SAMA YAS – Main Construction

Works in Yas Island

INDEX

1.0. Purpose

2.0. Scope

3.0. References

4.0. Responsibilities

5.0. Definitions

6.0. Resources

7.0. Sequence

7.1. General

7.2. Pre commencement Requirement

7.3. Work Procedure

8.0. Quality & Testing

9.0. Attachments
1.0 Purpose:

The purpose of this document is to lay down the systematic procedures for the various activities
required in the External Civil Works carried out in the project . Also to ensure that all works are carried
out in accordance with the approved shop drawings & contract specification.

2.0 Scope:

This method statement covers external civil works required for the projects. It generally encompasses
the following:

➢ Fencing

➢ Porcelain/Precast stone paving works

➢ Kerb Stone Laying

➢ Kerbstone Laying

➢ Timber Laying

Soft landscape works includes of plantation works, excavation, sweet soil filling, storage, planting, etc as
per project specification, drawing approval & contract documents.

3.0 References:

Standard Specification

Particular Specification

Standard Drawings

Particular Drawing

Bill of Quantities

4.0 Responsibilities:

4.1 Project Manager:

1. Overall responsible & full authority of all activities at the project site.

4.2 Project Engineer:

1. The coordinating to the employer for any clarification.

2. The provision of details of various activities and obtain set out/check as needed.

3. Following up of approved drawings with current revision.

4. Safety precautions and measures as per risk assessment plan.

4.4 Quality Engineer:

1. Ensure all the project key requirements are identified & fulfilled in method statement.

2. Revise the method statement whenever essential during the entire duration of project.

3. Verify the document used / referred is approved and of current revision.

4. Check the relevant materials are approved and inspected at site.


5. Perform the test as mentioned in the approved ITP and relevant records should be maintained.

4.5 Site Supervisor / Site Forman:

1. Ensure that work force is familiar with the activity.

2. Comply with the relevant safety requirements highlighted.

4.6 Safety Engineer / Project Safety Officer:

1. Ensure Risk involved in the activity is assessment & relevant control measures are put in place.

2. Ensure & monitor the adequate safety requirements are fulfilled during all stages of work.

4.6 Surveyor:

1. Responsible for the survey related works.

2. Ensures that adequate temporary control points are available to the vicinity of work site.

4.7 Document Controller:

1. Safe custodian of the Original “MASTER COPY” document.

2. Issue of controlled document to the identified recipient of Document Distribution Matrix.

3. Re issue to all recipients & withdraw of “superseded documents” when revision takes place.

5.0 Definitions:

Client : ALDAR

Consultant : MOTT MACDONALD

Contractor : Al Geemi Contracting Company L.L.C.

6.0 Resources

6.1 Manpower:

Workforce:

1. Mason

2. Helper

3. Landscape Labour

4. Gardener

General Supervision:

5. Site Foreman

6. QA/QC Engineer

7. Safety in charge

8. Site Engineer

9. Surveyor

6.2 Tools & Equipment:


1. Six Wheel

2. Backhoe Loader

3. Water tanker

4. Skid Steer Loader

5. Shovel

6. Steel Hammers

7. Masonry Tools

8. Cutting Machine/Powe Saw

9. Plate compactor

10. Roller Compactor

11. Rubber tampering hammer

12. Spatulas and Electric tile cutter

13. Aluminium Tubes & Angles

14. Spirit Level / String

6.3 Materials:

1. PPortable Water

7.0 Sequence of activity:

7.1 General:

1. Relevant personal protective equipment should be provided and utilized by the workforce.

2. Appropriate Safety guidelines must be adhered during all stages of construction activity.

1.

1.

2.

1.

8.0 Quality & Testing:

1. Prior to any concrete testing client / consultant shall be notified about the testing location, Date,
time & type of testing.

2. MIR to be raised for material upon received to the site.

3. Work Inspection Requests (WIR) shall be raised to the Client/Consultant for the following stages
of work as per ITP.

4. Relevant test report shall be maintained & copy shall be forwarded to the client / consultant.
9.0 Attachments:

1. ITP

2. Task Risk Assessment