 5440366, Fax: 5440388
Web: www.grankraft.com
SUB CONTRACTOR :
PROJECT:
Warehouse in Al Hamriyah
DRAWING NAME :
TYPICAL FRAME
KEY PLAN
DL50 DL50
DL50
DL50
DL50
DL50
DL50
LENGTH DL50
DL50
DL50
E DL50
OUTER FLANG DL50
DL50
SP03 SP06
DL50
DL50
WEB DL50
DL50
DL50
E DL50
INNER FLANG DL50 SP05
DL50
DL50
g DL50
Purlins Spacin DL50
DL50 DL50
SP05
SP03
SP01
DL50
CRANE-2 CRANE-3 CRANE-4
BOTTOM HEIGHT OF CRANE BEAM
±11828
2. Drawings shall not be scaled, follows written
11922
dimension
±10970
DL50
11422
3. All written dimension pertain Block to
Block or Concrete to Concrete.
DL50
DL50
INNER FLANGE
EAVE HEIGHT
FORMAL ISSUE
LENGTH
WEB
A' A1 B
A
00 21-02-2022 ISSUED FOR APPROVAL 7069-7080-7001
* DL50 : DENOTES FLANGE BRACE L50X3 IN TWO SIDE THE RED SEA DEVELOPMENT
COMPANY
The Red Sea DMO,BLDG No: IN01, 3rd Floor, ITCC Compound
Gate No 04, Al Nakheel, Riyadh
Riyadh Saudi Arabia 11452
TEL: +966 11 212 0000
EMAIL: trsdc@theredsea.sa
WEB: www.theredsea.sa
LEAD CONSULTANT:
MAIN CONTRACTOR:
GRANKRAFT KRAFTELL
GROUPE
P. O. Box 23282, Sharjah, U.A.E.,
Tel: 5440366, Fax: 5440388
Web: www.grankraft.com
SUB CONTRACTOR :
PROJECT:
Warehouse in Al Hamriyah
DRAWING NAME :
END FRAME
KEY PLAN
DL50 DL50
DL50
DL50
DL50
DL50
DL50 LENGTH
DL50
DL50
DL50
DL50 OUTER FLANG
DL50 E
SP06 SP03 DL50
DL50
DL50 WEB
DL50
DL50
DL50
SP05 DL50 INNER FLANG
DL50 E
DL50
DL50
DL50 Purlins Spacin
DL50 g
DL50
SP05
SP03
SP01
CRANE-5
±12078
2. Drawings shall not be scaled, follows written
12180
±11193
dimension
11680
DL50
3. All written dimension pertain Block to
Block or Concrete to Concrete.
DL50
DL50
OUTER FLANGE
INNER FLANGE
EAVE HEIGHT
REV VER DESCRIPTION DATE & TIME OF PRINT
Girts Spacing
FORMAL ISSUE
LENGTH
WEB
B C1 C'
C
00 21-02-2022 ISSUED FOR APPROVAL 7069-7080-7001
* DL50 : DENOTES FLANGE BRACE L50X3 IN TWO SIDE THE RED SEA DEVELOPMENT
COMPANY
The Red Sea DMO,BLDG No: IN01, 3rd Floor, ITCC Compound
Gate No 04, Al Nakheel, Riyadh
Riyadh Saudi Arabia 11452
TEL: +966 11 212 0000
EMAIL: trsdc@theredsea.sa
WEB: www.theredsea.sa
LEAD CONSULTANT:
MAIN CONTRACTOR:
GRANKRAFT KRAFTELL
GROUPE
P. O. Box 23282, Sharjah, U.A.E.,
Tel: 5440366, Fax: 5440388
Web: www.grankraft.com
SUB CONTRACTOR :
PROJECT:
Warehouse in Al Hamriyah
DRAWING NAME :
END FRAME
1 1' 2 3 4 5 6 7 8 9 10 11' 11
88140 OUT TO OUT OF STEEL LINE
8814 8814 8814 8814 8814 8814 8814 8814 8814 8814
(2)250Z18(Typ) 250Z20(Typ) 250Z18(Typ) 250Z18(Typ) 250Z18(Typ) 250Z18(Typ) 250Z18(Typ) 250Z18(Typ) 250Z20(Typ) (2)250Z18(Typ)
300 O/C
716 C/O
A' S.W. BRACING 300 C/O A'
716 C/O
DIAGONAL KEY PLAN
A ST-1 ST-1 ST-1 A
S.W. BRACING S.W. BRACING
A1 A1
DIAGONAL DIAGONAL
GENERAL NOTES
48000
2. Drawings shall not be scaled, follows written
dimension
3. All written dimension pertain Block to
Block or Concrete to Concrete.
