Professional Documents
Culture Documents
wtc2015_fullpaper_matsuo-4
wtc2015_fullpaper_matsuo-4
Keywords: SENS, urban tunnel, Shield. Extruded concrete lining system, NATM
1. Introduction
The Nishiya Tunnel on the Sotetsu - JR Through Line is the first project to be executed in an
urban area with the “extruded concrete lining system with shield” (hereafter SENS). This is the
third case that the SENS has been used; previously, it had been used to construct the
Sanbongihara Tunnel on the Tohoku Shinkansen (bullet train) Line and the Tsugaru-Yomogita
Tunnel on the Hokkaido Shinkansen Line. However, the previous two cases were the tunnel
construction in a mountainous area. This tunnel is the first trial of the use of the SENS in an urban
area with many adjacent structures. The primary characteristic of the SENS is that extruded
concrete is used for the primary lining instead of segments. During the excavation, the concrete
placement pressure may cause displacement of the ground surface, and actual uplift has been
confirmed in the shallow earth covering sections in mountainous areas. Accordingly, in order to use
the SENS in an urban area, it was necessary to conduct a study of tunneling control methods that
included both face pressure and concrete placement pressure, in addition to methods of dealing
with risk in shallow earth covering sections, and constrain displacement with respect to adjacent
structures.
This paper will report on the method used to manage the construction directly beneath National
Route 16, in a location with a shallow earth covering and the presence of numerous adjacent
structures, as well as the results of the construction.
3. Overview of construction
3.1 OUTLINE OF Nishiya Tunnel
Nishiya Tunnel extends for a length of 1,446 m. It has a curvature of R550 m near the Nishiya
Table 2 Intersecting and adjacent structures Station and R600 m near the Hazawa
Station. The maximum longitudinal
Intersecting /
Intersecting or Distance from
gradient is 35% and the minimum is
adjacent Location
adjacent tunnel 10%. The earth covering of the tunnel
structure varies between 6 m and 46 m.
National
Sections with a shallow earth covering
Route 16
Aboveground Intersecting 6.6m of 1D or less extend for approximately
150 m on the starting point side and
Yokohama approximately 100 m on the endpoint
Municipal
Aboveground Intersecting 12.7m side. The maximum ground water level
Ring Road is tunnel crown + 18.7 m. As indicated
No. 2 in Table 2, the distinguishing
Yokohama characteristics of this tunnel are that it
Municipal crosses or comes near many important
Ring Road To left of tunnel Adjacent 8.0m structures, and the area directly above
No. 2 ramp the tunnel is crowded with private
abutment residences.
In the sections with shallow earth covering on the starting point and endpoint sides, soft alluvial
cohesive soil (Ac) (N<1) is present above the excavated cross-section, so ground improvement
was conducted. Fig. 3 shows a geological profile of the Nishiya Tunnel.
SENS is a tunnel support system in which, while the ground is being initially excavated using a
sealed earth pressure balance type shield tunneling machine (with the face being stabilized at the
„SEE Tunnel:Promoting Tunneling in SEE Region“
ITA WTC 2015 Congress and 41st General Assembly
May 22-28, 2015, Lacroma Valamar Congress Center, Dubrovnik, Croatia
same time), concrete is pressurized at the shield tail section and placed to provide extruded
concrete lining (ECL) that will serve as the primary lining to support the tunnel, concurrently with
the shield tunneling excavation.
Subsequently, the stability of the primary lining is confirmed by taking measurements, and at the
same time the New Austrian Tunneling Method is used to construct the secondary lining to
complete the tunnel. "SENS" is an acronym formed from the first letter of each of these
technologies: SENS (Shield + Extruded concrete lining + New Austrian Tunneling Method +
System).
Fig. 6 shows the standard cross-section for the Nishiya Tunnel. The external diameter of the tunnel
is 10,400 mm, and the tunnel is made up of a primary lining (300 mm), a secondary lining (300
mm) and primary and secondary inverts. Between the primary and secondary linings, a full-
perimeter waterproofing sheet was constructed to provide improved water cut-off performance
and form a waterproof tunnel structure.
„SEE Tunnel:Promoting Tunneling in SEE Region“
ITA WTC 2015 Congress and 41st General Assembly
May 22-28, 2015, Lacroma Valamar Congress Center, Dubrovnik, Croatia
In applying the SENS to an urban environment, unlike the construction in mountain areas, the
construction had to be done safely to avoid affecting structures in the surrounding area and
conditions at the surface. Furthermore, tunneling and concrete placement would have an effect in
shallow earth covering sections, and there would be an enormous impact on society in the event
that major displacement occurred in an urban environment in particular.
As the SENS uses extruded concrete lining instead of the shield segments, it was extraordinarily
important to maintain appropriate control of not only the shield face earth pressure but also the
concrete placement pressure. In past cases of ground surface displacement due to the effect of
SENS concrete placement pressure, an uplift of up to 90 mm was observed in a shallow earth
covering of approximately 5 m. 2) Accordingly, in applying SENS to areas with a shallow earth
covering, the effect not only on conditions at the surface but also underground facilities beneath
the road and the leakage of excavation additives were a concern. The following are the risks and
the measures that were taken for these risks.
