Professional Documents
Culture Documents
Estimate Summary
Estimate Summary
RDA/ADB/IROAD-2(WP)/ICB/CL-03
COST TO COMPLETION
ITEM CONTRACT BOQ (A)
Bill No Sec. DESCRIPTION UNIT RATE
Bill Pay QUANTITY AMOUNT
1A BILL No.1 A : PRELIMINARY AND GENERAL ITEMS
1A 1.1 1.1 MAINTENANCE OF EXISTING ROADS
1A 1.1 1 103.2(2) Routine maintenance of existing roads Km-Mth 6,602.00 1,245.00 8,219,490.00
1A 1.2 1.2 CONTRACTOR'S SITE ESTABLISHMENT
1A 1.2 2 108.4 (1) Provide Main Laboratory LS 4,389,496.00 1.00 4,389,496.00
1A 1.2 3 108.4 (2) Provide Furniture and Laboratory equipment for main Laboratory LS 24,208,800.00 1.00 24,208,800.00
1A 1.3 1.3 SETTING OUT, CROSS SECTION SURVEYS AND DRAWINGS
1A 1.3 4 117(1) Surveying and Setting out of Centre Line km 291,874.00 83.00 24,225,542.00
Preparation of Longitudinal sections (LS) and Cross Sections (CSs) with all
assosiated costs for Design works (pavement and Geometrical) of road works
1A 1.3 5 117(2) other than bridge and retaining wall structures including submission of as-built km 165,060.00 83.00 13,699,980.00
drawing
1 OF 35
INTEGRATED ROAD INVESTMENT PROGRAMME (iRoad 2) - WESTERN PROVINCE
RDA/ADB/IROAD-2(WP)/ICB/CL-03
COST TO COMPLETION
ITEM CONTRACT BOQ (A)
Bill No Sec. DESCRIPTION UNIT RATE
Bill Pay QUANTITY AMOUNT
2 2.1 9 201(10)b Removal of overhanging branches; Girth 600 to 1,200 mm nr 6,448.20 40.00 257,928.00
2 2.1 10 201(10)c Removal of overhanging branches; Girth over 1,200 mm nr 7,034.31 4.00 28,137.24
2 2.2 2.2 REMOVAL OF EXISTING STRUCTURES
2 2.2 11 202(1) a Dismantle & remove pipe culverts up to 900mm diameter lm 4,103.75 330.00 1,354,237.50
2 2.2 12 202(1) b Dismantle & remove pipe culverts above 900mm diameter lm 4,103.75 80.00 328,300.00
2 2.2 13 202(2) Dismantle & remove concrete structures Cu.m 4,103.75 3,930.00 16,127,737.50
2 2.2 14 202(2) a Dismantle & remove random rubble masonry structures Cu.m 3,517.64 510.00 1,793,996.40
2 2.2 15 202(2) b Dismantle & remove existing brick /block structures Cu.m 3,517.64 438.00 1,540,726.32
2 2.2 16 202(2) c Dismantle & remove dressed stone and handover to the client Cu.m 3,517.64 160.00 562,822.40
2 2.2 17 202(3)a Remove fencing and like other lm 410.66 3,790.00 1,556,401.40
2 Bill No.2 Carried to Summary 126,476,315.46
3 BILL No.3 : EARTH WORKS
3 3.1 3.1 ROADWAY EXCAVATION
3 3.1 1 301(1) Roadway excavation , soil suitable for fill Cu.m 937.97 9,000.00 8,441,730.00
3 3.1 2 301(2) Roadway excavation, soft rock Cu.m 1,172.22 238.00 278,988.36
3 3.1 3 301(8) Roadway excavation, hard rock Cu.m 5,275.97 75.00 395,697.75
3 3.1 4 301(11) Roadway excavation, unsuitable soil Cu.m 937.97 36,000.00 33,766,920.00
3 3.1 5 301(13) Road pavement excavation Cu.m 1,172.22 1,680.00 1,969,329.60
3 3.1 6 301(16) Preparation of sub grade in cut areas Sq.m 70.37 113,110.00 7,959,550.70
3 3.2 3.2 CHANNEL EXCAVATION
3 3.2 7 301A(1) Channel excavation soil suitable for fill Cu.m 1,172.22 4,000.00 4,688,880.00
3 3.2 8 301A(2) Channel excavation, soft rock Cu.m 1,406.48 865.00 1,216,605.20
3 3.2 9 301A(4) Channel excavation, hard rock Cu.m 9,379.72 100.00 937,972.00
3 3.2 10 301A(5) Channel excavation, unsuitable soil Cu.m 1,172.22 9,500.00 11,136,090.00
3 3.3 3.3 EXCAVATION AND BACKFILL OF STRUCTURES
3 3.3 11 302(1) Excavation for structures, soil suitable for backfill Cu.m 1,969.45 1,750.00 3,446,537.50
3 3.3 12 302(2) Excavation for structures, soft rock Cu.m 3,517.64 105.00 369,352.20
3 3.3 13 302(4) Excavation for structures, hard rock Cu.m 9,379.72 700.00 6,565,804.00
3 3.3 14 302(5) Excavation for structures, unsuitable soil Cu.m 2,344.45 4,000.00 9,377,800.00
3 3.3 15 302(8) Backfill with granular material Cu.m 4,317.76 860.00 3,713,273.60
3 3.4 3.4 EMBANKMENT CONSTRUCTION
3 3.4 16 304(1) a Embankment construction using material from roadway excavation, Type I Cu.m 937.97 4,750.00 4,455,357.50
3 3.4 17 304(1) b Embankment construction using material from roadway excavation, Type II Cu.m 937.97 10,000.00 9,379,700.00
3 3.4 18 304(2) a Embankment construction using borrow material, Type I Cu.m 3,776.95 17,500.00 66,096,625.00
3 3.4 19 304(2) b Embankment construction using borrow material, Type II Cu.m 2,795.60 10,000.00 27,956,000.00
3 3.4 20 304(3) Trimming, leveling and compaction of original ground Sq.m 58.81 67,880.00 3,992,022.80
3 3.4 21 304(4) providing and place geofabric Sq.m 264.14 750.00 198,105.00
3 3.4 22 304(6) Embankment construction using rockfill Cu.m 4,583.82 2,290.00 10,496,947.80
3 Bill No.3 Carried to Summary : 216,839,289.01
4 BILL No.4 : ROAD PAVEMENT
4 4.1 4.1 SUB BASES, CAPPING LAYERS AND BASES
4 4.1 1 401(1) a Sub base as compacted in position(upper Subbase) Cu.m 3,882.03 14,750.00 57,259,942.50
4 4.1 2 408(2) Scarification of existing base Sq.m 5.78 29,450.00 170,221.00
4 4.1 3 405(1) Dense graded aggregate base (Nominal size of aggregate 37.5 mm) Cu.m 5,533.36 46,500.00 257,301,240.00
4 4.2 4.2 SHOULDER CONSTRUCTION
4 4.2 4 409(1) Earthen shoulders as compacted in position Cu.m 3,927.34 27,300.00 107,216,382.00