FORMAL ISSUE
250Z15(STRUT) 250Z15(STRUT) 250Z15(STRUT)
LEAD CONSULTANT:
HILLSIDE WASHER RAFTER
KILLA ARCHITECTURAL DESIGN
48000
48000
C.P.WASHER BRACE ROD
Office 3103, Burj Al Salam Tower,
Sheikh Zayed Road, PO Box 26642, Dubai, UAE
NUT
SLOT IN WEB TO INSERT TEL: +971 4 3554447
HILLSIDE WASHER desi gn EMAIL: info@killadesign.com
WEB: www.killadesign.com
AND EYEBOLT
MAIN CONTRACTOR:
R=
50
±550
PROJECT:
0
SAG ANGLE
Warehouse in Al Hamriyah
DRAWING NAME :
C1 C1
75
ST-1 ST-1 ST-1 INSIDE FOAM
ROOF FRAMING PLAN
716 O/C
CLOSURE
C C DRIP TRIM RAFTER
716 O/C
SHEETING ANGLE
S.W. BRACING S.W. BRACING S.W. BRACING
C'
DIAGONAL ROOF FRAMING PLAN DIAGONAL DIAGONAL
C' CLOSURE TRIM
FIXING SCREW (GS)
1 1' 2 3 4 5 6 7 8 9 10 11' 11
88140 OUT TO OUT OF STEEL LINE
8814 8814 8814 8814 8814 8814 8814 8814 8814 8814
300 O/C
716 C/O
ROOF PANEL SPECIFICATION
A' S.W. BRACING 300 C/O A' TOP SKIN : PROFILE - CORRUGATED 0.50MM THK.
716 C/O DIAGONAL MATERIAL -GI COLOR - RAL 9002 KEY PLAN
A A FINISH - POLYESTER PAINTED
A A A A A
SECTION - A
B B B B B B B B B B B
SECTION - B
B
A
GENERAL NOTES
48000
SLOPE
SLOPE
SANDWICH PANEL FIXING DETAIL ROOF PANEL DETAIL (ISO VIEW)
dimension
3. All written dimension pertain Block to
Block or Concrete to Concrete.
COORDINATION TRACKER
96000 OUT TO OUT OF COLUMN FLG.
LEAD CONSULTANT:
SLOPE
SLOPE
48000
Office 3103, Burj Al Salam Tower,
Sheikh Zayed Road, PO Box 26642, Dubai, UAE
MAIN CONTRACTOR:
GRANKRAFT KRAFTELL
GROUPE
P. O. Box 23282, Sharjah, U.A.E.,
Tel: 5440366, Fax: 5440388
Web: www.grankraft.com
SUB CONTRACTOR :
PROJECT:
Warehouse in Al Hamriyah
DRAWING NAME :
C C
716 O/C
S.W. BRACING S.W. BRACING S.W. BRACING SCALE @ A1: DRAWN: CHECKED: APPROVED:
C' C'
DIAGONAL DIAGONAL DIAGONAL 7069 7080 7001
PROJECT No: DESIGNED BY: DATE OF ISSUE:
1 1' 2 3 4 5 6 7 8 9 10 11' 11
88140 OUT TO OUT OF STEEL LINE
8814 8814 8814 8814 8814 8814 8814 8814 8814 8814
300 O/C
716 C/O
KEY PLAN
A' S.W. BRACING 300 C/O A'
716 C/O
DIAGONAL
A A
S.W. BRACING S.W. BRACING
A1 A1
4721
DIAGONAL DIAGONAL
CRB-1 CRB-1 CRB-1 CRB-1 CRB-1 CRB-1 CRB-1 CRB-1 CRB-1 CRB-1
TYP. TYP. TYP. TYP. TYP. TYP. TYP. TYP. TYP. TYP.
Crane 1 MT
8500
1650
WHEEL LOAD DIAGRAM FOR 1.0 M.T CRANE
Crane 1 MT
8500
GENERAL NOTES
48000
CRANE NAME 1
1650
CRANE CAPACITY (MT) 1 3. All written dimension pertain Block to
Block or Concrete to Concrete.
