Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 52

BOQ RUANG PERAWATAN PUSKESMAS RASANAE TIMUR LT.

1
No URAIAN PEKERJAAN PERHITUNGAN VOLUME VOLUME
1. Pek. Pengukuran, Pematokan, dan Pemasangan Bauplank = 118.00 M
Arah Horisontal = 15.00 + 3.00 + 4.00 + 16.50 + 1.50 + 11.00 + 3.00 + 15.00 = 69.00 M
Arah Vertikal = 3.00 + 10.00 + 3.00 + 6.00 + 6.00 + 2.00 + 6.00 + 13.00 = 49.00 M
### M

2. Pek. Galian Tanah FootPlate Menggunakan Alat Berat = 39.01 M3


Footplate Bangunan = Pjg X Lbr X Tgg X Jml Foot= 1.20 X 1.20 X 1.55 X 16 Bh = 35.71 M3
Footplate Ramp = = 1.00 X 1.00 X 1.10 X 3 Bh = 3.30 M3
39.01 M3

3. Pek. Galian Tanah Menggunakan Tenaga Manusia = 61.80 M3


Galian Pondasi = Vol. Galian Pondasi Pas. Batu - Vol. Galian Kolom Padestal
= (Pjg Total X Lbr X Tgg) - (Pjg X Lbr X Tgg X Jml Klm)
= ### X 0.50 X 0.75) - (0.50 X 0.50 X 0.75 X 16.00) = 46.05 M3
Galian Saluran Keliling = Pjg Total Sal. X Lbr X Tgg = 63.00 X 0.50 X 0.50 = 15.75 M3
61.80 M3

4. Urugan Kembali Tanah Hasil Gali = 25.20 M3


= 0.25 X ### = 25.20 M3

5. Urugan Tanah Pilihan Peninggian Lantai = 87.60 M3


Ket. :Dihitung Langsung pada Gbr Sketchup R. Perawatan 1 = 10.69 M3 Lorong = 17.45 M3 Teras = 2.39 M3
R. Perawatan 2 = 10.69 M3 R. Perawat = 2.55 M3 R. Perawatan 1 = 0.93 M3
R. Dokter = 4.56 M3 R. Dibawah Ramp = 19.48 M3 R. Perawatan 2 = 0.93 M3
R. Tindakan + Gudang Alat = 10.17 M3 R. Pelayanan = 6.98 M3/WC R. Perawat = 0.78 M3
87.60 M3
6. Pek. Urugan Pasir dibawah Pondasi dan Lantai = 15.82 M3
Urugan Dibawah Footplate Bangunan = 1.20 X 1.20 X 0.05 X 16 Bh = 1.15 M3
Urugan Dibawah Footplate Ramp = 1.00 X 1.00 X 0.05 X 3.00 = 0.15 M3
Urugan Dibawah Pondasi Pas. Batu = ### X 0.50 X 0.05 = 3.27 M3
Urugan Dibawah Rabbat Keliling = 47.16 X 0.05 = 2.36 M3
Urugan Dibawah Lantai
R. Perawatan 1 = 3.82 X 5.80 X 0.05 = 1.11 M3
R. Perawatan 2 = 3.82 X 5.80 X 0.05 = 1.11 M3
R. Dokter = 2.66 X 3.82 X 0.05 = 0.51 M3
R. Tindakan + Gudang Alat = 3.80 X 5.62 X 0.05 = 1.07 M3
Lorong = 2.80 X 12.92 X 0.05 = 1.81 M3
R. Perawat = 1.33 X 2.80 X 0.05 + 1.32 X 1.36 X 0.05 = 0.28 M3
R. Dibawah Ramp = 5.30 X 3.80 X 0.05 + 5.30 X 3.60 X 0.05 = 1.96 M3
R. Pelayanan = 3.80 X 3.80 X 0.05 = 0.72 M3
Teras = = - M3
KM/WC R. Perawatan 1 = 1.33 X 1.82 X 0.05 = 0.12 M3
KM/WC R. Perawatan 2 = 1.33 X 1.82 X 0.05 = 0.12 M3
KM/WC R. Perawat = 1.32 X 1.35 X 0.05 = 0.09 M3
15.82 M3

7. Pek. Pasangan Batu Kosong = 13.08 M3


= Pjg Pondasi X Lbr X Tbl Pas. Batu Ko = ### X 0.50 X 0.20 = 13.08 M3

8. Pek. Pondasi Pas. Batu = 26.74 M3


Pondasi Pas. Batu 1
Arah Horisontal = (5.00 + 5.00 + 3.50) X 4 Brs X 0.40 X 0.50 = 10.80 M3
Arah Vertikal = (3.50 + 2.50 + 5.50) X 4 Brs X 0.40 X 0.50 = 9.20 M3
Pondasi Pas. Batu 2
Arah Horisontal = (2.70 + 3.70 + 3.70 + 3.24) X 0.40 X 0.50 = 2.67 M3
Arah Vertikal = (11.40 + 2.70 + 3.30 + 2.94) X 0.40 X 0.50 = 4.07 M3
26.74 M3
9. Pek. Pasangan Dinding 1/2 bata camp. 1pc:5ps = 513.17 M2
Arah Horisontal = (5.00 + 5.00 + 3.50) X 3 Brs X 3.98 = ### M2
= (5.00 + 5.00) X 3.98 = 39.80 M2
= (1.19 + 1.32 + 1.19) X 3.98 = 14.73 M2
= (2.87 + 3.87 + 1.18) X 3.98 = 31.52 M2
Arah Vertikal
= (3.50 + 2.50 + 5.50) X 2 Brs X 3.98 - 91.54 M2
= (5.87 X 5.87 + 5.87 + 1.68 + 2.87 + 1.18) X 3.98 = 92.89 M2
Pada Saluran = 63.00 X 0.50 X 2 Sisi = - M2
Pada Ramp = 18.00 X 1.00 = 18.00 M2
Pembungkus Kolom Baja = 1.70 X 4.00 X 16.00 = ### M2

Pengurangan Luas Pas. Bata


Pintu Masuk Utama P1 = 2.28 X 4.30 X 1 Unit = (9.80) M2
Pintu P2 = 1.70 X 2.15 X 1 Unit = (3.66) M2
Pintu P3 = 1.40 X 2.15 X 3 Unit = (9.03) M2
Pintu P4 = 1.00 X 2.05 X 3 Unit = (6.15) M2
Pintu P5 = 1.00 X 1.90 X 2 Unit = (3.80) M2
Pintu P6 = 0.80 X 1.90 X 1 Unit = (1.52) M2
Jendela J1 = 1.90 X 1.80 X 0 Unit = - M2
Jendela J2 = 1.05 X 1.50 X 6 Unit = (9.45) M2
Ventilasi V1 = 0.60 X 0.35 X 9 Unit = (1.89) M2
Ventilasi V2 = 1.00 X 0.40 X 0 Unit = - M2
### M2

Plasteran = Pas. Bata X 2 Sisi = ### X 2 Sisi = ### M2 = ### M2


Acian = Plasteran = ### M2 = ### M2
Pengecatan Tembok Baru = Plasteran = ### M2 = ### M2

