ML-PRD01-ENG-CRPT-0026_PIPING FLEXIBILITY ANALYSIS REPORT FOR LP TWO PHASE PIPELINE FROM WELLPAD ML-H TO SEPARATOR STATION SS1_Rev B
ML-PRD01-ENG-CRPT-0026_PIPING FLEXIBILITY ANALYSIS REPORT FOR LP TWO PHASE PIPELINE FROM WELLPAD ML-H TO SEPARATOR STATION SS1_Rev B
ML-PRD01-ENG-CRPT-0026_PIPING FLEXIBILITY ANALYSIS REPORT FOR LP TWO PHASE PIPELINE FROM WELLPAD ML-H TO SEPARATOR STATION SS1_Rev B
Page 2 of 12
Consortium of Sumitomo Corporation and PT REKAYASA INDUSTRI
PIPING FLEXIBILITY ANALYSIS REPORT FOR LP TWO PHASE PIPELINE FROM
WELLPAD ML-H TO SEPARATOR STATION SS1
Document No : Origin Rev No. Contract No :
TABLE OF CONTENTS
1. INTRODUCTION.....................................................................................................................................5
2. SYSTEM DESCRIPTION........................................................................................................................5
2.2 Notes...................................................................................................................................................5
4. DESIGN CRITERIA.................................................................................................................................6
5. DESCRIPTION OF ANALYSIS.............................................................................................................7
6. MODELLING ASSUMPTION................................................................................................................9
6.3 Mitre..................................................................................................................................................10
7. RESULTS.................................................................................................................................................12
7.2 Support..............................................................................................................................................13
8. CONCLUSION........................................................................................................................................14
Page 3 of 12
Consortium of Sumitomo Corporation and PT REKAYASA INDUSTRI
PIPING FLEXIBILITY ANALYSIS REPORT FOR LP TWO PHASE PIPELINE FROM
WELLPAD ML-H TO SEPARATOR STATION SS1
Document No : Origin Rev No. Contract No :
1. INTRODUCTION
Page 4 of 12
Consortium of Sumitomo Corporation and PT REKAYASA INDUSTRI
PIPING FLEXIBILITY ANALYSIS REPORT FOR LP TWO PHASE PIPELINE FROM
WELLPAD ML-H TO SEPARATOR STATION SS1
Document No : Origin Rev No. Contract No :
This report covers the pipeline flexibility analysis for the LP two phase pipeline from Wellpad ML-H to
Separator Station SS1 of Muara Laboh Geothermal Power Project – EPC Contract for Stage 1
Development at South Solok, West Sumatera, Indonesia.
2. SYSTEM DESCRIPTION
Data and design condition method used in the analysis are described below
SCH Cond
- 250 10S G25A 65 10 - - ensate 1000 - -
2.2 Notes:
1. The stress model has been made in global coordinates are as follows:
Z
X = North Direction
Y
Y = West Direction
Z = Vertical Direction X
2. Hydrostatic testing is not required, so that there is no HYD Load Case in CAESAR II
(Pipeline will be 100% RT and service test)
Page 5 of 12
Consortium of Sumitomo Corporation and PT REKAYASA INDUSTRI
PIPING FLEXIBILITY ANALYSIS REPORT FOR LP TWO PHASE PIPELINE FROM
WELLPAD ML-H TO SEPARATOR STATION SS1
Document No : Origin Rev No. Contract No :
4. DESIGN CRITERIA
The piping flexibility analysis result shall fulfill the following criteria:
1. The stresses of piping system in the analysis shall be within the allowable of ASME B31.3.
2. The actual stress load for this system consist of sustain, occasional & expansion as shown in result
attachment-3.
3. Support type and location to be determined under flexibility analysis calculation, identified in
isostress drawings, and to be informed to Piping Designer.
5. Component data such as gate valve, flange & blind flange used Pipe Data Pro Software, unless
there is a general arrangement or data sheet as a weight references.
5. DESCRIPTION OF ANALYSIS
Page 6 of 12
Consortium of Sumitomo Corporation and PT REKAYASA INDUSTRI
PIPING FLEXIBILITY ANALYSIS REPORT FOR LP TWO PHASE PIPELINE FROM
WELLPAD ML-H TO SEPARATOR STATION SS1
Document No : Origin Rev No. Contract No :
Wind speed and prevailing wind direction as per document Design Specification for
Civil and Structural, No. ML-PRD01-ENG-CSPC-0001
6. MODELLING ASSUMPTION
Rigid model consist of flanges, valves, bolt,nut, instrument equipments such as control valves,
flow elements, pressure relief valves & wellhead model. All rigid model are taken from Pipe
data pro V8.05 as shown in attachment-9, unless there is a general arrangement or data sheet as
a weight references.