CRANE TYPE UNDER HANG
Crane 1 MT
CRANE LOCATION APD
8500
CRANE SYSTEMS MANUFACTURER ABUSE
1650
MAXIMUM WHEEL LOAD (kN) W/OUT IMPACT 8.50
VERTICAL 25%
Crane 1 MT
COORDINATION TRACKER
8500 IMPACT PERCENTAGE HORIZONTAL 20%
REV VER DESCRIPTION DATE & TIME OF PRINT
96000 OUT TO OUT OF COLUMN FLG.
A
B M24 BOLTS
BRACKET
DEPTH
1650
COMPANY
8500
CRANE BEAM / BRACKET ARRANGEMENT DETAIL A The Red Sea DMO,BLDG No: IN01, 3rd Floor, ITCC Compound
Gate No 04, Al Nakheel, Riyadh
Riyadh Saudi Arabia 11452
TEL: +966 11 212 0000
EMAIL: trsdc@theredsea.sa
5 WEB: www.theredsea.sa
10 mm THK. B/U "T"
1650
10 W/ M20
LEAD CONSULTANT:
AIC SCOPE OF WORK IS TO SUPPLY 10 BOLTS TO RAFTER
48000
10 mm THK. B/U "T" Sheikh Zayed Road, PO Box 26642, Dubai, UAE
CRANE BEAM BRACKET
Crane 1 MT
FLANGES 175 x 8
NOTE:
8500
WEB 300 x 5
(MAX. LATERAL LOAD=1.70 KN.) TEL: +971 4 3554447
END PLATE 200 x 20
desi gn EMAIL: info@killadesign.com
WEB: www.killadesign.com
BRACE DETAIL
MAIN CONTRACTOR:
GRANKRAFT KRAFTELL
1650
GROUPE
P. O. Box 23282, Sharjah, U.A.E.,
Tel: 5440366, Fax: 5440388
Web: www.grankraft.com
Crane 1 MT
8500
Warehouse in Al Hamriyah
80
200X10 FLG
GRIND
SMOOTH DRAWING NAME :
VIEW B
C1 C1 CRANE LAYOUT PLAN
716 O/C
C C
716 O/C
S.W. BRACING S.W. BRACING S.W. BRACING SCALE @ A1: DRAWN: CHECKED: APPROVED:
C' C'
DIAGONAL DIAGONAL DIAGONAL ** Customer to Verify dimension 7069 7080 7001
PROJECT No: DESIGNED BY: DATE OF ISSUE:
1 2 3 4 5 6 7 8 9 10 11
88140 OUT TO OUT OF STEEL LINE
KEY PLAN
8814 8814 8814 8814 8814 8814 8814 8814 8814 8814
(2)250Z18(Typ) 250Z20(Typ) 250Z18(Typ) 250Z18(Typ) 250Z18(Typ) 250Z18(Typ) 250Z18(Typ) 250Z18(Typ) 250Z20(Typ) (2)250Z18(Typ)
250Z18 250Z15 250Z15 250Z15 250Z15 250Z15 250Z15 250Z15 250Z15 250Z18
GENERAL NOTES
1 2 3 4 5 6 7 8 9 10 11
88140 OUT TO OUT OF STEEL LINE
COORDINATION TRACKER
FORMAL ISSUE
8814 8814 8814 8814 8814 8814 8814 8814 8814 8814
LEAD CONSULTANT:
SUB CONTRACTOR :
PROJECT:
Warehouse in Al Hamriyah
DRAWING NAME :
KEY PLAN
1 2 3 4 5 6 7 8 9 10 11
88140 OUT TO OUT OF STEEL LINE
8814 8814 8814 8814 8814 8814 8814 8814 8814 8814
GENERAL NOTES
COORDINATION TRACKER
FORMAL ISSUE
LEAD CONSULTANT:
MAIN CONTRACTOR:
PIR FM : Density (Kg/m3) : 35-40 50MM THK.(excluding rib depth) Fax : +966 2 591 0099
PROJECT:
First Issue Date : 20/05/2006 : ﺗﺎﺭﻳﺦ ﺃﻭﻝ ﺇﺻﺪﺍﺭ Enviroment No. : 1323 : ﺍﻟﺮﻗﻢ ﺍﻟﺒﻴﺌﻲ
Issue Date : 22/05/2021 : ﺗﺎﺭﻳﺦ ﺍﻹﺻﺪﺍﺭ FCR No. : - : ﺍﻟﺴﺠﻞ ﺍﻟﻤﺮﻛﺰﻱ ﺍﻟﻤﻮﺣﺪ
Expiry Date : 21/05/2022 : ﺗﺎﺭﻳﺦ ﺍﻹﻧﺘﻬﺎﺀ Trade Name No. : IN-1001320 : ﺭﻗﻢ ﺍﻹﺳﻢ ﺍﻟﺘﺠﺎﺭﻱ
Activities ﺍﻷﻧﺸــــﻄــﺔ
Activity ﺍﻟﻨﺸﺎﻁ #
1 Steel Welded Tubes and Pipes Manufacturing ﺻﻨﺎﻋﺔ ﺃﻧﺎﺑﻴﺐ ﻭﻣﻮﺍﺳﻴﺮ ﻣﻠﺤﻮﻣﺔ ﻣﻦ ﺍﻟﺼﻠﺐ 1
2 Metal Coating ﻃﻼﺀ ﺑﺎﻟﻤﻌﺎﺩﻥ 2
Products ﺍﻟﻤﻨﺘﺠﺎﺕ
Product ﺍﻟﻤﻨﺘﺞ #
1 Welded Steel Pipes ﺃﻧﺎﺑﻴﺐ ﺻﻠﺐ ﻣﻠﺤﻮﻣﺔ 1
2 Hot-Dipped Galvanized Welded Steel Pipes ﺃﻧﺎﺑﻴﺐ ﺻﻠﺐ ﻣﻠﺤﻮﻣﺔ ﻣﺠﻠﻔﻨﺔ ﻋﻠﻰ ﺍﻟﺴﺎﺧﻦ 2
IR-4133114 - 21/04/2021
Page1 of 1 TAHAQAQ ﺗﺤﻘﻖ
idb.added.gov.ae
8 . Previous approvals for reference
fiIBBilI
a-6tr-ll 5;l + i t iJL-LS3'-l .r--=t-'o
MAJID BUKATTARA GENERAL TRADING
72019/06123 :g;tiJl
crl$-dldii,.Li]
EOUIPMENT DETAILS
6tt-eJl ;r-t i.)t*I rJt{J eL 6lrij.ll Jt
MODEL NO. COC NO. COUNTRY OT ORIGIN
{rHlp-Yl 6.rtrll !+ I
TRADE NAME EQUIPMENT S
1" x 6mtr. YIZY. i Jrj.ll i.#.
Jdl €lJl-y iJlyJfll d.+l
- 02 nos,
EX16065 UNITED ARAB EMIRATES
I METALIC SPRINKLER PIPE
\
AJMAL STEEL SCHEDULE 40 STEEL PIPE
Please be informed that, based on the evaluation of submitted Update application, your company's record has been updated in our list of vendors
