EXPERIMENT NO: 5

To prepare the detailed estimate of small septic tank and soakpit from the given set of drawings using
Details of Measurement and Calculations of Quantities
SL No: Particulars No: Length(m) Breadth(m) Height(m) Quantity (cu m)
1 Earthwork excavation
Septic Tank 1 2.8 1.7 1.95 9.28
Soakpit upto 3 m depth 1 3.14 3 9.42
Soakpit lower portion 1 1.54 0.2 0.31
Total 19
2 Cement Concrete 1:3:6
Foundation 1 2.8 1.7 0.2 0.95
Sloping Floor 1 2 0.9 0.05 0.09
Total 1.04
1st class BW in 1:4 CM in septic
3 tank
1st step: Long wall 2 2.6 0.3 0.6 0.94
Short wall 2 0.9 0.3 0.6 0.32
2nd step: Long wall 2 2.4 0.2 1.15 1.1
Short wall 2 0.9 0.2 1.15 0.41
Total 2.78
4 2nd class BW in 1:6 CM in soak pit
Upper portion 1 3.77 0.2 0.5 0.38
Lower portion 1 3.77 0.2 0.2 0.15
Total 0.53
5 2nd class dry BW in soak pit 1 3.77 0.2 2.5 1.89
6 Precast RCC work
Roof cover slab of septic tank 1 2.4 1.3 0.075 0.23
Roof covr slab of soak pit 1 1.54 0.075 0.12
Baffle wall in septic tank 1 1 0.04 0.45 0.02
Total 0.37
12mm cement plastering in septic
7 tank
Long wall 2 2 1.7 6.8
Short wall 2 0.9 1.7 3.06
Total 9.86
20mm cement plaster in the floor of
8 septic tank 1 2 0.9 1.8
9 50mm size brick aggregate
Outer side of soak pit 1 4.87 0.15 2.5 1.83
At bottom of soak pit 1 0.78 0.2 0.16
Total 1.98
10 Coarse sand- Outer side of soak pit 1 5.81 0.15 2.5 2.18