10. Pek. Rabbat Keliling Bangunan = - M3


= Luas X Tbl = 47.16 X 0.05 = 2.36 M3

11. Pek. Rabbat dibawah Lantai = 8.89 M3


= Vol. Urugan Pasir dibawah L= 8.89 M3
=
12. Pek. Rabbat dibawah Footplate = 2.60 M3
Urugan Dibawah Footplate Bangunan = 1.20 X 1.20 X 0.10 X 16.00 = 2.30 M3
Urugan Dibawah Footplate Ramp = 1.00 X 1.00 X 0.10 X 3.00 = 0.30 M3
2.60 M3
13. Pek. Beton Pondasi Footplate = 11.56 M3
Footplate Bangunan
Footplate = {(Pjg X Lbr X Tb)+(Pjg Rata2 X Lbr Rta2 X Tbl)} X Jml Footplate
= {0.29 + (0.85 X 0.85 X 0.05)} X 16 Bh = 5.19 M3
Kolom Padestal = 0.50 X 0.50 X 1.30 X 16 Bh = 5.20 M3
Footplate Ramp
Footplate = {(Pjg X Lbr X Tb)+(Pjg Rata2 X Lbr Rta2 X Tbl)} X Jml Footplate
= {0.20 + (0.68 X 0.68 X 0.10)} X 3 Bh = 0.74 M3
Kolom Padestal = 0.35 X 0.35 X 1.20 X 3 Bh = 0.44 M3
11.56 M3

14. Pek. Bakesting Pondasi Footplate = 64.40 M2


Footplate Bangunan
Footplate = Lebar Sisi X Tbl = 4.80 X 0.20 X 16 Bh = 15.36 M2
Kolom Padestal = Lebar Sisi X Tgg X 2.00 X 1.30 X 16 Bh = 41.60 M2
Footplate Ramp
Footplate = Lebar Sisi X Tbl X J 4.00 X 0.20 X 3 Bh = 2.40 M2
Kolom Padestal = Lebar Sisi X Tgg X 1.40 X 1.20 X 3 Bh = 5.04 M2
64.40 M2

15. Pek. Pembesian Footplate = 1,292.47 Kg


Footplate Bangunan
Footplate
Tul. Lentur Arah X Dia 12.00 = Pjg Tul. X Jml Tulangan X Jml Pond X BJ 12 Pjg Tul = 1.62 Jml = 8 Bh
= 1.62 X 8.00 X 16 Bh X 0.89 = 183.94 Kg = 183.94 Kg
Tul. Lentur Arah Y Dia 12.00 = Pjg Tul. X Jml Tulangan X Jml Pond X BJ 12 Pjg Tul = 1.62 Jml = 8 Bh
= 1.62 X 8.00 X 16 Bh X 0.89 = 183.94 Kg = 183.94 Kg
Tul. Susut Arah X Dia 12.00 = Pjg Tul. X Jml Tulangan X Jml Pond X BJ 12 Pjg Tul = 1.56 Jml = 8.00 Bh
= 1.56 X 8.00 X 16 Bh X 0.89 = 177.12 Kg = 177.12 Kg
Tul. Susut Arah Y Dia 12.00 = Pjg Tul. X Jml Tulangan X Jml Pond X BJ 12 Pjg Tul = 1.56 Jml = 8.00 Bh
= 1.56 X 8.00 X 16 Bh X 0.89 = 177.12 Kg = 177.12 Kg
Kolom Padestal =
Dia 16.00 = Pjg Total Tul X Jml Tul. X Jml Footpl = 2.17 X 4.00 X 16.00 X 1.58 = 219.01 Kg
Dia 14.00 = Pjg Total Tul X Jml Tul. X BJ D14 = 2.17 X 4.00 X 16.00 X 1.21 = 167.68 Kg
Tul. Sengk. Dia 6.00 = Pjg 1 Seng. X Jml Sengk. X BJ D 6 = 1.87 X 15 X 0.22 = 6.23 Kg

Footplate Ramp
Footplate
Tul. Lentur Arah X Dia 12.00 = Pjg Tul. X Jml Tulangan X Jml Pond X BJ 12 Pjg Tul = 1.52 Jml = 7 Bh
= 1.52 X 7.00 X 3 Bh X 0.89 = 28.31 Kg = 28.31 Kg
Tul. Lentur Arah Y Dia 12.00 = Pjg Tul. X Jml Tulangan X Jml Pond X BJ 12 Pjg Tul = 1.52 Jml = 7 Bh
= 1.52 X 7.00 X 3 Bh X 0.89 = 28.31 Kg = 28.31 Kg
Tul. Susut Arah X Dia 12.00 = Pjg Tul. X Jml Tulangan X Jml Pond X BJ 12 Pjg Tul = 1.36 Jml = 7 Bh
= 1.36 X 7.00 X 3 Bh X 0.89 = 25.33 Kg = 25.33 Kg
Tul. Susut Arah Y Dia 12.00 = Pjg Tul. X Jml Tulangan X Jml Pond X BJ 12 Pjg Tul = 1.36 Jml = 7 Bh
= 1.36 X 7.00 X 3 Bh X 0.89 = 25.33 Kg = 25.33 Kg
Kolom Padestal =
Dia 16.00 = Pjg Total Tul X Jml Tul. X Jml Footpl = 1.77 X 4.00 X 3.00 X 1.58 = 33.49 Kg
Dia 14.00 = Pjg Total Tul X Jml Tul. X Jml Footpl = 1.77 X 4.00 X 3.00 X 1.21 = 25.64 Kg
Tul. Sengk. Dia 6.00 = Pjg 1 Seng. X Jml Sengk. X Jml Footp = 1.27 X 13 X 3.00 X 0.22 = 11.00 Kg
### Kg

16. Pek. Beton Sloof = 12.13 M3


Sloof S1 Pjg Total Sloof X Lbr X Tgg
Arah Horisontal = (5.00 + 5.00 + 3.50) X 4 Brs X 0.45 X 0.25 = 6.08 M3
Arah Vertikal = (3.50 + 2.50 + 5.50) X 4 Brs X 0.45 X 0.25 = 5.18 M3
Sloof S2
Arah Horisontal = (2.70 + 3.70 + 3.70 + 3.24) X 0.20 X 0.13 = 0.35 M3
Arah Vertikal = (11.40 + 2.70 + 3.30 + 2.94) X 0.20 X 0.13 = 0.53 M3
12.13 M3

17. Pek. Bakesting Sloof = 103.47 M2


= Pjg X (lbr + Tgg)
Sloof S1
Arah Horisontal = (5.00 + 5.00 + 3.50) X 4 Brs X (0.45 + 0.45) = 48.60 M2
Arah Vertikal = (3.50 + 2.50 + 5.50) X 4 Brs X (0.45 + 0.45) = 41.40 M2
Sloof S2
Arah Horisontal = (2.70 + 3.70 + 3.70 + 3.24) X (0.20 + 0.20) = 5.34 M2
Arah Vertikal = (11.40 + 2.70 + 3.30 + 2.94) X (0.20 + 0.20) = 8.14 M2
### M2
Plasteran = 55.80 X 0.45 X 1 Sisi = 25.11 M2
Acian = Pjg Sloof Sisi Luar X Tgg X = 55.80 X 0.45 X 1 Sisi = 25.11 M2
Pengecatan Tembok Baru = = 25.11 M2

18. Pek. Pembesian Sloof = 1,037.50 Kg


Tulangan Pokok = Pjg Besi X Jml Besi X Bj Besi
Tul. Sengkang = Jml Sengk. X Pjg 1 Sengk. X Bj Besi
Sloof S1
Tulangan Pokok Dia 12 = ### X 8 Bh X 0.89 = ### Kg
Tul. Sengkang Dia 6 = ### X 1.24 X 0.22 = ### Kg
Sloof S1
Tulangan Pokok Dia 12 = 33.68 X 4 Bh X 0.89 = ### Kg
Tul. Sengkang Dia 6 = ### X 0.50 X 0.22 = 24.95 Kg
= ### Kg
19. Pek. Beton Kolom = 1.11 M3
Kolom Ramp = Pjg X Lbr X Tgg Total
= 0.35 X 0.35 X 7.83 = 0.96 M3
Kolom Pintu Tempered = 0.18 X 0.20 X 4.10 = 0.15 M3
1.11 M3