groups have been added /changed/de-linked (as specified in the action column) .
The following accepted stock list product groups have been added /changed/de-linked (as specified in the action column) .
It is important to be aware that you have to follow the manufacturer pre-qualification process for any manufacturer you represent whose products
projects.
Please note that at the time of release of enquiries, a further short listing takes place based on the specific scope of work .
You are advised to quote your ZADCO registration code 101123 in all future correspondence.
Comments:
UPDATED
For further assistance, please logon to our Frequently Asked Questions page
or contact us via e-mail.
Regards,
Log in information for the E-registration system ( i.e. username and password) are the property of the locally Licensed/registered agent in Abu Dhabi; such log in inf
otherwise transferred to third parties and others, suppliers doing so will be granting access to his information and information of his principals/associates at his sole
1
e-Prequalification Registration Request # 246 Notification
Prequalification
Tel.: 0097125501131
We are referring to your registration request submittal online dated 18/06/2011. We have reviewed and
evaluated the same, and are pleased to inform you that, your Company is now considered as a potential Vendor
to National Petroleum Construction Co. (NPCC), for the following activities listed below:
# Activity Name
1 RIGGING ITEMS - SCAFFOLDING (TUBULARS, COUPLERS ETC.)
Other activities STEEL PIPES
Nevertheless, this approval should not be construed as a commitment by NPCC to invite you on all our Bid
Invitations or to purchase from you, but you will be allowed to participate in our future Bid Invitations as & when
the opportunity arises solely at NPCC's discretion for the supply of above activities.
Further, you are advised that your facilities may be subjected to periodic Inspection/Audits by NPCC.
Please view our General Purchase Conditions, which will be referred to in our Bid Invitations.
Regards,
Important Note:
Please DO NOT reply to this email. It’s auto-generated by our system.
EMPOWER ENGINEERING
Dears;
Regards
Essam Mahmoud
PQ Engineer – 02/6051138
050/5702477
Product
PG Description Principal Principal Name MLCAS_P License Type Status
Group
AIC Steel warrants its materials for …….. for steel materials and from the last substantial shipment of all
the Steel Structures contained in this job. This warranty extends only to material manufactured by AIC
Steel stating that such material shall not fail due to defective raw material or workmanship when utilized
in the intended manner.
AIC Steel warrants that the structure shall support load described in AIC Steel drawing & contract; and that
the complete system designed by AIC Steel comprised only of parts made by AIC Steel and is used in
manner and the purpose for which it was designed will perform as intended.
This warranty is contingent upon the fact that no changes are made to any of the Steel Structures in this job
prior or during the warranty period without the prior notification. This is to ensure that the design integrity
of the PEB Steel Structures is not compromised by such Changes.
This warranty becomes valid to be submitted only with official letter from AIC stating that the full contract
amount for the supply and erection for this job is received by AIC Steel.
Company Stamp