4 4.2 5 409(2) Trench excavation in shoulders for filter drain Cu.m 937.97 50.00 46,898.50
4 4.2 6 409(3) Geotextile for filter drain Sq.m 261.24 500.00 130,620.00
4 4.2 7 409(4) Porous material for filter drain Cu.m 5,015.69 60.00 300,941.40
4 4.3 4.3 PRIME COAT AND TACK COAT
4 4.3 8 501(5) a Bituminous prime coat using MC 30 at rate of 1.0 ltr per sq.m Sq.m 251.60 294,500.00 74,096,200.00
Blotting Material applied at the rate of 1 cum
4 4.3 9 501 (5) c per 250 Sq.m. Sq.m 17.35 294,500.00 5,109,575.00
4 4.3 10 502(2) Tack coat using CRS 1 at rate of 0.25 - 0.55 ltr per sq.m Sq.m 63.62 308,000.00 19,594,960.00
4 4.4 4.4 ASPHALTIC CONCRETE SURFACING
4 4.4 11 506(1) Asphalt concrete in wearing course 50mm thick Sq.m 1,604.10 294,500.00 472,407,450.00
4 4.4 12 506(2) a Asphalt concrete regulating course Mt 13,228.97 1,750.00 23,150,697.50
4 4.5 4.5 CONCRETE PAVEMENT
4 4.5 13 1008(1) formwork rough finish Sq.m 1,406.48 166.00 233,475.68
4 4.5 14 1002(1) Tor steel Reinforcement Mt 225,109.42 5.00 1,125,547.10
4 4.5 15 901B(1) Concrete pavement (30) Cu.m 22,622.19 250.00 5,655,547.50
4 4.5 16 806A(1) Concrete block paving Sqm - -
4 Bill No. 4 Carried to Summary 1,023,799,698.18
5 BILL No.5 : DRAINAGE
5 5.1 5.1 ROAD SIDE AND LEADAWAY DRAINS
5 5.1 1 701(1) Lining of Drains with pre-cast units (d=300mm , Drawing No DS-01) lm 6,101.16 9,140.00 55,764,602.40
5 5.1 2 701(2) a Lining of drains with Concrete: Grade 15 (20) Cu.m 18,045.12 310.00 5,593,987.20
5 5.1 3 701(2) b Lining of drains with Concrete: Grade 20 (20) Cu.m 18,918.50 1,650.00 31,215,525.00
5 5.1 4 701(2) c Lining of drains with Concrete: Grade 25 (20) Cu.m 20,619.96 1,000.00 20,619,960.00
5 5.1 5 701(6) a 100 mm thick Precast concrete cover slab including reinforcement & formwork Sq.m 6,684.38 1,125.00 7,519,927.50
5 5.1 6 701(6) b 125mm thick Precast concrete cover slab including reinforcement & formwork Sq.m 8,143.87 2,200.00 17,916,514.00
5 5.1 7 701(6) c 150mm thick Precast concrete cover slab including reinforcement & formwork Sq.m 12,142.54 160.00 1,942,806.40
5 5.1 8 705(2) d Filter medium Cu.m 4,493.20 45.00 202,194.00
5 5.1 9 706(1) d Weep hole, PVC pipe (Type 600) - 75mm diameter lm 958.22 1,235.00 1,183,401.70
5 5.1 10 1002(1) Tor steel reinforcement Mt 225,109.42 90.00 20,259,847.80
5 5.1 11 1008(1) Formwork smooth finish Sq.m 1,769.90 9,500.00 16,814,050.00
5 5.1 12 1008(2) Formwork rough finish Sq.m 1,758.34 12,085.00 21,249,538.90
5 5.2 5.2 CLEANING, DESILTING AND REPAIRING OF CULVERTS
5 5.2 13 1303(1) a Clearing and repairing pipe culverts nr 35,172.50 45.00 1,582,762.50
5 5.2 14 1303(1) b Clearing and reparing other culvert types nr 41,034.59 45.00 1,846,556.55
5 Bill No. 5 Carried to Summary 203,711,673.95
6 BILL No.6 : CULVERTS,RETAINING STRUCTURES & BUS BAYS
6 6.1 6.1 CULVERTS
6 6.1 1 705(1) Aggregate backfill Cu.m 4,675.40 260.00 1,215,604.00
6 6.1 2 705(2) Filter medium Cu.m 4,506.70 65.00 292,935.50
2 OF 35
INTEGRATED ROAD INVESTMENT PROGRAMME (iRoad 2) - WESTERN PROVINCE
RDA/ADB/IROAD-2(WP)/ICB/CL-03
COST TO COMPLETION
ITEM CONTRACT BOQ (A)
Bill No Sec. DESCRIPTION UNIT RATE
Bill Pay QUANTITY AMOUNT
6 6.1 3 705(3) Impervious layer Sq.m 1,325.50 120.00 159,060.00
6 6.1 4 706(1) Weep hole, PVC pipe (Type 600) - 75mm diameter lm 961.11 450.00 432,499.50
6 6.1 5 707(3) Concrete encasement of pipes Cu.m 29,021.22 100.00 2,902,122.00
6 6.1 6 707(5) Reinforcement steel for concrete encasement Mt 225,813.14 5.00 1,129,065.70
6 6.1 7 707(6) a Reinforced concrete pipe 450mm diameter lm - -
6 6.1 8 707(6)b Reinforced concrete pipes 600mm diameter lm 12,349.80 1,800.00 22,229,640.00
6 6.1 9 707(6)c Reinforced concrete pipes 900mm diameter lm 18,946.46 130.00 2,463,039.80
6 6.1 10 707(6) d Reinforced concrete pipe 1200mm diameter lm - -
6 6.1 11 805(1) Gabions Cu.m - -
6 6.1 12 808(5) c Guard stone nr 3,671.88 650.00 2,386,722.00
6 6.1 13 1001(1) Concrete: Grade 15 Cu.m 18,101.99 1,450.00 26,247,885.50
6 6.1 14 1001(2) Concrete: Grade 20 Cu.m 18,977.30 200.00 3,795,460.00
6 6.1 15 1001(3) Concrete: Grade 25 Cu.m 20,684.55 500.00 10,342,275.00
6 6.1 16 1001(4) Concrete: Grade 30 Cu.m 21,235.96 125.00 2,654,495.00
6 6.1 17 1001(6) Concrete: Grade 40 Cu.m - -
6 6.1 18 1002(1)k Tor steel reinforcement Mt 225,813.14 75.00 16,935,985.50
6 6.1 19 1006(1) Random rubble masonry Cu.m 12,698.77 870.00 11,047,929.90
6 6.1 20 1008(1)k Formwork smooth finish Sq.m 2,363.73 3,435.00 8,119,412.55
6 6.1 21 1008(2)k Formwork rough finish Sq.m 2,352.16 4,830.00 11,360,932.80
6 6.1 22 1006(3) Plastering rough finish Sq.m 935.08 1,165.00 1,089,368.20
6 Bill No. 6 Carried to Summary : 124,804,432.95
7 BILL No.7 BRIDGES
7 7.1 7.1 BRIDGES
7 7.1 1 1006(1) Random rubble masonry Cu.m - -
7 7.1 2 705(1) Aggregate backfill Cu.m - -
7 7.1 3 705(2) Filter medium Cu.m - -
7 7.1 4 705(3) Impervious layer Sq.m - -
7 7.1 5 706(1) Weep hole, PVC pipe (Type 600) - 75mm diameter lm - -
7 7.1 6 804(1) c Rip rap protection as approved by the Engineer Cu.m - -