20. Pek. Bakesting Kolom = 14.08 M2


= (2XPjg + 2Xlbr )X Tgg Total
Kolom Ramp = (0.70 + 0.70) X 7.83 = 10.96 M2
Kolom Pintu Tempered = (0.36 + 0.40) X 4.10 = 3.12 M2
14.08 M2

Plasteran = 14.08 M2 = 14.08 M2


Acian = 14.08 M2 = 14.08 M2
Pengecatan Tembok Baru = 14.08 M2 = 14.08 M2

21. Pek. Pembesian Kolom = 102.59 Kg


Kolom Ramp
Tulangan Pokok Dia 14 = Pjg 1 Tul. X Jml Tul. X Bj. = 7.83 X 4 Bh X 1.21 = 37.81 Kg
Dia 12 = Pjg 1 Tul. X Jml Tul. X Bj. = 7.83 X 4 Bh X 0.89 = 27.78 Kg
Tul. Sengkang Dia 6 = Pjg 1 Sengk. X Jml Sengk. X= 1.24 X 52.00 X 0.22 = 14.30 Kg
Kolom Pintu Tempered
Tulangan Pokok Dia 12 = Pjg 1 Tul. X Jml Tul. X Bj. = 4.10 X 4 Bh X 0.89 = 14.55 Kg
Dia 10 = Pjg 1 Tul. X Jml Tul. X Bj. = 4.10 X 0 Bh X 0.62 = - Kg
Tul. Sengkang Dia 6 = Pjg 1 Sengk. X Jml Sengk. X= 1.36 X 27.00 X 0.22 = 8.14 Kg
= ### Kg

22. Pek. Beton K.125 Pembungkus Kolom Baja = - M3


= Pjg X Lbr X Tgg X Jml Kolom
= 0.48 X 0.22 X 4.00 X 16 Bh = 6.76 M3

23. Pek. Kolom Praktis = 118.43 M


= Tgg Kolom X Jml Kolom = 3.67 X 29.00 + 2.00 = ### M
Klm Pd Rmp = = 1.00 X 10 Bh = 10.00 M
### M
24. Pek. Beton Balok = 1.61 M3
= Lbr X Tgg X Pjg Total
Balok Ramp Pjg Tot= 8.62 + 9.00 = 17.62 M
Balok Diatas Pintu Tempered Pjg Tot= 2.00 = 2.00 M
Balok Plat Pjg Tot= 1.5+3+1.5+3 = - M

Balok Ramp = 0.25 X 0.35 X 17.62 = 1.54 M3


Balok Diatas Kusen = 0.18 X 0.20 X 2.00 = 0.07 M3
Balok Plat = 0.13 X 0.17 X - = - M3
1.61 M3

25. Pek. Bakesting Balok = 17.90 M2


Balok Ramp = (Lbr + 2xTgg )X Pjg Total = (0.25 + 0.70) X 17.62 = 16.74 M2
Balok Diatas Kusen = (Lbr + 2xTgg )X Pjg Total = (0.18 + 0.40) X 2.00 = 1.16 M2
Balok Plat = (Lbr + 2xTgg )X Pjg Total = (0.13 + 0.34) X - = - M2
17.90 M2

Plasteran = 17.90 M2 = 17.90 M2


Acian = 17.90 M2 = 17.90 M2
Pengecatan Tembok Baru = 17.90 M2 = 17.90 M2

26. Pek. Pembesian Balok = 286.03 Kg


Balok Ramp
Tulangan Pokok Dia 16 = Pjg 1 Tul. X Jml Tul. X Bj. = 17.62 X 6 Bh X 1.58 = ### Kg
Dia 12 = Pjg 1 Tul. X Jml Tul. X Bj. = 17.62 X 4 Bh X 0.89 = 62.52 Kg
Tul. Sengkang Dia 8 = Pjg 1 Sengk. X Jml Sengk. X= 1.04 X ### X 0.39 = 47.97 Kg
Balok Diatas Kusen
Tulangan Pokok Dia 12 = Pjg 1 Tul. X Jml Tul. X Bj. = 2.00 X 4 Bh X 0.89 = 7.10 Kg
Dia 10 = Pjg 1 Tul. X Jml Tul. X Bj. = 2.00 X 0 Bh X 0.62 = - Kg
Tul. Sengkang Dia 6 = Pjg 1 Sengk. X Jml Sengk. X= 0.60 X 13.00 X 0.22 = 1.73 Kg
Balok Plat
Tulangan Pokok Dia 12 = Pjg 1 Tul. X Jml Tul. X Bj. = - X 4 Bh X 0.89 = - Kg
Dia 10 = Pjg 1 Tul. X Jml Tul. X Bj. = - X 2 Bh X 0.62 = - Kg
Tul. Sengkang Dia 6 = Pjg 1 Sengk. X Jml Sengk. X= 0.44 X - X 0.22 = - Kg
### Kg

27. Pek. Beton Ringbalk = - M

28. Pek. Balok Late = 54.63 M


Balok Diatas Kusen Pjg Tot= 5.15+2.26+1.78+1.4+1.87+1.87+1.87+1.87 = 18.07 M
Balok Plat Pjg Tot= 8.9+14.7+6.41+1.4+5.15 = 36.56 M
29. Pek. Beton Plat 10cm = 0.88 M3
Plat Diatas Kusen Pjg Pla = 8.9+14.7+6.41+1.4+5.15 = 36.56 M
= Pjg Plat X Lbr X Tbl = 36.56 X 0.30 X 0.08 = 0.88 M3
Plat Samping Kusen = Lbr Rata2 X Tgg X Tbl X J = 0.20 X 4.00 X 0.08 X 0 Bh = - M3
= 0.88 M3

30. Pek. Bakesting Plat 10cm = 10.24 M2


Plat Diatas Kusen = Pjg X Lbr Rata2 + Pjg X Tbl = 36.56 X 0.20 + 36.56 X 0.08 = 10.24 M2 = 10.2368 M2
Plat Samping Kusen = (Lbr Rata2 X Tgg X 2 Sisi + Tbl X Tgg= 0.20 X 4.00 X 2 Sisi + 0.08 X 4.00 X 0 Bh = - M2
10.24 M2

Plasteran = 10.24 M2 = 10.24 M2


Acian = 10.24 M2 = 10.24 M2
Pengecatan Tembok Baru = 10.24 M2 = 10.24 M2

31. Pek. Pembesian Plat 10cm = 112.65 Kg


Plat Diatas Kusen =
Arah X Dia 10 = Pjg Tul. X Jml Tul. X BJ. Tu= 0.30 X 244 Bh X 0.616 = 45.09 Kg
Arah Y Dia 10 = Pjg Tul. X Jml Tul. X BJ. Tu= 36.56 X 3 Bh X 0.616 = 67.56 Kg
Plat Samping Kusen =
Arah Horisontal Dia 10 = Pg Rata2 Tul. X Jml Tul X Bj. Tul. X = 0.40 X 27.00 X 0.616 X 0 Bh = - Kg
Arah Vertikal Dia 10 = Pjg Tul. X Jml Tul. X BJ. Tul X Jml T = 4.00 X 2.00 X 0.616 X 0 Bh = - Kg
### Kg

