Professional Documents
Culture Documents
Bur - premix
Bur - premix
Bur - premix
60mm (finishes) layer of asphalt concrete binder course spread and levels
M2 RM23.68
tofall and chambers and well rolled as specified
DATA MANIPULATION RM RM
1 MATERIAL COST
3 LABOUR COST
a) 2 plant operator
b) 1 general worker
BRC A10 (A392) weight 6.16kg/m with 225mm side and 125mm end laps M2 RM26.64
DATA MANIPULATION RM RM
1 MATERIAL COST
laps percentage : 9%
wastage : 5%
wire fastener &
10 %
spacer blocks :
total additional : 24 % RM4.09 RM21.15
3 LABOUR COST
Others
FINAL TOTAL RM26.64 /m2