1) Effect on surface conditions and adjacent structures caused by SENS face earth pressure and
concrete placement pressure
To avoid affecting surface conditions and adjacent structures, it is necessary to set suitable control
values for face earth pressure and concrete placement pressure. In some cases, protective
measures also needed to be implemented to prevent displacement of adjacent structures, in
addition to conducting appropriate control by means of measurement.
halted and repair of the road surface and underground structures was required. The most
stringent control value was the one for
Table 3 Control values for road surface and underground objects displacement of gas pipes (± 8 mm)
(primary control value). The limit values
Road Sewer pipes / Gas pipes for displacement of the gas pipe and
manholes (ø400 steel TELEPHONE cables were both ± 20 mm.
pipe)
For measurement control in underground areas, measurements (once every 2 hours) of gas pipes
were conducted using a subsidence rod. For the sewer and rainwater manholes that were
extremely close to the tunnel, automatic displacement measurements (once every five minutes)
were performed for the manholes using pressure type subsidence gauges placed at the top of the
manholes.
Tunneling directly beneath National Route 16 began on April 21, 2014 from 1,136R (assembly
ring). The results of construction in the sections before and after National Route 16 are shown
below. Ring management was performed using the assembly rings in the shield tail section, so if
the position of the assembly ring is 0R, the face ring was at +8R and the concrete placement ring
was at -1R.
6.1 Manual displacement measurements for road surface and gas pipes
Of the results of manual measurements for the road surface and gas pipes, this section will
„SEE Tunnel:Promoting Tunneling in SEE Region“
ITA WTC 2015 Congress and 41st General Assembly
May 22-28, 2015, Lacroma Valamar Congress Center, Dubrovnik, Croatia
Accordingly, with regard to the manual displacement measurements for the road surface and gas
pipes, tunneling directly under National Route 16 was achieved without exceeding the primary
control values as a result of appropriate adjustment of the control values based on the
construction management procedure.
„SEE Tunnel:Promoting Tunneling in SEE Region“
ITA WTC 2015 Congress and 41st General Assembly
May 22-28, 2015, Lacroma Valamar Congress Center, Dubrovnik, Croatia
6.4 Summary
The risks of tunneling in sections with a
shallow earth covering in an urban area and
measures to deal with these risks were studied,
and tunneling control methods and protective
measures were implemented. Firstly, in the trial
sector, appropriate control methods for face
earth pressure and concrete placement
pressure were established. In addition,
protective measures and control by means of
measurement were implemented for the
possibility that excavation additives would erupt
from the surface of the ground, and for the
underground objects very close to the tunnel.
Fig.15 View after primary lining concrete placement Furthermore, to prevent trouble with the pipes
from occurring during continuous tunneling,
resulting in the shield machine being stopped in
the middle of the process, the same value for
the scope of actual tunneling (24R) was used
even in the section directly beneath National
Route 16. Based on the above, a construction
management procedure for the National Route
16 section was prepared for the execution of
the construction, and as a result the
displacement of the road surface and
underground objects in the National Route 16
section was less than the primary control value,
making it possible to keep the impact on road
surface and buried objects to a minimum.
Fig.16 Shield machine after arrival at Nishiya Shaft Moreover, the primary lining thickness also
satisfied the design value, and little concrete cracking and almost no water leakage was detected.
7. Conclusion
Up to now, the SENS had been used for construction only in mountain areas, and there was no
precedent for construction under the difficult conditions of a shallow earth covering in an urban
area. In addition, as a result of the placement pressure for cast-in-place concrete, uplift at the
ground surface had occurred in construction up to now in shallow earth covering sections in
mountain areas. Based on these considerations, when applying the SENS in an urban area,
appropriate control methods for face earth pressure and concrete placement pressure as well as
risks were studied to ensure that the road surface and structures in the surrounding area would
not be affected. As a result, the tunnel was successfully constructed directly beneath National
Route 16 without incident. Construction of the tunnel using the SENS began in February 2013, and
the Nishiya Shaft was reached on May 1, 2014. (Fig.16)
At present, dismantling of the shield machine has been completed. The machine has been placed
temporarily at a location near the departure shaft, and preparations are underway for the start of
construction of the next tunnel, the Hazawa Tunnel. As in the case of this tunnel, the Hazawa
Tunnel will have many nearby adjacent structures. For this reason, the differences between the
analysis values and the actual measurements in the case of this tunnel must be studied, and the
results must be reflected in study and analysis of the impact of the Hazawa Tunnel.
Finally, the authors would like to express their profound gratitude to Visiting Professor Yukinori
Oyama of Ritsumeikan University and many others for their guidance and assistance in the
planning and construction of this tunnel.
„SEE Tunnel:Promoting Tunneling in SEE Region“
ITA WTC 2015 Congress and 41st General Assembly
May 22-28, 2015, Lacroma Valamar Congress Center, Dubrovnik, Croatia
8. References
1)Hiromi Iida: “Cast-in-place support system using shield machine in an unconsolidated mountain
area containing water” (Waseda University Dissertations, pp. 3, February 2008)
2)Toshihiko Miyazaki, Mikio Mikami, Atsuhiro Tanaka and Koichi Nishikawa: “The Tsugaru Yomogita
Tunnel on the Hokkaido Shinkansen (bullet train), constructed at an average rate of progress of
190 meters per month using SENS” (Tunnel and Underground, Vol. 44, No. 7, pp. 483 - 490, July
2013)
3)Kazuhiko Takeda, Satoru Sakata, Koji Wada and Eiji Matsumura: “The Nishiya Tunnel on the
Sotetsu - JR Through Line: Trial construction for construction management of SENS in an urban
environment” (Tunnel and Underground, Vol. 45, No. 5, May 2014)