32. Pek. Beton Plat 12 cm Pada Plat Ramp & Bordes = 5.11 M3
Plat Ramp = Pjg Plat X Lbr Plat X Tbl Pl = 18.25 X 1.925 X 0.12 = 4.22 M3
Plat Bordes = Pjg Plat X Lbr Plat X Tbl Pl = 3.85 X 1.940 X 0.12 = 0.90 M3
5.11 M3

33. Pek. Bakesting Plat 12 cm Pada Plat Ramp & Bordes = 45.25 M2
Plat Ramp = Pjg Plat X Lbr Plat + Pjg Plat X Tbl Pla= 18.25 X 1.93 + 18.25 X 0.12 = 37.32 M2
Plat Bordes = Pjg Plat X Lbr Plat + Pjg Plat X Tbl Pla= 3.85 X 1.94 + 3.85 X 0.12 = 7.93 M2
45.25 M2

Plasteran = Pjg Plat X Lbr Pl = 18.25 X 1.93 + 3.85 X ### = 42.60 M2 = 42.60 M2
Acian = 42.60 M2 = 42.60 M2
Pengecatan Tembok Baru = 42.60 M2 = 42.60 M2

34. Pek. Pembesian Plat 12 cm Pada Plat Ramp & Bordes = 673.44 Kg
Plat Ramp = Pjg Tul X Jml Tul. X Bj Tul.
Tulangan Lentur Arah Memanjang Dia 10 = 18.25 X 12.00 X 0.616 = ### Kg
Tulangan Lentur Arah Melintang Dia 10 = 1.93 X ### X 0.616 = ### Kg
Tulangan Susut Arah Memanjang Dia 10 = 18.25 X 12.00 X 0.616 = ### Kg
Tulangan Susut Arah Melintang Dia 10 = 1.93 X ### X 0.616 = ### Kg
Plat Bordes = Pjg Tul X Jml Tul. X Bj Tul.
Tulangan Lentur Arah Memanjang Dia 10 = 3.85 X 12.00 X 0.616 = 28.46 Kg
Tulangan Lentur Arah Melintang Dia 10 = 1.94 X 25.00 X 0.616 = 29.88 Kg
Tulangan Susut Arah Memanjang Dia 10 = 3.85 X 12.00 X 0.616 = 28.46 Kg
Tulangan Susut Arah Melintang Dia 10 = 1.94 X 25.00 X 0.616 = 29.88 Kg
### Kg
35. Pek. Plat Lantai Bondek Tebal 12cm = 18.11 M3
Luas = Luas Bangunan - Luas Void Rampp - L=
= (Pjg X Lbr Bangunan ) - (Pjg X Lbr Void Ramp) - (Luas Permukaan Klm Baja X Jml Klm Baja)
Dimana Luas Permukaan Kl = 0.125*0.009*2+0.25*0.006* = ### M2

= 15.00 X 13.00 - 11.00 X 4.00 - 0.00 X 16 Bh = ### M2


Volume Plat Lantai = Luas X Tbl Plat = ### X 0.12 = 18.11 M3

36. Pek. Keramik Lantai 50x50cm = 180.21 M2

R. Perawatan 1 = 3.87 X 5.87 = 22.72 M2


R. Perawatan 2 = 3.87 X 5.87 = 22.72 M2
R. Dokter = 2.87 X 3.87 = 11.11 M2
R. Tindakan + Gudang Alat = 3.87 X 3.37 + 3.87 X 2.37 = 22.21 M2
Lorong = 2.87 X 13.37 + 1.37 X 2.87
= + 1.50 X 1.37 = 44.36 M2
R. Dibawah Ramp = 11.00 X 3.87 = 42.57 M2
R. Pelayanan = 3.87 X 3.87 = 14.98 M2
Teras = - - - = - M2
Pengurangan Sudut Klm = 0.50 X 0.18 X 0.18 X 28 Bh = (0.45) M2
### M2

37. Pas. Plint/list keramik ukuran 10cmx 60cm = - M2

38. Pas. Lantai Keramik Motif KM/WC = 7.00 M2


= Pjg X Lbr
KM/WC R. Perawatan 1 = 1.37 X 1.87 = 2.56 M2
KM/WC R. Perawatan 2 = 1.37 X 1.87 = 2.56 M2
KM/WC R. Perawat = 1.37 X 1.37 = 1.88 M2
7.00 M2

39. Pas. Keramik Dinding ukuran 20x60cm (termasuk pada KM/WC) = 69.88 M2
KM/WC R. Perawatan 1 = 2.59 X 1.25 + 3.54 X 1.25 - 1.00 X 1.25 = 6.41 M2
KM/WC R. Perawatan 2 = 2.59 X 1.25 + 3.54 X 1.25 - 1.00 X 1.25 = 6.41 M2
KM/WC R. Perawat = 2.65 X 1.25 + 2.62 X 1.25 - 0.90 X 1.25 = 5.46 M2
R. Perawatan 1 = 11.54 X 1.25 + 7.64 X 1.25 - 1.00 X 1.25 - 1.40 X 1.25 -
1.05 X 0.70 X 4 Bh = 18.03 M2
R. Perawatan 2 = 11.54 X 1.25 + 7.64 X 1.25 - 1.00 X 1.25 - 1.40 X 1.25 -
1.05 X 0.70 X 2 Bh = 19.51 M2
R. Tindakan = 7.58 X 1.25 + 6.26 X 1.25 - 1.70 X 1.25 - 0.90 X 1.25 = 14.05 M2
69.88 M2
Pengurangan
Plasteran = - M2 = - M2
Acian = ### M2 = (69.88) M2
Pengecatan Tembok Baru = ### M2 = (69.88) M2

40. Pas. Dinding Batu Tempel Motif = - M2

41. Pas. Keramik Dinding Artistik motif Batu Alam = - M2

42. Plesteran dinding Camp. 1Pc;3Ps, Tebal 15mm = - M2


Total = - M2
43. Plesteran dinding dan Beton Camp. 1Pc;5Ps, Tebal 15mm = 1,136.27 M2
Total Plasteran = ### M2
44. Acian PC. pada Dinding dan Beton = 1,066.39 M2
Total Acian = ### M2

45. Pasang Kusen Pintu dan Jendela Alumunium = 97.80 M


= Lbr X 1 Bh + Tgg X 2 Bh X Jml
Pintu Masuk Utama P1 = 2.28 X 1 Bh + 4.30 X 2 Bh X 0 Unit = - M
Pintu P2 = 1.70 X 1 Bh + 2.10 X 2 Bh X 1 Unit = 5.90 M
Pintu P3 = 1.40 X 1 Bh + 2.10 X 2 Bh X 3 Unit = 16.80 M
Pintu P4 = 1.00 X 1 Bh + 2.00 X 2 Bh X 3 Unit = 15.00 M
Pintu P5 = 1.00 X 1 Bh + 1.85 X 2 Bh X 2 Unit = 9.40 M
Pintu P6 = 0.80 X 1 Bh + 1.85 X 2 Bh X 1 Unit = 4.50 M
Jendela J1 = 1.90 X 2 Bh + 1.75 X 2 Bh X 0 Unit = - M
Jendela J2 = 1.05 X 2 Bh + 1.45 X 2 Bh X 6 Unit = 30.00 M
Ventilasi V1 = 0.60 X 2 Bh + 0.30 X 2 Bh X 9 Unit = 16.20 M
Ventilasi V2 = 1.00 X 2 Bh + 0.35 X 2 Bh X 0 Unit = - M
97.80 M