7 7.1 7 805(1) Gabions Cu.m - -
7 7.1 8 808(5) c Guard stone nr - -
7 7.1 9 1001(1) Concrete: Grade 15 Cu.m - -
7 7.1 10 1001(2) Concrete: Grade 20 Cu.m - -
7 7.1 11 1001(3) Concrete: Grade 25 Cu.m - -
7 7.1 12 1001(4) Concrete: Grade 30 Cu.m - -
7 7.1 13 1001(6) Concrete: Grade 40 Cu.m - -
7 7.1 14 1002(1)k Tor steel reinforcement Mt - -
7 7.1 15 1008(1)k Formwork smooth finish Sq.m - -
7 7.1 16 1008(2)k Formwork rough finish Sq.m - -
7 7.1 17 1006(3) Plastering rough finish Sq.m - -
75x12 mm hard rubber bearing pads supplied & laid over capping beam as per
7 7.1 18 1010(1) drawing lm - -
20mm dia 1800mm long cold worked high steel dowels driven into bed rock for
7 7.1 19 1011B(1) abutment and wing walls supplied fixed and grouted nr - -
Precast reinforced concrete railing & uprights in Grade 25 (20) concrete as per
7 7.1 20 1018(1) drawing No.T/B/102 A & B lm - -
End pilasters in Class A concrete of Grade 25 (20) with foundation type I as per
7 7.1 21 1019(1)a drawing No. T/B/106 Rev.1 nr - -
End pilasters in Class A concrete of Grade 25 (20) with foundation type II as per
7 7.1 22 1019(1)b drawing No. T/B/106 Rev.1 nr - -
End pilasters in Class A concrete of Grade 25 (20) with foundation type III as per
7 7.1 23 1019(1)c drawing No. T/B/106 Rev.1 nr - -
End pilasters in Class A concrete of Grade 25 (20) with foundation type IV as per
7 7.1 24 1019(1)d drawing No. T/B/106 Rev.1 nr - -
7 Bill No. 7 Carried to Summary :
8 BILL No.8 : INCIDENTAL CONSTRUCTION
8 8.1 8.1 TOP SOILING AND GRASSING
8 8.1 1 802(4) Grass sodding as approved by the Engineer Sq.m 703.72 11,900.00 8,374,268.00
Plants of suitable species not less than 2.0m in height suppllied,planted,nurtured
8 8.1 2 803(1) and maintained during contract period nr 1,758.34 1,430.00 2,514,426.20
8 8.2 8.2 RIP RAP PROTECTION FOR EMBANKMENT SLOPES
8 8.2 3 804(1) Rip rap protection as approved by the Engineer Cu.m 12,254.37 335.00 4,105,213.95
8 8.3 8.3 GUARD RAILS, GUARD WALLS, GUARD STONES
8 8.3 4 808(5) Guard stone nr 3,660.31 770.00 2,818,438.70
8 8.3 5 809(1) a Pedestrian guard fence lm 12,497.30 130.00 1,624,649.00
8 8.4 8.4 ROAD MARKINGS
8 8.4 6 810(1) a Center line : Continuous Sq.m - -
8 8.4 7 810(1) b Center line : Intermittent Sq.m - -
8 8.4 8 810(1) c Edge line : Continuous Sq.m 1,934.75 16,850.00 32,600,537.50
8 8.4 9 810(1) d Pedestrian crossing Sq.m 2,169.00 382.00 828,558.00
8 8.4 10 810(3) Reflecting road studs nr 2,169.00 330.00 715,770.00
8 8.5 8.5 TRAFFIC SIGNS
8 8.5 11 811(1) Single pole, sign area up to 0.5m2 nr 16,882.53 990.00 16,713,704.70
8 8.5 12 811(2) Double pole, sign area up to 2.0m2 nr 111,379.60 15.00 1,670,694.00
8 8.5 13 1501 (10) Repairing, painting and reinstate existing traffic signs nr - -
8 8.6 8.6 KILOMETRE POSTS AND BOUNDARY MARKERS
8 8.6 14 819(1) Provide ,install and paint new kilometre post nr 16,414.03 60.00 984,841.80
8 8.6 15 819(2) Reposition of existing killometre post nr - -
Provide, install and paint new precast right of way boundary markers
8 8.6 16 819. (5) nr 7,620.42 1,420.00 10,820,996.40
8 Bill No. 8 Carried to Summary 83,772,098.25
9 9 BILL No.9 : DAY WORK SUMMARY
9 9 1 Total Daywork: Labor 431,400.00 431,400.00
9 9 2 Total Daywork: Contractor's Equipment 1,427,500.00 1,427,500.00
9 9 3 Total Daywork: Materials 1,608,756.00 1,608,756.00
9 Bill No. 9 Dayworks Carried to Summary : 3,467,656.00
9 BILL No.9 : SCHEDULE OF DAY WORK RATES
9 9.1 9.1 : LABOR
9 9.1 1 Surveyor Hr 813.00 50.00 40,650.00
9 9.1 2 Survey Assistant (skilled) Hr 438.00 50.00 21,900.00
3 OF 35
INTEGRATED ROAD INVESTMENT PROGRAMME (iRoad 2) - WESTERN PROVINCE
RDA/ADB/IROAD-2(WP)/ICB/CL-03
COST TO COMPLETION
ITEM CONTRACT BOQ (A)
Bill No Sec. DESCRIPTION UNIT RATE
Bill Pay QUANTITY AMOUNT
9 9.1 3 Welder Hr 438.00 50.00 21,900.00
9 9.1 4 Electrician Hr 375.00 50.00 18,750.00
9 9.1 5 Carpenter Hr 438.00 50.00 21,900.00
9 9.1 6 Mason Hr 438.00 100.00 43,800.00
9 9.1 7 Labour (skilled) Hr 500.00 150.00 75,000.00
9 9.1 8 Semi-skilled workman Hr 375.00 200.00 75,000.00
9 9.1 9 Unskilled workman (labourer) Hr 375.00 300.00 112,500.00
9 Labour Day works Carried to Daywork Summary 431,400.00
9 9.2 9.2 : CONTRACTOR'S EQUIPMENT
9 9.2 1 Lorry, 3 to 5 tonnes Hr 600.00 50.00 30,000.00
9 9.2 2 Lorry, 5 to 10 tonnes Hr 800.00 50.00 40,000.00
9 9.2 3 Low-loader, 20 to 40 tonnes Hr 2,000.00 50.00 100,000.00
9 9.2 4 Site dumper, over 1.0 m3 Hr 200.00 100.00 20,000.00
9 9.2 5 Tipper truck, up to 5 tonnes Hr 1,300.00 50.00 65,000.00
9 9.2 6 Bowser, water, up to 6,000 litres with Spray Bar Hr 1,200.00 50.00 60,000.00
9 9.2 7 Farm Tractor & Broom over 2m width Hr 850.00 50.00 42,500.00
9 9.2 8 Farm tractor, with trailer minimum 3 tonne Hr 800.00 50.00 40,000.00
9 9.2 9 Backhoe, wheeled, 50 - 100 HP Hr 2,500.00 50.00 125,000.00
9 9.2 10 Backhoe, tracked, 50 - 100 HP Hr 2,600.00 50.00 130,000.00
9 9.2 11 Motor grader, up to 100 HP Hr 3,200.00 50.00 160,000.00
9 9.2 12 Steel-wheeled roller, static, 8 to 12 tonnes Hr 900.00 50.00 45,000.00
