Professional Documents
Culture Documents
Manpower Schedule Include & Daily Rept-(Date, 36 Oct 2021) Doc.Mst-N0
Manpower Schedule Include & Daily Rept-(Date, 36 Oct 2021) Doc.Mst-N0
1 9-Jun-21 Mr. Mahardika 11-Jun-21 SP-040 Provide Permanent Platform for Wellpad-C 1. PH 1 Prs Fab-Platform PT, Sdbltg-Pntg Instll Platform
Mr. Eko Susilo GTT and GTC in Air Intake 2. Fitter-1 2 Prs 17 Days Job-Complated 22 1 1 1 PB60 CPF WS-Clakep Wellpad-C
HVAC WPC (for KK PB) Sep 2021 In Progress
Mr. Junaidy 3. Helper 1 Prs
4. HSE 1 Prs 1 1 1 1 1 0 1 1 1 1 1 1 0 1 1 1 1 1 1 0 1 1 1
2 9-Jun-21 Mr. Mahardika 11-Jun-21 SP-057 Additional & Modification Acess 700 1. PH 1 Prs Fab Platform PT, Sndblstg-Pnt Instll Pltfm
Mr. Eko Susilo Platform for Line Number: 2. Fitter-1 1 Prs 13 Days Job-Complated 1 PB60 CPF WS-Clakep Area-700 CPF
Mr. Junaidy 24" MV-684501-28 outlet 3. Helper 2 Prs Sep 2021 Job Complated
injection Water Surge Tank 4. HSE 1 Prs 1 1 1 1 0 1 1 1 1 1 1 0 1 1 1
ABJ-684501
3 9-Jun-21 Mr. Mahardika 11-Jun-21 SP-058 Additional & Modification Acess 700 1. PH 1 Prs Fab Platform PT, Sndblstg-Pnt Install Pltfm CPf
Mr. Eko Susilo Platform for Line Number: 2. Fitter-1 1 Prs 17 Days Job-Complated 8 PB60 CPF WS-Clakep Area-700 CPF
Mr. Junaidy 24" MV-684501-28 outlet 3. Helper 1 Prs Sep 2021 Job Complated
injection Water Surge Tank 4. HSE 1 Prs 1 1 0 1 1 1 1 1 1 0 1 1 1 1 1 1 0 1 1 1
ABJ-684502
4 9-Jun-21 Mr. Mahardika 9-Jun-21 SP-049 Relocate 16" 150# Flowmeter WPC 1. PH 1 Prs Remove FLM Fab Spool 16" Install FLW-M
Mr. Eko Susilo from WPC to CFF Disperson 2. Fitter-1 1 Prs 15 Days WPC WS-Clakep Area-KP.17&18
Ponds Job Complated
Mr. Junaidy 3. Helper 1 Prs
4. HSE 1 Prs Job-Complated 15 1 1 1 1 1 1 0 1 1 1 1 1 1 0 1 1 1
Modification Pipe Spool 16" KP-17/18 Sep 2021
Flometer at Gate Control Box
5 9-Jun-21 Mr. Mahardika N/Y SP-049 Cutting Pipe Spool 16"-150#RF WPC 1. PH 1 Prs Ctg Spl
Mr. Eko Susilo PVR Flometer 2 Joint at Wellpad-C 2. Fitter-1 1 Prs 2 Days WPC
Job-Complated 2
Mr. Junaidy 3. Helper 1 Prs JB Cmpld
Sep 2021
4. HSE 1 Prs 1 1
6 9-Jun-21 Mr. Junaidy N/Y SP-076 Additional Floor Concreate for PB61 1. PH 1 Prs Fab-Strc Rbr & Purg Concrt Fab & Install Pipe HDPE
Area Tank Chimical at Area 2. Fitter-1 1 Prs 12 Days PB61 CPF PB61 CPF
PB61 Job Complated Plan Construction
3. Helper 1 Prs
4. HSE 1 Prs Job-Complated 1 1 0 1 1 1 1 1 1 1 0 1 1 1
Replacement Pump & countinue to 1"
Fabrication, Installation Pipe 1"- Chemical HDPE
HDPE From PB61 to Water
Clarifie Raw Water Area
7 09/06/2021 Mr. Junaidy N/Y SP-067 Remove Hose 10-300# & Blind 400 1. PH 1 Prs Remove Hose 10-300
Flange Location Waste Pond 2. Fitter-1 1 Prs 4 Days Job-Complated 19 Area 400
3. Helper 1 Prs Augst 2021 Job Complated