46. Pek. Kusen Kayu Kalas I = - M2

47. Pasang Daun Pintu Kaca Bening T= 8mm Rangka Alumunium = - M2

48. Pek. Pintu Double Kaca Tempret T= 12mm Lengkap dengan Handle dan Expanolet serta Kelengkapannya = 3.20 M2
= Pjg X Lbr
= 1.60 X 2.00 = 3.20 M2
49. Pek. Partisi Kaca Tempret T= 12mm
50. Pek. daun pintu panel kayu klas I = = 13.86 M2
Pintu P3 = 1.30 X 2.10 X 3 Unit = 8.19 M2
Pintu P4 = 0.90 X 2.10 X 3 Unit = 5.67 M2
13.86 M2
51. Pek. Daun pintu plywood 4mm rangkap Lapis HPL , rangka kayu klas I tertutup (KM/WC) = 4.63 M2
Pintu P5 = 0.90 X 1.85 X 2 Unit = 3.33 M2
Pintu P6 = 0.70 X 1.85 X 1 Unit = 1.30 M2
4.63 M2
52. Pek. Daun pintu plywood 6mm rangkap Lapis HPL , rangka kayu klas I tertutup (lebar sampai 90cm) = 3.36 M2
Pintu P2 = 1.60 X 2.10 X 1.00 = 3.36 M2
53. Pek. Jendela dan Fentilasi Casement Kaca Bening T=5mmRangka Alumunium(Lengkap dgn Asesoris) = 10.12 M2
Jendela J2 = 1.35 X 1.25 X 6 Unit = 10.12 M2

54. Pek. Daun Jendela Sliding Kaca Bening T=5mmRangka Alumunium(Lengkap dgn Asesoris) = - M2
55. Pek. Kaca Bening T= 5mm(Jendela Kaca Mati) = 2.25 M2
Jendela J2 = 1.25 X 0.30 X 6.00 = 2.25 M2
56. Pek. Kaca Bening T= 8 mm(Jendela Kaca Mati) = - M2
Jendela J1 = 1.50 X 0.88 X 2 Bh X 0 Unit = - M2
57. Pengadaan dan Pemasangan Stiker Sanblast = 0.96 M2
Pintu Masuk Utama P1 = 1.60 X 0.60 = 0.96 M2
58. Pengadaan dan Pemasangan Stiker One Way = 12.37 M2
Jendela J1 = - M2
Jendela J2 = 10.12 + 2.25 = 12.37 M2
12.37 M2
59. Pek. Grendel Pintu Tanam Pada Pintu Dobel = 4.00 Bh
Pintu P2 = 1.00 X 1.00 = 1.00 Bh
Pintu P3 = 1.00 X 3.00 = 3.00 Bh
4.00 Bh
60. Pek. Grendel Jendela = 12.00 Bh
Jendela J2 = 2 Bh X 6 Unit = 12.00 Bh
61. Pek. Haag Angin = 6.00 Bh
Jendela J2 = 1 Bh X 6.00 = 6.00 Bh
62. Pek. Pengadaan dan Pemasangan Kunci Pintu Kwalitas I 2 Slaag = 6.00 Bh
Pintu P2 = - X 1 Unit = - Bh
Pintu P3 = - X 3 Unit = - Bh
Pintu P4 = 1.00 X 3 Unit = 3.00 Bh
Pintu P5 = 1.00 X 2 Unit = 2.00 Bh
Pintu P6 = 1.00 X 1 Unit = 1.00 Bh
6.00 Bh
63. Pek. Engsel Pintu Mutu Baik (Doors Hinge) setara Deksson = 18.00 Bh
Pintu P2 = 2.00 X 1 Unit = - Bh
Pintu P3 = 2.00 X 3 Unit = 6.00 Bh
Pintu P4 = 2.00 X 3 Unit = 6.00 Bh
Pintu P5 = 2.00 X 2 Unit = 4.00 Bh
Pintu P6 = 2.00 X 1 Unit = 2.00 Bh
18.00 Bh
64. Pek. Engsel Jendela Mutu Baik (windows Hinge) = 12.00 Bh
Jendela J2 = 2 Bh X 6 Unit = 12.00 Bh
65. Pasang Kunci Silinder Pintu mutu baik pada Pintu Dobel = 4.00 Bh
Pintu P2 = 1.00 X 1.00 = 1.00 Bh
Pintu P3 = 1.00 X 3.00 = 3.00 Bh
4.00 Bh
66. Pengadaan Handel Pintu Panjang Minal 60cm = 4.00 Bh
Pintu P2 = 4.00 X 1.00 = 4.00 Bh
67. Pek. Rangka Atap Baja Ringan Profil "C", ukuran 75 x 35 x 0.75 mm dan Reng ukuran 0,45/16/31/11mm = - M2
Didapat Langsung dari Luas Pd GBr Sketchup = M2
68. Pek. Atap Zincalume (Spandek) T.0,40mm = - M2
= Pek. Rangka Atap Baja Ringan Profil "C", ukuran 75 x 35 x 0.75 mm dan Reng = - M2
69. Pek. Listplank (Kalciplank) = - M2
= M2
70. Pek. Rangka Langit-Langit/Plafon Besi Holow 40/40mm& 40/20 mm, Modul 60/60cm = 144.64 M2
= Volume Granit Lantai + Keramik Lant = ### + 7.00 = ### M2
Ruang dibawah Ramp = = 11.00 X 3.87 = ###
Tritisan = = = - M2
### M2
71. Pek. Langit-Langgit / Plafon Kalsiboard 3,5 mm = 144.64 M2
= Pek. Rangka Langit-Langit/Plafon Besi Holow 40/40mm& 40/20 mm, = ### M2
72. Pek. List Plafond GypsumProfil C-7 = 141.80 M
R. Perawatan 1 = 3.87 X 2.00 + 5.87 X 2.00 = 19.48 M
R. Perawatan 2 = 3.87 X 2.00 + 5.87 X 2.00 = 19.48 M
R. Dokter = 2.87 X 2.00 + 3.87 X 2.00 = 13.48 M
R. Tindakan + Gudang Alat = 3.87 X 2.00 + 3.37 X 2.00 = 14.48 M
Lorong = 2.87 X 2.00 + 13.37 X 2.00 = 32.48 M
- = 1.37 X 2.00 + 2.87 X 2.00 = 8.48 M
R. Dibawah Ramp = = - M
R. Pelayanan = 3.87 X 2.00 + 3.87 X 2.00 = 15.48 M
Teras = - - 2.00 + - X 2.00 = - M
KM/WC R. Perawatan 1 = 1.37 X 2.00 + 1.87 X 2.00 = 6.48 M
KM/WC R. Perawatan 2 = 1.37 X 2.00 + 1.87 X 2.00 = 6.48 M
KM/WC R. Perawat = 1.37 X 2.00 + 1.37 X 2.00 = 5.48 M
Tritisan = = - M
### M
73. Pek. Instalasi Listrik (Titik Lampu) dengan Kabel NYA 3X2.5mm = 23.00
74. Pek. Lampu Downlight ex. Philips 4" + lampu 18 Watt = 20.00
75. Pek. Lampu Downlight ex. Philips 4" + lampu 11 Watt = 3.00
76. Pek. Pengadaan Dan Pemasangan Saklar Dobel Panasonic = 5.00
77. Pek. Pengadaan Dan Pemasangan Saklar Tunggal = 10.00
78. Pek. Pengadaan Dan Pemasangan Stop Kontak = 9.00
79. Pek. AC 1 PK Termasuk MCB = -
80. Pek. MCB Untuk Persiapan AC = 3.00
81. Pek. Zakering Box 3 Group = -
82. Pek. Panel Induk = 1.00
83. Pek. Exhaust Fan 6" ex. PANASONIC KM/WC = -
84. Pek. Kabel Inlet Panel NYA 1x 16 mm (Pengadaan + Biaya Pasang) = 70.00
85. Pek. Kabel Outlet Panel 1X10 mm (Pengadaan + Biaya Pasang) = 70.00
86. Pek. Penambahan Daya dari 7,700 Volt Menjadi 23,000 Volt pada PLN = 1.00 Pkt
87. Pek. Pengadaan dan Pemasangan Closed Duduk Kwalitas I (Merk Toto) = 3.00 Bh
74. Pek. Pengadaan dan Pemasangan Closed Jongkok Kwalitas I = - Bh