9 9.2 13 Steel-wheeled roller, vibratory, 4 to 8 tonnes Hr 2,000.00 50.00 100,000.00
9 9.2 14 Pneumatic-tyred roller, 8 to 12 tonnes Hr 3,200.00 50.00 160,000.00
9 9.2 15 Hand roller, vibratory, 1/2 - 1 tonne Hr 850.00 50.00 42,500.00
9 9.2 16 Plate compactor, vibratory, over 90 kg Hr 500.00 50.00 25,000.00
9 9.2 17 Rammer, mechanical, over 60 kg Hr 750.00 50.00 37,500.00
9 9.2 18 Air compressor with hoses and tools, 250 to 600 cfm Hr 700.00 50.00 35,000.00
9 9.2 19 Water pump with hoses, 50 to 100 mm outlet Hr 800.00 50.00 40,000.00
9 9.2 20 Concrete mixer, 0.25 to 0.50 cu.m. Hr 1,000.00 50.00 50,000.00
9 9.2 21 Generator, 10 to 50 KVA Hr 500.00 50.00 25,000.00
9 9.2 22 Welding set, electric, 300 - 400 amp Hr 650.00 50.00 32,500.00
9 9.2 23 Poker Vibrator, petrol driven Hr 450.00 50.00 22,500.00
9 Equipment Day works Carried to Daywork Summary 1,427,500.00
9 9.3 9.3 : MATERIALS
9 9.3 1 Aggregate base, dense graded (37.5 mm) Cu.m 1,960.00 50.00 98,000.00
9 9.3 2 Aggregate (20mm) Cu.m 2,474.00 50.00 123,700.00
9 9.3 3 Asphalt concrete, cold mix tonne 8,110.00 10.00 81,100.00
9 9.3 4 Bitumen emulsions, ( CRS 1, CRS 2, CSS 1) ltr 80.00 100.00 8,000.00
9 9.3 5 Bitumen prime coat, cutback MC 30 ltr 110.00 100.00 11,000.00
9 9.3 6 Bitumen, straight run, 60/70 penetration ltr 80.00 100.00 8,000.00
9 9.3 7 Bitumen, straight run, 80/100 penetration ltr 80.00 100.00 8,000.00
9 9.3 8 Block, cement, 400 x 200 x 100 mm nr 40.00 500.00 20,000.00
9 9.3 9 Brick, hand-cut nr 16.00 500.00 8,000.00
9 9.3 10 Cement, ordinary Portland tonne 18,400.00 2.50 46,000.00
9 9.3 11 Concrete pipe, reinforced 600 mm diameter lm 5,833.00 5.00 29,165.00
9 9.3 12 Concrete pipe, reinforced 900 mm diameter lm 9,016.00 5.00 45,080.00
9 9.3 13 Concrete pipe, reinforced 1200 mm diameter lm 13,525.00 5.00 67,625.00
9 9.3 14 Concrete, Grade 15 Cu.m 15,000.00 3.00 45,000.00
9 9.3 15 Concrete, Grade 20 Cu.m 16,000.00 3.00 48,000.00
9 9.3 16 Concrete, Grade 25 Cu.m 16,500.00 3.00 49,500.00
9 9.3 17 Concrete, Grade 30 Cu.m 17,000.00 3.00 51,000.00
9 9.3 18 Formwork, timber (smooth) Sq.m 1,100.00 50.00 55,000.00
9 9.3 19 Pipe, PVC, 160 mm diameter (Type 600) lm 2,000.00 50.00 100,000.00
9 9.3 20 Reinforcement, high-yield steel, Grade 460/425 kg 140.00 100.00 14,000.00
9 9.3 21 Reinforcement, mild steel, Grade 250 kg 140.00 100.00 14,000.00
9 9.3 22 Rubble, 100 - 150 mm Cu.m 1,767.00 50.00 88,350.00
9 9.3 23 Rubble, 150 - 225 mm Cu.m 1,696.00 50.00 84,800.00
9 9.3 24 River Sand Cu.m 6,360.00 10.00 63,600.00
9 9.3 25 Timber, Class 2, Sri Lanka Timber Corporation Cu.m 2.00 5.00 10.00
9 9.3 26 Precast concrete paving slabs 450x450x50 mm Nos 266.00 200.00 53,200.00
9 9.3 27 Paint, emulsion ltr 400.00 100.00 40,000.00
9 9.3 28 Paint, enamel ltr 450.00 100.00 45,000.00
9 9.3 29 Auto diesel ltr 120.00 100.00 12,000.00
9 9.3 30 Petrol ltr 150.00 100.00 15,000.00
9 9.3 31 kerosene Oil ltr 85.00 100.00 8,500.00
Carry out survey works for bridges, design and prepare working drawings for
11 11 3 117(4) bridges and all other structures and works, where specified, as described in PS 1,000,000.00 1,000,000.00
Employer’s requirements
11 11 4 123(1) Payment to Dispute Board (only for Employer's portion) PS 1,000,000.00 1,000,000.00
11 11 5 103(2) Temporary by-passes for culverts, bridges and other structures PS 3,500,000.00 3,500,000.00
4 OF 35
INTEGRATED ROAD INVESTMENT PROGRAMME (iRoad 2) - WESTERN PROVINCE
RDA/ADB/IROAD-2(WP)/ICB/CL-03
COST TO COMPLETION
ITEM CONTRACT BOQ (A)
Bill No Sec. DESCRIPTION UNIT RATE
Bill Pay QUANTITY AMOUNT
11 11 6 103.2(1) Initial maintenance of existing road PS 4,000,000.00 4,000,000.00
11 11 7 112.1(1) Repairs to damages of existing services PS 165,000.00 165,000.00
11 11 8 112.1(2) Demolition / Rebuilding of property PS 4,000,000.00 4,000,000.00
Allow for the construction of house Accesses (Improving / Modifing existing
11 11 9 112.1(3) accesses) PS 100,000.00 100,000.00
11 11 10 112.1(4) Diversion, protection or removal of electrical services PS 3,500,000.00 3,500,000.00
11 11 11 112.1(5) Diversion, protection or removal of water services PS 4,500,000.00 4,500,000.00
11 11 12 112.1(6) Diversion, protection or removal of telecommunication services PS 1,000,000.00 1,000,000.00
11 11 13 703(1) Grade adjustment of existing manholes PS 1,000,000.00 1,000,000.00
11 11 14 Conducting Public Stakeholders Awareness & Social Safeguard ralated activities PS 1,500,000.00 1,500,000.00
11 11 15 To attend Emergency works during Performanse Based Maintenanse Period PS 10,000,000.00 10,000,000.00
11 1116 Repairs to damages of existing Bridges PS 4,000,000.00 4,000,000.00
11 Bill No. 11 Carried to Summary 39,765,000.00
12 12 BILL No.12 : PHYSICAL CONTINGENCIES
12.1 12.1 NON ADJUSTABLE VARIATIONS
VO-01 VEHICLES FOR THE ENGINEER
Vehicle
1.1 Supply and maintain Vehicle Type 2 - (PJ -1603) month 320,213.00
Vehicle
1.2 Supply and maintain Vehicle Type 2 - (PJ -1602) month 315,888.00