4. HSE 1 Prs 1 0 1 0 1 1
10 09/06/2021 Mr. Mahardika 9-Sep-21 SP-068 Repaire pipe spool 16" Pin RWB 1. PH 1 Prs Repaire & Instll Dabler
Mr. Eko Susilo Hold at Discharge Pump-E 2. Fitter-1 1 Prs 8 Days Job-Complated 11 Area RWB
Mr. Junaidy 3. Helper 1 Prs Sep 2021 Job Complated
4. Welder 1 Prs 1 1 0 1 1 1 1 1 1
5.HSE 1 Prs
11 9-Sep-21 Mr. Eko Susilo N/Y SP-073 Fabrication & Installation 2 800 1. PH 1 Prs Fab-Platform WSAC A/B PT, Sdbltg-Pntg Instll Platform
Platform WSAC for Acess 2. Fitter-1 1 Prs 17 Days PB60 CPF WS-Clakep WSAC Area 800
operate Valve 4" In-Progress 50%
3. Helper 1 Prs In Progress
4. Welder 1 Prs 1 1 1 1 1 0 1 1 1 1 1 1 0 1 1 1 1 1 1
5.HSE 1 Prs
12 29-Aug-21 Mr. Mahardika N/Y SP-071 Fabrication & Installation 1" HRSG-D 1. PH 1 Prs Fab-Pp Spool Pntg & NDT Install
Mr. Eko Susilo Sampling Line 2. Fitter-1 1 Prs 9 Days Ready for PB60 WS Clankep HRSG-D
3. Helper 1 Prs Construction Const Plan Schedule
4. Welder 1 Prs 1 1 0 1 1 1 1 1 1 0 1
5.HSE 1 Prs
13 24-Aug-21 Mr. Mahardika N/Y SP-066 Fabrication & Installation 2" HRSG-D 1. PH 1 Prs Fab Pipe Spool Pntg & NDT Install
Mr. Eko Susilo Drain Line System 2. Fitter-1 1 Prs 11 Days Ready for PB60 WS Clankep HRSG-D
3. Helper 1 Prs Construction Const Plan Schedule
4. Welder 1 Prs 1 1 0 1 1 1 1 1 1 0 1 1 1
5.HSE 1 Prs
15 26-Aug-21 Mr. Junaidy N/Y SP-072 Fabrication & Installation Wellpad-A 1. PH 2 Prs Fab-Platform C& Installation Foundation & Platform
Platform for Acess operate Wellpad-B 2. Fitter-1 3 Prs 0 Days Workshop WS Clankep Location Instr Corosin Inhibitor Wellpad A/B/C
Valve at Location Corrosin Ready for
Wellpad-C 3. Helper 3 Prs Construction Plan Schedule
Inhibitor; A/B/C Construction
4. Welder 2 Prs 1 1 1 1 1 1 0 1 1 1 1 1 1 0 1 1 1 1 1 1 0 1 1 1 1 1 1 0 1 1 0 1 1 1 1 1 1 0 1 1 1 1 1 1 0 1 1 1 1 1 1 0 1 1 1
5.HSE 1 Prs
16 29-Aug-21 Mr. Mahardika N/Y SP-074 Fabrication & Installation 1" HRSG-A 1. PH 1 Prs Fab Pipe Spool Pntg & NDT Install
Mr. Eko Susilo Sampling Line 2. Fitter-1 1 Prs 11 Days PB60 WS Clankep HRSG-D
In-Progressn 50%
3. Helper 1 Prs In Progress
4. Welder 1 Prs 1 1 0 1 1 1 1 1 1 0 1 1 1
5.HSE 1 Prs
17 24-Aug-21 Mr. Mahardika N/Y SP-075 Fabrication & Installation 2" HRSG-A 1. PH 1 Prs Fab Pipe Spool Pntg & NDT Install
Mr. Eko Susilo Drain Line System 2. Fitter-1 1 Prs 11 Days PB60 WS Clankep HRSG-D
In-Progressn 50%
3. Helper 1 Prs In Progress
4. Welder 1 Prs 1 1 1 1 1 0 1 1 1 1 1 1 0
5.HSE 1 Prs
19 15-Sep-21 Mr. Eko Susilo N/Y SP-065 Fabrication & Installation Pipe 1600 1. PH 1 Prs 11 Days Fab Spool 6" GL sx
Spool 6"-GZ-654-0091-E9E 2. Fitter-1 1 Prs WS-Clakep Area-1600
Area 1600 In-Progressn 65%
3. Helper 1 Prs In Progress
4. Welder 1 Prs 1 1 0 1 1 1 1 1 1 0 1 1 1
5.HSE 1 Prs
Page 1 of 1