75. Pasang Wasthafel Model Kotak Merk Toto lengkap dengan Kran Air = 3.00 Unit

76. Pengadaan dan Pemasangan bak cuci piring stainlessteel + Acc + Kran = 1.00 Bh

77. Pasang Pipa PVCØ 4" type D& Accessories (dari Klosed) = - M

78. Pasang Pipa PVCØ 3" type D& Accessories (dari Klosed) = 18.80 M

79. Pasang Pipa PVCØ 2" type AW& Accessories (Air Kotor) = 18.00 M

80. Pasang Pipa GI Medium Ø 1 1/4" & Accessories (Dari Tandon Air) = - M

81. Pasang Pipa PVCØ 1/2" type AW& Accessories (yg Menuju Kran Air) = 7.60 M

82. Pasang Pipa PVCØ 1" type AW& Accessories (Pembagi Air Bersih dari Tandon) = 20.79 Bh

83. Pasang Pipa PVCØ 3/4" type AW& Accessories (Distribusi Air Bersih) = - Bh

84. Pek. Pengeboran Air Tanah Dangkal Min 30m = 1.00 Bh

85. Pek. Pengadaan dan Pemasangan Pompa Air Jenis Jetpam = 1.00 Bh

86. Pengadaan Ember Besar + Gayung = 3.00 Pkt

87. Pasang Kran air Besi (ex Taho) Ø ½" dan Accessories = 3.00 Bh

88. Pasang Saringan air (Avour) Besi (Stainles) = 3.00 Bh

89. Pembuatan Septiptank dan Sumur Peresapan (Lengkap) Kapasitas 2,00 m3 = 1.00 Unit
90. Pek. Pipa Pegangan Stainless (Handle Grib) Ø 1.5" Panjang 100cm pada KM/WC Pasien (Harga + Biaya Pasang) = 9.00 Bh

91. Pek. Pengadaan Dan Pemasangan Tandon Air MPOIN PLUS L SNI 2400 Liter (Anti Lumut), lengkap dengan Accessories (input 1 1/2" Output 1 1/2") (Harga + Biaya Pasang = - Unit

92. Pengecatan Tembok dengan Cat Tembok Mutu Baik yang mengandung Acrelic Merk Nippon Paint = 1,066.39 M2
Total ecatan Tembok Baru = ### M2
93. Pek. Plafond dengan Cat Tembok Mutu Baik yang mengandung Acrelic Merk Nippon Paint = 144.64 M2
= Volume Plafond = ### M2
94. Pengecatan Baja IWF dengan Cat Anti Karat
= Pada BOQ Baja
95. Pek. Pengecatan/Polituran Daun Pintu dan Kusen Kayu = 34.32 M2
Pintu Masuk Utama P1 =
Pintu P2 = Luas Pintu X 2 Si = - X 2 Sisi = - M2
Pintu P3 = Luas Pintu X 2 Si = 8.19 X 2 Sisi = 16.38 M2
Pintu P4 = Luas Pintu X 2 Sisi 5.67 X 2 Sisi = 11.34 M2
Pintu P5 = Luas Pintu X 2 Sisi 3.33 X 2 Sisi = M2
Pintu P6 = Luas Pintu X 2 Sisi 1.30 X 2 Sisi = M2
Jendela J1 = = - M2
Jendela J2 = (1.25 X 2.00 + 0.40 X 2.00) X 2 Sisi = 6.60 M2
Ventilasi V1 = = - M2
Ventilasi V2 = = - M2
34.32 M2

96. Pek. Pengecatan Batu Alam = - M2


97. Pelapisan Waterprofing atap beton / Pelat Dak = - M2
98. Pengacatan Tembok dengan Cat KCA (Cat Textur Pasir) Termasuk Pengecatan Dasar = 5.44 M2
Pada Papan Nama Ruang Perawatan = 3.20 X 1.70 = 5.44 M2
99. Pek. ACP Exterior 4mm rangka Konstruksi Pipa Kotak = 76.44 M2
= (15.70 X 2.00 + 13.70 X 2.00) X 1.30 = 76.44 M2
100. Pek. Pengadaan dan Pemasangan Atap Kaca Tempered Clear 5 mm + PVB Clear 0.38mm + Kaca Tempered Clear 5 mm (Tebal Total 10.38mm) pada Teras Termasuk Aseso = - M2
101. Pek. Leter Nama dari Acrilic 5MM = 0.75 M2
= 0.15 X 2.00 + 0.15 X 3.00 = 0.75 M2
BOQ RUANG PERAWATAN PUSKESMAS RASANAE TIMUR LT.1
No URAIAN PEKERJAAN PERHITUNGAN VOLUME VOLUME
1. Pek. Pengukuran, Pematokan, dan Pemasangan Bauplank = - M
Arah Horisontal = 15.00 + 3.00 + 4.00 + 16.50 + 1.50 + 11.00 + 3.00 + 15.00 = 69.00 M
Arah Vertikal = 3.00 + 10.00 + 3.00 + 6.00 + 6.00 + 2.00 + 6.00 + 13.00 = 49.00 M
### M

2. Pek. Galian Tanah FootPlate Menggunakan Alat Berat = - M3


Footplate Bangunan = Pjg X Lbr X Tgg X Jml Foot= 1.20 X 1.20 X 1.55 X 16 Bh = 35.71 M3
Footplate Ramp = = 1.00 X 1.00 X 1.10 X 3 Bh = 3.30 M3
39.01 M3

3. Pek. Galian Tanah Menggunakan Tenaga Manusia = - M3


Galian Pondasi = Vol. Galian Pondasi Pas. Batu - Vol. Galian Kolom Padestal
= (Pjg Total X Lbr X Tgg) - (Pjg X Lbr X Tgg X Jml Klm)
= ### X 0.50 X 0.75) - (0.50 X 0.50 X 0.75 X 16.00) = 39.00 M3
Galian Saluran Keliling = Pjg Total Sal. X Lbr X Tgg = 63.00 X 0.50 X 0.50 = 15.75 M3
54.75 M3