Hard roack excavation using non explosive chemical agent (Chemical blasting) -
New3.2 Structure excavation areas cu.m 46,749.00
New4 Remove and replacing 600mm dia. Existing hume pipe nr 4,663.00
5 OF 35
Road Development Authority New Rate
Second Integrated Road Investment Program
Contract Package : RDA/ADB/iROAD-2(WP)/ICB/CL-03
Rate Analysis
BILL NO - 4.4.11 Assumed Qty, (sqm)= 325.00
Bill Item Asphalt concrete in wearing course 50mm thick Mark-up = 27.00%
00+000
REHABILITATION/ IMPROVEMENT AND MAINTENANCE OF 84.33 KM RURAL ROADS IN COLOMBO DISTRICT IN THE WESTERN PROVINCE - PACKAGE 3
Material 0.00 Cu.m of Concrete 0.00 Cube of Soil 7.20 Cube of ABC 0.00 Mt 0.00 Mt of Asphalt
REHABILITATION/ IMPROVEMENT AND MAINTENANCE OF 84.33 KM RURAL ROADS IN COLOMBO DISTRICT IN THE WESTERN PROVINCE - PACKAGE 3
RDA/ADB/iROAD-2(WP)/ICB/CL-03
SUMMARY SHEET
SUMMARY SHEET
###
###
###
###
###
Prepaired By Submitted By
P.G.G.C.N.Gangewaththa K.S.D.S.Senanayake
REHABILITATION/ IMPROVEMENT AND MAINTENANCE OF 84.33 KM RURAL ROADS IN COLOMBO DISTRICT IN THE
WESTERN PROVINCE - PACKAGE 3
RDA/ADB/iROAD-2(WP)/ICB/CL-03
4.3 -
PRIME COAT AND TACK COAT ###
Blotting Material applied at the rate of 1 cum
9 501 (5) c Sq.m 54.00 17.35 936.90
per 250 Sq.m.
Bill No.4 Carried to Summary 87,285.67
VARIATIONS - ADJUSTABLE
VO-05 - Priming using CSS-1 bitumen Sq.m 54.00 194.00 10,476.00
Variations - Adjustable Carried to Summary 10,476.00
###
Prepaired By Submitted By
REHABILITATION/ IMPROVEMENT AND MAINTENANCE OF 84.33 KM RURAL ROADS IN COLOMBO DISTRICT IN THE
WESTERN PROVINCE - PACKAGE 3
RDA/ADB/iROAD-2(WP)/ICB/CL-03
P.G.G.C.N.Gangewaththa K.S.D.S.Senanayake
Quantity Surveyor Project Manager
ESTIMATE FOR "WCO-211 Insurance Claim"
###
0+323-0+333 LHS Embankment wash away & Replacing drain units (Annexture-01)
###
ITEM
DESCRIPTION UNIT QUANTITY RATE AMOUNT (Rs)
Bill Pay
3.1 - ROADWAY EXCAVATION ###
1 301(1) Roadway excavation , soil suitable for fill Cu.m 1.80 937.97 1,688.35
3.4 - EMBANKMENT CONSTRUCTION ###
Embankment construction using borrow material,
18 304(2) a Cu.m 3.19 3,776.95 12,048.47
Type I
4.2 - SHOULDER CONSTRUCTION ###
4 409(1) Earthen shoulders as compacted in position Cu.m 3.60 3,927.34 14,138.42
9.1 : LABOR ###
7 Labour (skilled) Hr 8.00 500.00 4,000.00
9 Unskilled workman (labourer) Hr 8.00 375.00 3,000.00
9.2 : CONTRACTOR'S EQUIPMENT ###
2 Lorry, 5 to 10 tonnes Hr 5.00 800.00 4,000.00
9 Backhoe, wheeled, 50 - 100 HP Hr 4.00 2,500.00 10,000.00
Total Amount (Rs) 48,875.24
###
###
###
###
REHABILITATION/ IMPROVEMENT AND MAINTENANCE OF 84.33 KM RURAL ROADS IN COLOMBO DISTRICT IN THE
WESTERN PROVINCE - PACKAGE 3
RDA/ADB/iROAD-2(WP)/ICB/CL-03
Prepaired By Submitted By
P.G.G.C.N.Gangewaththa K.S.D.S.Senanayake
Quantity Surveyor Project Manager
REHABILITATION/ IMPROVEMENT AND MAINTENANCE OF 84.33 KM RURAL ROADS IN COLOMBO DISTRICT IN THE WESTERN PROVINCE -
PACKAGE 3
COST ESTIMATION FOR EMPLOYER'S WORK PROPOSAL
DESCRIPTION CONTRACTOR'S
EMPLOYER'S ESTIMATED
ESTIMATED COST -
COST -INCLUDING PRICE
ROAD No. INCLUDING PRICE REMARKS
ESCALATION (87%
CHAINAGE SIDE PROPOSED WORKS ESCALATION (87%
+5%-June'23) (SLRS)
+5%-June'23) (SLRS)
TOTAL ESTIMATED COST Including (84%) + (5%)of Price Escalation) 84,449,314.68 #REF! LKR
REHABILITATION/ IMPROVEMENT AND MAINTENANCE OF 84.33 KM RURAL ROADS IN COLOMBO DISTRICT IN THE
WESTERN PROVINCE - PACKAGE 3
COST ESTIMATION
BOQ Item : VO-16
Provide Furniture and Laboratory equipment for main Laboratory ( Critical works period)
CALCULATION SHEET
t
en
)
(C
m
Break up %
) i re
No Description Remark
d
Provided %
de
(A)
( B e qu
vi
(A/BxC)
o
R
Pr
Provide furniture and laboratory equipment for main
laboratory
B Furnishing and Equipment
Office desks 120x7cm and each having at least 3 drawers,
1 0.477% 4 4 0.477%
one of which is lockable
2 Computer desks 0.102% 2 2 0.102%
3 Typist chairs, gas lift height adjustment, arm rests 0.230% 6 6 0.230%
4 Bench Stools 0.062% 6 - 0.000%
5 Steel filing cabinets with four drawers 0.266% 2 2 0.266%
Book shelves 1m x 2m with 3 shelves and lockable
6 0.152% 1 1 0.152%
cupboard at base
7 Storage cabinets 1mx2m, two doors, lockable 0.121% 1 1 0.121%
8 Laboratory benches sufficient for all testing equipment 0.059% 1 1 0.059%
9 Laboratory sinks with cold tap(minimum) 0.293% 2 2 0.293%
10 Bulletin board 0.9x0.6m 0.020% 1 - 0.000%
11 White marker board 1.2mx0.8m 0.020% 1 1 0.020%
COST ESTIMATION
BOQ Item : VO-16
Provide Furniture and Laboratory equipment for main Laboratory ( Critical works period)
CALCULATION SHEET
t
en
)
(C
m
Break up %
) i re
No Description Remark
d
Provided %
de
(A)
( B e qu
vi
(A/BxC)
o
R
Pr
Total B/F from Previous Page 4.466% 4.314%
D General Laboratory Equipment
Geographic Positioning system (500 way points / icon,
GLE1 automatic track log in both directions, trip computer, 0.258% 1 0 0.000%
reversible routes, 12 parallel channel GPS receiver)
GLE2 Rubber mallet (100mm Dia.) 0.020% 5 5 0.020%
Scoops (cast Aluminum), 80*130*50mm (round and flat 04