Page 7 of 12
Consortium of Sumitomo Corporation and PT REKAYASA INDUSTRI
PIPING FLEXIBILITY ANALYSIS REPORT FOR LP TWO PHASE PIPELINE FROM
WELLPAD ML-H TO SEPARATOR STATION SS1
Document No : Origin Rev No. Contract No :
Page 8 of 12
Consortium of Sumitomo Corporation and PT REKAYASA INDUSTRI
PIPING FLEXIBILITY ANALYSIS REPORT FOR LP TWO PHASE PIPELINE FROM
WELLPAD ML-H TO SEPARATOR STATION SS1
Document No : Origin Rev No. Contract No :
Where:
OPE : Operating Condition
P1 : Design Pressure
T1 : Design Temperature
T2 : Operating Temperature
T3 : Minimum Temperature
Page 9 of 12
Consortium of Sumitomo Corporation and PT REKAYASA INDUSTRI
PIPING FLEXIBILITY ANALYSIS REPORT FOR LP TWO PHASE PIPELINE FROM
WELLPAD ML-H TO SEPARATOR STATION SS1
Document No : Origin Rev No. Contract No :
7. RESULTS
The calculated stresses in sustain, occasional & thermal expansion cases are acceptable based
on ASME B31.1 as shown in attachment-3.
Page 10 of 12
Consortium of Sumitomo Corporation and PT REKAYASA INDUSTRI
PIPING FLEXIBILITY ANALYSIS REPORT FOR LP TWO PHASE PIPELINE FROM
WELLPAD ML-H TO SEPARATOR STATION SS1
Document No : Origin Rev No. Contract No :
CALCULATED
ALLOWABLE STRESS RATIO
NODE LOAD CASE STRESS REMARK
(Mpa) (%)
(Mpa)
2070 (37)OCC: L37=L25+L16 36.1 141.5 25.5 PASSED
1570 (38)OCC: L38=L26+L16 38.8 141.5 27.4 PASSED
1570 (39)OCC: L39=L27+L16 38.5 141.5 27.2 PASSED
1570 (40)OCC: L40=L28+L16 38.4 141.5 27.2 PASSED
1008 (41)EXP: L41=L1-L16 222.4 268.2 82.9 PASSED
1008 (42)EXP: L42=L2-L16 191.5 268.2 71.4 PASSED
2130 (43)EXP: L43=L3-L16 10.5 271.6 3.9 PASSED
1009 (44)EXP: L44=L41-L42 33.0 271.3 12.2 PASSED
1008 (45)EXP: L45=L41-L43 229.6 268.2 85.6 PASSED
1008 (46)EXP: L46=L42-L43 198.8 268.2 74.1 PASSED
7.2 Support
The support load as attached in attachment-4 for live design temperature (EXP Case), sustain &
occasional cases has been informed to Civil Engineer for steel structure and foundation design.
Load for occasional seismic will be calculated by Civil Engineer.
The type and location of support in Wellpad H to LP Separator are shown in isometric stress
drawings in attachment-7.
8. CONCLUSION
1. Based on flexibility analysis, the stresses for Wellpad H to separator low pressure are within the
allowable of ASME B31.1 as shown in attachment 3.
2. Support type and support location as shown in the allignment sheets have been determined under
flexibility analysis. Loading data and support type has been informed to Civil Engineer and Piping
Designer for support design.
3. The pipe support on the drawing ML-M-SG-S06-0004-01 from pipe support PS-S06-01001
(Wellpad ML-H To Separator Station SS1 Plan & Long Section Sheet 1) to anchor at PS-S06-
01005A (Wellpad ML-H To Separator Station SS1 Plan & Long Section Sheet 1) is covered by
document number ML-PRD01-ENG-CRPT-0017 (Flexibility analysis report for LP Production
Wellpad ML-H1). PS-S06-01006 is an interface between low pressure two phase pipeline with
wellpad ML-H. Combination of loading data attached on attachment-10.
Page 11 of 12
Consortium of Sumitomo Corporation and PT REKAYASA INDUSTRI
PIPING FLEXIBILITY ANALYSIS REPORT FOR LP TWO PHASE PIPELINE FROM
WELLPAD ML-H TO SEPARATOR STATION SS1
Document No : Origin Rev No. Contract No :
4. The pipe support on the drawing ML-M-SG-SPA-0001-02 (Production wellpad ML-A piping
arrangement lay out sheet 2) PS-SPA-02006 is an interface between low pressure two phase pipeline
with wellpad ML-A. Combination of loading data attached on attachment-10.
5. The pipe support on the drawing ML-M-SG-SPA-0001-02 (Production wellpad ML-A piping
arrangement lay out sheet 2) PS-SPA-02027 is an interface between low pressure two phase pipeline
with separator (FUJI portion). Combination of loading data attached on attachment-10.
Page 12 of 12