4. Urugan Kembali Tanah Hasil Gali = - M3


= 0.25 X 54.75 = 13.69 M3

5. Urugan Tanah Pilihan Peninggian Lantai = - M3


Ket. :Dihitung Langsung pada Gbr Sketchup R. Perawatan 1 = 10.69 M3 Lorong = 17.45 M3 Teras = 2.39 M3
R. Perawatan 2 = 10.69 M3 R. Perawat = 2.55 M3 R. Perawatan 1 = 0.93 M3
R. Perawatan 3 = 4.56 M3 R. Dibawah Ramp = 19.48 M3 R. Perawatan 2 = 0.93 M3
R. Tindakan + Gudang Alat = 10.17 M3 R. Pelayanan = 6.98 M3/WC R. Perawat = 0.78 M3
87.60 M3
6. Pek. Urugan Pasir dibawah Pondasi dan Lantai = - M3
Urugan Dibawah Footplate Bangunan = 1.20 X 1.20 X 0.05 X 16 Bh = 1.15 M3
Urugan Dibawah Footplate Ramp = 1.00 X 1.00 X 0.05 X 3.00 = 0.15 M3
Urugan Dibawah Pondasi Pas. Batu = ### X 0.50 X 0.05 = 2.80 M3
Urugan Dibawah Rabbat Keliling = 47.16 X 0.05 = 2.36 M3
Urugan Dibawah Lantai
R. Perawatan 1 = 3.82 X 5.80 X 0.05 = 1.11 M3
R. Perawatan 2 = 3.82 X 5.80 X 0.05 = 1.11 M3
R. Perawatan 3 = 2.66 X 3.82 X 0.05 = 0.51 M3
R. Tindakan + Gudang Alat = 3.80 X 5.62 X 0.05 = 1.07 M3
Lorong = 2.80 X 12.92 X 0.05 = 1.81 M3
R. Perawat = 1.33 X 2.80 X 0.05 + 1.32 X 1.36 X 0.05 = 0.28 M3
R. Dibawah Ramp = 5.30 X 3.80 X 0.05 + 5.30 X 3.60 X 0.05 = 1.96 M3
R. Pelayanan = 3.80 X 3.80 X 0.05 = 0.72 M3
Teras = 3.85 X 1.54 X 0.05 = 0.30 M3
KM/WC R. Perawatan 1 = 1.33 X 1.82 X 0.05 = 0.12 M3
KM/WC R. Perawatan 2 = 1.33 X 1.82 X 0.05 = 0.12 M3
KM/WC R. Perawat = 1.32 X 1.35 X 0.05 = 0.09 M3
15.65 M3

7. Pek. Pasangan Batu Kosong = - M3


= Pjg Pondasi X Lbr X Tbl Pas. Batu Ko = ### X 0.50 X 0.20 = 11.20 M3

8. Pek. Pondasi Pas. Batu = - M3


Pondasi Pas. Batu 1
Arah Horisontal = (5.00 + 5.00 + 3.50) X 4 Brs X 0.40 X 0.50 = 10.80 M3
Arah Vertikal = (3.50 + 2.50 + 5.50) X 4 Brs X 0.40 X 0.50 = 9.20 M3
Pondasi Pas. Batu 2
Arah Horisontal = (2.70 + 3.70 + 3.70 + 3.24) X 0.40 X 0.50 = 2.67 M3
Arah Vertikal = (11.40 + 2.70 + 3.30 + 2.94) X 0.40 X 0.50 = 4.07 M3
26.74 M3
9. Pek. Pasangan Dinding 1/2 bata camp. 1pc:5ps = 378.10 M2
Arah Horisontal = (5.00 + 5.00 + 3.50) X 3 Brs X 3.60 = ### M2
= (5.00 + 1.74) X 1.20 = 8.09 M2
= (1.37 + 1.37 + 1.37) X 3.60 = 14.80 M2
= (0.37 + 1.37 + 1.37) X 3.60 = 11.20 M2
Arah Vertikal
= (3.50 + 2.50 + 5.50) X 2 Brs X 3.60 - 82.80 M2
= (5.50 X 5.50 + 3.74 + 1.37 + 1.37 + 1.87) X 3.60 = 69.66 M2
Pada Saluran = = - M2
Pada Ramp = = - M2
Pembungkus Kolom Baja = 1.70 X 3.60 X 16.00 = 97.92 M2

Pengurangan Luas Pas. Bata


Pintu Masuk Utama P1 = 2.28 X 4.30 X 0 Unit = - M2
Pintu P2 = 1.70 X 2.15 X 1 Unit = (3.66) M2
Pintu P3 = 1.40 X 2.15 X 3 Unit = (9.03) M2
Pintu P4 = 1.00 X 2.05 X 2 Unit = (4.10) M2
Pintu P5 = 1.00 X 1.90 X 3 Unit = (5.70) M2
Pintu P6 = 0.80 X 1.90 X 1 Unit = (1.52) M2
Jendela J1 = 1.90 X 1.80 X 4 Unit = ### M2
Jendela J2 = 1.05 X 1.50 X 7 Unit = ### M2
Ventilasi V1 = 0.60 X 0.35 X 5 Unit = (1.05) M2
Ventilasi V2 = 1.00 X 0.40 X 6 Unit = (2.40) M2
### M2

Plasteran = Pas. Bata X 2 Sisi = ### X 2 Sisi = ### M2 = 756.20 M2


Acian = Plasteran = ### M2 = 756.20 M2
Pengecatan Tembok Baru = Plasteran = ### M2 = 756.20 M2

10. Pek. Rabbat Keliling Bangunan = - M3


= Luas X Tbl = 47.16 X 0.05 = 2.36 M3

11. Pek. Rabbat dibawah Lantai = - M3


= Vol. Urugan Pasir dibawah L= 9.19 M3
=
12. Pek. Rabbat dibawah Footplate = - M3
Urugan Dibawah Footplate Bangunan = 1.20 X 1.20 X 0.10 X 16.00 = 2.30 M3
Urugan Dibawah Footplate Ramp = 1.00 X 1.00 X 0.10 X 3.00 = 0.30 M3
2.60 M3
13. Pek. Beton Pondasi Footplate = - M3
Footplate Bangunan
Footplate = {(Pjg X Lbr X Tb)+(Pjg Rata2 X Lbr Rta2 X Tbl)} X Jml Footplate
= {0.29 + (0.85 X 0.85 X 0.05)} X 16 Bh = 5.19 M3
Kolom Padestal = 0.50 X 0.50 X 1.20 X 16 Bh = 4.80 M3
Footplate Ramp
Footplate = {(Pjg X Lbr X Tb)+(Pjg Rata2 X Lbr Rta2 X Tbl)} X Jml Footplate
= {0.20 + (0.68 X 0.68 X 0.10)} X 3 Bh = 0.74 M3
Kolom Padestal = 0.35 X 0.35 X 1.00 X 3 Bh = 0.37 M3
11.09 M3

14. Pek. Bakesting Pondasi Footplate = - M2


Footplate Bangunan
Footplate = Lebar Sisi X Tbl = 4.80 X 0.20 X 16 Bh = 15.36 M2
Kolom Padestal = Lebar Sisi X Tgg X 2.00 X 1.20 X 16 Bh = 38.40 M2
Footplate Ramp
Footplate = Lebar Sisi X Tbl X J 4.00 X 0.20 X 3 Bh = 2.40 M2
Kolom Padestal = Lebar Sisi X Tgg X 1.40 X 1.00 X 3 Bh = 4.20 M2
60.36 M2

15. Pek. Pembesian Footplate


Footplate Bangunan
Footplate
Tul. Lentur Arah X Dia 12.00 = Pjg Tul. X Jml Tulangan X Jml Pond X BJ 12 Pjg Tul = 1.52 Jml = 8 Bh
= 1.52 X 8.00 X 16 Bh X 0.89 = 172.58 Kg = 172.58 Kg
Tul. Lentur Arah Y Dia 12.00 = Pjg Tul. X Jml Tulangan X Jml Pond X BJ 12 Pjg Tul = 1.52 Jml = 8 Bh
= 1.52 X 8.00 X 16 Bh X 0.89 = 172.58 Kg = 172.58 Kg
Tul. Susut Arah X Dia 12.00 = Pjg Tul. X Jml Tulangan X Jml Pond X BJ 12 Pjg Tul = 1.56 Jml = 8.00 Bh
= 1.56 X 8.00 X 16 Bh X 0.89 = 177.12 Kg = 177.12 Kg
Tul. Susut Arah Y Dia 12.00 = Pjg Tul. X Jml Tulangan X Jml Pond X BJ 12 Pjg Tul = 1.56 Jml = 8.00 Bh
= 1.56 X 8.00 X 16 Bh X 0.89 = 177.12 Kg = 177.12 Kg
Kolom Padestal =
Dia 16.00 = Pjg Total Tul X Jml Tul. X Jml Footpl = 2.07 X 4.00 X 16.00 X 1.58 = 208.92 Kg
Dia 14.00 = Pjg Total Tul X Jml Tul. X BJ D14 = 2.07 X 4.00 X 16.00 X 1.21 = 159.95 Kg
Tul. Sengk. Dia 6.00 = Pjg 1 Seng. X Jml Sengk. X BJ D 6 = 1.87 X 15 X 0.22 = 6.23 Kg