GLE3 0.760% 5 Sets 5 Sets 0.760%
Nos. each)
Measuring flasks (Glass) & Measuring Cylinders (Plastic) 0.899% 8 Sets 2 Sets 0.225%
Measuring flasks (Glass)
• 2 Nos 100ml, 16 4
• 2 Nos 250ml, 16 4
GLE4 • 2 Nos 500ml, 16 4
• 2 Nos 1000ml 16 4
Measuring Cylinders (Plastic)
• 3 Nos 250ml, (Graduation 1ml), 24 6
• 3 Nos 500ml,Graduation 5ml), 24 6
• 3 Nos 1000ml, (Graduation 10ml) 24 6
GLE5 Digital Vernier Caliper 150mm 0.264% 1 1 0.264%
GLE6 Steel ruler 300mm 0.004% 3 3 0.004%
Sample Splitter 6mm, Nos. of slots 12 with three pans and
GLE7 0.185% 1 1 0.185%
one flat scoop (88812 of 1989, part 102)
Sample splitter 13mm, Nos. of slots 12 with three pans and
GLE8 0.185% 1 1 0.185%
one flat scoop (88812 of 1989, part 102)
Sample splitter 50mm,Nos. of slots 08 with three pans and
GLE9 0.413% 2 2 0.413%
one flat scoop (BS 812 of 1989, part 102)
GLE10 Galvanized steel trays 24*40cm 0.100% 12 12 0.100%
Electric forced draught oven-capacity 125 liters, 1500w,
GLE11 1.113% 1 1 1.113%
230v, 50 Hz. 1-ph (with thermometer)
Electronic Field scale balance capacity -35kg accuracy
GLE12 0.334% 2 2 0.334%
1gm (Rechargeable battery include)
Electronic balance of 5000gm capacity accurate to 0.1gm
GLE13 with a tare correction of not less than 100gm 0.381% 2 1 0.191%
(Rechargeable battery include)
Electronic balance of 1500gm capacity accurate to 0.01gm
GLE14 0.381% 2 1 0.191%
230 v, AC, 50 Hz, 1-ph (Rechargeable battery include)
GLE15 Flexible spatula 100mm 0.322% 10 10 0.322%
GLE16 Glass plate - 400*600*6mm 0.057% 4 4 0.057%
GLE17 Sets crowbars, pick axe and spade 0.117% 2 1 0.059%
Total C/F to Next Page 10.259% 8.737%
COST ESTIMATION
BOQ Item : VO-16
Provide Furniture and Laboratory equipment for main Laboratory ( Critical works period)
CALCULATION SHEET
t
en
)
(C
m
Break up %
) i re
No Description Remark
d
Provided %
de
(A)
( B e qu
vi
(A/BxC)
o
R
Pr
Total B/F from Previous Page 10.259% 8.737%
175mm diameter porcelain bowl together with a rubber
GLE18 0.076% 2 1 0.038%
head pestle
Mixing bowl-dia. 225mm, height 1OOmm wall thickness
GLE19 0.014% 2 1 0.007%
not less than 0.75mm stainless steel
Digital Hotplate 300*600mm ,not less than 2.5Kw 30°C
GLE20 1.113% 2 1 0.557%
-300°C, 230V,AC, 50Hz,1-ph
GLE21 Heat resistant gloves, 300mm,men's size with gauntlets 0.035% 2 2 0.035%
GLE22 Neoprene gloves, 300mm , men's size 0.014% 2 2 0.014%
GLE23 Rubber gloves, 300mm men's size 0.007% 2 2 0.007%
Metal Thermometer 0-250°C (in metal casing) 60cm in
GLE24 0.120% 3 3 0.120%
length
Metal Thermometer 0-250°C 50mm diameter dial and
GLE25 stainless steel stem of approx . 200mm lenqth and 5mm 0.149% 3 3 0.149%
diameter
Digital Thermometer 0-250°C liquid crystal display,
GLE26 0.501% 3 3 0.501%
complete with penetration probe , battery and case
GLE27 Glass thermometer 0-110°C 0.029% 2 2 0.029%
GLE28 Glass thermometer 0-25ooc 0.029% 2 2 0.029%
GLE29 Bulk density measure 30 litre capacity 0.180% 1 1 0.180%
GLE30 Bulk density measure 07 litre capacity 0.116% 1 1 0.116%
GLE31 Sand Absorption cone and tamping rod 0.073% 1 1 0.073%
Camber measuring boards, 3.0m fitted with spirit levels
GLE32 0.820% 2 1 0.410%
and adjusters
Straight edge 3m long use to measure irregularities of
GLE33 0.762% 2 1 0.381%
road pavement with graduated two wedges
Steel Crucible tongs of bow type, made of steel&
GLE34 0.076% 2 1 0.038%
having aoorox.225mm lenqth
GLE35 Brass wire brush ( for cleaning of coarse sieve) 0.038% 2 2 0.038%
GLE36 Soft hair sieve brush 9 (for cleaning of fine sieves) 0.029% 2 2 0.029%
Sample tray, 610*610*63mm shall be made of heavy duty
GLE37 0.281% As req. 10 0.281%
galvanized steel plate
Sample tray 254*254*38mm shall be made of heavy duty
GLE38 0.205% As req. 10 0.205%
galvanized steel plate
Refrigerator Freezer for non flammable material, temp
GLE39 0.586% 1 1 0.586%
range - 5°C-15°C power supply 230V AC, 50hz
GLE40 Desiccator, 250ml 0.568% 2 1 0.284%
Total C/F to Next Page 16.080% 12.844%
COST ESTIMATION
BOQ Item : VO-16
Provide Furniture and Laboratory equipment for main Laboratory ( Critical works period)
CALCULATION SHEET
t
en
)
(C
m
Break up %
) i re
No Description Remark
d
Provided %
de
(A)
( B e qu
vi
(A/BxC)
o
R
Pr
Total B/F from Previous Page 16.080% 12.844%
E Soil testing equipment
California bearing test equipment (Complying with BS
1377 of 1990 part 04) or AASHTO T193-99
• Multi speed compression tester 50kN capacity
19.165% 2 Sets 1 Sets 9.583%
testing speed adjustable from 0 .1 to 51mm/Min, 230V, 50-
60 Hz , 1ph for CBR test, with accessories,
COST ESTIMATION
BOQ Item : VO-16
Provide Furniture and Laboratory equipment for main Laboratory ( Critical works period)
CALCULATION SHEET
t
en
)
(C
m
Break up %
) i re
No Description Remark
d
Provided %
de
(A)
( B e qu
vi
(A/BxC)
o
R
Pr
COST ESTIMATION
BOQ Item : VO-16
Provide Furniture and Laboratory equipment for main Laboratory ( Critical works period)
CALCULATION SHEET
t
en
)
(C
m
Break up %
) i re
No Description Remark
d
Provided %
de
(A)
( B e qu
vi
(A/BxC)
o
R
Pr
Total B/F from Previous Page 38.644% 23.277%
Standard Compaction Test Set (complying with BS 1377) 0.424% 2 Sets 1 Sets 0.212%
• Standard compaction rammer 2 1
STE3 • Standard compaction moulds + collar + base 2 1
• One set of Parts Catalogue & Operation and Service
2 1
Manual shall be provided
Field Density test equipment BS1377-1990 part 9 (for fine
1.112% 2 Sets 2 Sets 1.112%
and medium grained soil)
• Sand pouring cylinder, internal diameter,150mm 2 2
• Metal dibber tool for excavating hole 2 2
• Pointed steel rod about 250mm long and 1Omm in
2 2
diameter and having a wooden handle
• Scraper for leveling ground 2 2
• Calibrating container to match with the above pouring
2 2
cylinder
STE4 • Field density plate or metal tray square shape ,
50mmdeep ,with a central hole exactly match with the above 2 2
pouring cylinder
• Density sampling spoon 2 2
• Rubber headed mallet 2 4
• Club hammer 2 2
• Density chisel 2 2
• 2" paint brush 2 4
• One set of Parts Catalogue & Operation and Service
Manual shall be provided
Washing sieve 200*200mm, brass or stainless steel wire
cloth,
Aperture size 0.075mm
• Diameter : 200mm
STE5 • Height : 200mm 0.088% 2 Sets 2 Sets 0.088%
Complying with BS 410
One set of Parts Catalogue & Operation and Service Manual
shall be provided
Atterberg limit test equipment complying with BS 1377-
1.178% 2 Sets 1 Sets 0.589%
1990 part 02 or ASTM D 423 re-approved 1972
• Liquid limit device(hand operated type) 2 1
• Palette knives 100mm long, 30mm wide 2 1
• Casagrande grooving tool 2 1
• ASTM Grooving Tool 2 1
STE6 • Gauge made of brass / stainless steel 2 1
• Evaporating dish (Diameter 150mm) 2 1
• 500mm square glass plate (thickness 10mm) 2 1
• Wash bottle (plastic) 2 1
• Stainless steel rod 3mm diameter and 100mm long 2 1
• Mortar and rubber headed pestle 2 1
• One set of Parts Catalogue & Operation and Service
Manual shall be provided
Total C/F to Next Page 41.446% 25.278%
COST ESTIMATION
BOQ Item : VO-16
Provide Furniture and Laboratory equipment for main Laboratory ( Critical works period)
CALCULATION SHEET
t
en
)
(C
m
Break up %
) i re
No Description Remark
d
Provided %
de
(A)
( B e qu
vi
(A/BxC)
o
R
Pr
COST ESTIMATION
BOQ Item : VO-16
Provide Furniture and Laboratory equipment for main Laboratory ( Critical works period)
CALCULATION SHEET
t
en
)
(C
m
Break up %
) i re
No Description Remark
d
Provided %
de
(A)
( B e qu
vi
(A/BxC)
o
R
Pr
Total progress B/F from Previous Page 41.446% 25.278%
Dynamic Cone Penetrometer (DCP} equipment 3.323% 2 Sets 1 Sets 1.662%
COST ESTIMATION
BOQ Item : VO-16
Provide Furniture and Laboratory equipment for main Laboratory ( Critical works period)
CALCULATION SHEET
t
en
)
(C
m
Break up %
) i re
No Description Remark
d
Provided %
de
(A)
( B e qu
vi
(A/BxC)
o
R
Pr
COST ESTIMATION
BOQ Item : VO-16
Provide Furniture and Laboratory equipment for main Laboratory ( Critical works period)
CALCULATION SHEET
t
en
)
(C
m
Break up %
) i re
No Description Remark
d
Provided %
de
(A)
( B e qu
vi
(A/BxC)
o
R
Pr
Total B/F from Previous Page 53.70% 31.217%
Steel cube moulds 150*150*150 mm (BS 1881 part
CTE2 0.615% 20 20 0.615%
108:1983)
Slump cones and associated equipment (Slump cone, Base
CTE3 0.220% 3 3 0.220%
plate, Tamping rod) BS 1881 part-102
CTE4 Curing tank for test cubes (3m x 1.5m x 1m) 1.440% 1 1 1.440%
CTE5 Flakiness index gauge 0.127% 3 1 0.042%
E Bitumen Testing Equipment
COST ESTIMATION
BOQ Item : VO-16
Provide Furniture and Laboratory equipment for main Laboratory ( Critical works period)
CALCULATION SHEET
t
en
)
(C
m
Break up %
) i re
No Description Remark
d
Provided %
de
(A)
( B e qu
vi
(A/BxC)
o
R
Pr
COST ESTIMATION
BOQ Item : VO-16
Provide Furniture and Laboratory equipment for main Laboratory ( Critical works period)
CALCULATION SHEET
t
en
)
(C
m
Break up %
) i re
No Description Remark
d
Provided %
de
(A)
( B e qu
vi
(A/BxC)
o
R
Pr
Total B/F from Previous Page 59.386% 35.537%
Solubility of Asphalt materials ASTM D 2042-1993 0.636% 1 0.5 0.318%
• Erlenmeyerflasks (125ml) 1 0.5
• Filter flasks 1 0.5
• Beaker burner 1 0.5
• Beakers (100ml) 1 0.5
BTE4 • Filter pump 1 0.5
• Rubber tubing 1 0.5
• Trichloroethylene 1 0.5
• Gooch crucibles with glass fibre filter 1 0.5
One set of Parts Catalogue & Operation and Service Manual
shall be provided
Flash and Fire point Test eguipment (Cleveland open cup
1.729% 1 0.5 0.865%
apparatus conforming to ASTM D 92-1996) including
BTE5 • Test cup, heating plate and heater, shield and 1 0.5
• Thermometer conforming to ASTME1, 11C 1 0.5
One set of Parts Catalogue & Operation and Service Manual
shall be provided
BTE6 Ductility apparatus 3.011% 1 0.0 0.000%
BTE7 Rotating Oven -Temo 10°-200°c (30x30x30 cm3 2.487% 1 0.5 1.244%
F Asphalt Concrete Testing Equipment
Marshall Test Equipment (complying with ASTMD 1559-
1989) It shall be used for Marshall test on asphalt concrete 10.417% 1 1 10.417%
including
• 06 No's of moulds and accessories 6 6
• Specimen extractor 1 1
• Compaction hammer (electrically operated) 1 1
• Compaction pedestal 1 1
• Compaction mould holder 1 1
• Breaking head 1 1
• Testing machine and proving ring 1 1
• Flow meter with break 1 1
• Mixing apparatus 1 1
• Containers for heating bitumen 1 -
ACTE1 • Metal thermometer 1 1
• Electrically heated water bath 1 1
• Thermometers for water bath 1 1
• Scoop and spoon all conforming to ASTM D1559 -89 1 1
COST ESTIMATION
BOQ Item : VO-16
Provide Furniture and Laboratory equipment for main Laboratory ( Critical works period)
CALCULATION SHEET
t
en
)
(C
m
Break up %
) i re
No Description Remark
d
Provided %
de
(A)
( B e qu
vi
(A/BxC)
o
R
Pr
COST ESTIMATION
BOQ Item : VO-16
Provide Furniture and Laboratory equipment for main Laboratory ( Critical works period)
CALCULATION SHEET
t
en
)
(C
m
Break up %
) i re
No Description Remark
d
Provided %
de
(A)
( B e qu
vi
(A/BxC)
o
R
Pr
Total B/F to Previous Page 77.666% 48.381%
Extraction Test 3.754% 1 1 3.754%
• Centrifuge extractor complying with ASTM D 2172- 1995,
Capacity : 1,500 gms, Voltage : 220 - 240 v, 50-60 1 1
ACTE2 Hz, 1Ph, 550 w Speed Control up to 3600 r.p.m
• Filter disks 5 packs with 100 pieces in each pack. 5 5
One set of Parts Catalogue & Operation and Service Manual
shall be provided
Petrol Driven Core Cutting Machine
A petrol driven core cutting machine 3hp, 2 stroke engine, 9.533% 2 2 9.533%
supplied complete with water swivel including,
• 100mm diameter core bits (03 Nos) 3 3
ACTE3 • 150mm diameter core bits 3 3
• 03 Nos. Core sample extruder 2 2
Note: The core bits shall be well fitted to the core cutting
machine. One set of Parts Catalogue & Operation and
Service Manual shall be provided
Specific Gravity Test Equipment (Bituminous Mix) 1.406% 1.00 1.00 1.406%
It shall be used in determining the theoretical maximum
specific gravity and density of bituminous paving mixtures
complying with ASTM testing standard 02041-90
• TypeE-4500ml metal vacuum pyknometer with lid clear
(poly methyl metacrylate lid)
• Vacuum pump capable of evacuating air from the vacuum
container to a residual pressure of 30mm of Hg
ACTE4 • Residual pressure manometer to be connected directly to
the vacuum vessel and capable of measuring residual
pressure down to 30mm of Hg
• Manometer or vacuum gauge suitable for measuring the
vacuum being applied at the source of the vacuum .
• Balance, with ample capacity and shall be equipped with a
suitable suspension apparatus and holder to permit weighing
the sample while suspended from the center.
One set of Parts Catalogue & Operation and Service
Manual shall be provided
G Aggregate Testing Equipment
Aggregate Impact Value (AIV) Test Equipment Complying
0.692% 1 Sets 0.5 Sets 0.346%
with BS 812 of 1990
This equipment shall include the following
• Test machine 01 1 0.5
ATE1 • Cylindrical steel cup 01 1 0.5
• Cylindrical metal measure 01 1 0.5
• Straight metal tamping rod 16mm dia, 600mm long 1 0.5
One set of Parts Catalogue & Operation and Service Manual
shall be provided
Total C/F to Next Page 93.051% 63.420%
COST ESTIMATION
BOQ Item : VO-16
Provide Furniture and Laboratory equipment for main Laboratory ( Critical works period)
CALCULATION SHEET
t
en
)
(C
m
Break up %
) i re
No Description Remark
d
Provided %
de
(A)
( B e qu
vi
(A/BxC)
o
R
Pr
COST ESTIMATION
BOQ Item : VO-16
Provide Furniture and Laboratory equipment for main Laboratory ( Critical works period)
CALCULATION SHEET
t
en
)
(C
m
Break up %
) i re
No Description Remark
d
Provided %
de
(A)
( B e qu
vi
(A/BxC)
o
R
Pr
Total B/F from Previous Page 93.051% 63.420%
Flakiness Index gauge (complying with BS 812 of 1990)
Specific gravity and absorption of aggregate BS 812 Part 02 1.082% 1 Sets 1 Sets 1.082%
of 1990. It shall be used in determining specific gravity
if aggregate, including
COST ESTIMATION
BOQ Item : VO-16
Provide Furniture and Laboratory equipment for main Laboratory ( Critical works period)
CALCULATION SHEET
t
en
)
(C
m
Break up %
) i re
No Description Remark
d
Provided %
de
(A)
( B e qu
vi
(A/BxC)
o
R
Pr
Total B/F from Previous Page 98.042% 67.928%
• Density sampling spoon large size. 2 2
• Rubber headed mallet 2 2
• Club Hammer 2 2
ATE7 • Density chisel 2 2
• 2" paint brush 2 2
One set of Parts Catalogue & Operation and Service Manual
shall be provided
Aggregate crushing value test apparatus inclusive of
measuring mould and tamping rod Complying with BS 812
ATE8 0.399% 1 Sets 0.5 Sets 0.200%
part 110 One set of parts catalogue And oparation manual
shall be provided
COST ESTIMATION
BOQ Item : VO-16
Provide Furniture and Laboratory equipment for main Laboratory ( Critical works period)
CALCULATION SHEET
t
en
)
(C
m
Break up %
) i re
No Description Remark
d
Provided %
de
(A)
( B e qu
vi
(A/BxC)
o
R
Pr
CHAINAGE -
Omitted by the Employer at site inspection as no any critcal
PROPOSED WORK -
condition at site
WORK REFERANCE No -
ITEM Estimated BOQ
Description Pay Unit Remarks
Bill Pay Qty Rate(SLRS) Amount (SLRS)
4.4.11 506(1) Asphalt concrete in wearing course 50mm thick Sq.m - 1,604.10 -