Footplate Ramp
Footplate
Tul. Lentur Arah X Dia 12.00 = Pjg Tul. X Jml Tulangan X Jml Pond X BJ 12 Pjg Tul = 1.32 Jml = 7 Bh
= 1.32 X 7.00 X 3 Bh X 0.89 = 24.59 Kg = 24.59 Kg
Tul. Lentur Arah Y Dia 12.00 = Pjg Tul. X Jml Tulangan X Jml Pond X BJ 12 Pjg Tul = 1.32 Jml = 7 Bh
= 1.32 X 7.00 X 3 Bh X 0.89 = 24.59 Kg = 24.59 Kg
Tul. Susut Arah X Dia 12.00 = Pjg Tul. X Jml Tulangan X Jml Pond X BJ 12 Pjg Tul = 1.36 Jml = 7 Bh
= 1.36 X 7.00 X 3 Bh X 0.89 = 25.33 Kg = 25.33 Kg
Tul. Susut Arah Y Dia 12.00 = Pjg Tul. X Jml Tulangan X Jml Pond X BJ 12 Pjg Tul = 1.36 Jml = 7 Bh
= 1.36 X 7.00 X 3 Bh X 0.89 = 25.33 Kg = 25.33 Kg
Kolom Padestal =
Dia 16.00 = Pjg Total Tul X Jml Tul. X Jml Footpl = 1.57 X 4.00 X 3.00 X 1.58 = 29.71 Kg
Dia 14.00 = Pjg Total Tul X Jml Tul. X Jml Footpl = 1.57 X 4.00 X 3.00 X 1.21 = 22.75 Kg
Tul. Sengk. Dia 6.00 = Pjg 1 Seng. X Jml Sengk. X Jml Footp = 1.27 X 11 X 3.00 X 0.22 = 9.31 Kg
### Kg

16. Pek. Beton Sloof = - M3


Sloof S1 Pjg Total Sloof X Lbr X Tgg
Arah Horisontal = (5.00 + 5.00 + 3.50) X 4 Brs X 0.35 X 0.20 = 3.78 M3
Arah Vertikal = (3.50 + 2.50 + 5.50) X 4 Brs X 0.35 X 0.20 = 3.22 M3
Sloof S2
Arah Horisontal = (2.70 + 3.70 + 3.70 + 3.24) X 0.20 X 0.13 = 0.35 M3
Arah Vertikal = (11.40 + 2.70 + 3.30 + 2.94) X 0.20 X 0.13 = 0.53 M3
7.88 M3

17. Pek. Bakesting Sloof = - M2


= Pjg X (lbr + Tgg)
Sloof S1
Arah Horisontal = (5.00 + 5.00 + 3.50) X 4 Brs X (0.20 + 0.70) = 48.60 M2
Arah Vertikal = (3.50 + 2.50 + 5.50) X 4 Brs X (0.20 + 0.70) = 41.40 M2
Sloof S2
Arah Horisontal = (2.70 + 3.70 + 3.70 + 3.24) X (0.13 + 0.40) = 7.07 M2
Arah Vertikal = (11.40 + 2.70 + 3.30 + 2.94) X (0.13 + 0.40) = 10.78 M2
### M2
Plasteran = = - M2
Acian = Pjg Sloof Sisi Luar X Tgg X = 55.80 X 0.35 X 1 Sisi = 19.53 M2
Pengecatan Tembok Baru = = 19.53 M2

18. Pek. Pembesian Sloof = - Kg


Tulangan Pokok = Pjg Besi X Jml Besi X Bj Besi
Tul. Sengkang = Jml Sengk. X Pjg 1 Sengk. X Bj Besi
Sloof S1
Tulangan Pokok Dia 12 = ### X 8 Bh X 0.89 = ### Kg
Tul. Sengkang Dia 6 = ### X 0.94 X 0.22 = ### Kg
Sloof S1
Tulangan Pokok Dia 12 = 33.68 X 4 Bh X 0.89 = ### Kg
Tul. Sengkang Dia 6 = ### X 0.50 X 0.22 = 24.95 Kg
= ### Kg
19. Pek. Beton Kolom = - -

20. Pek. Bakesting Kolom = - -

- -

Plasteran = - - = - M2
Acian = - - = - M2
Pengecatan Tembok Baru = - - = - M2

21. Pek. Pembesian Kolom = - Kg


0
Tulangan Pokok Dia 14 = Pjg 1 Tul. X Jml Tul. X Bj. = - X 4 Bh X 1.21 = - Kg
Dia 12 = Pjg 1 Tul. X Jml Tul. X Bj. = - X 4 Bh X 0.89 = - Kg
Tul. Sengkang Dia 6 = Pjg 1 Sengk. X Jml Sengk. X= (0.16) X - X 0.22 = - Kg
0
Tulangan Pokok Dia 10 = Pjg 1 Tul. X Jml Tul. X Bj. = - X 6 Bh X 0.62 = - Kg
Dia 10 = Pjg 1 Tul. X Jml Tul. X Bj. = - X 0 Bh X 0.62 = - Kg
Tul. Sengkang Dia 6 = Pjg 1 Sengk. X Jml Sengk. X= (0.16) X - X 0.22 = - Kg
= - Kg

22. Pek. Beton K.125 Pembungkus Kolom Baja = 6.08 M3


= Pjg X Lbr X Tgg X Jml Kolom
= 0.48 X 0.22 X 3.60 X 16 Bh = 6.08 M3

23. Pek. Kolom Praktis = 104.40 M


= Tgg Kolom X Jml Kolom = 3.60 X 29.00 = ### M

24. Pek. Beton Balok = 1.26 M3


= Lbr X Tgg X Pjg Total
Balok Ramp Pjg Tot= - + - = - M
Balok Diatas Kusen Pjg Tot= 5.15+5.15+3.65+2.27+2.51+1.76+1.76+5.15+5.15+6+3+4+1.37+2.87+ = 56.83 M
Balok Plat Pjg Tot= - = - M

Balok Ramp = 0.25 X 0.35 X - = - M3


Balok Diatas Kusen = 0.13 X 0.17 X 56.83 = 1.26 M3
Balok Plat = 0.13 X 0.17 X - = - M3
1.26 M3

25. Pek. Bakesting Balok = 26.71 M2


Balok Ramp = (Lbr + 2xTgg )X Pjg Total = (0.25 + 0.70) X - = - M2
Balok Diatas Kusen = (Lbr + 2xTgg )X Pjg Total = (0.13 + 0.34) X 56.83 = 26.71 M2
Balok Plat = (Lbr + 2xTgg )X Pjg Total = (0.13 + 0.34) X - = - M2
26.71 M2

Plasteran = - M2 = - M2
Acian = 26.71 M2 = 26.71 M2
Pengecatan Tembok Baru = 26.71 M2 = 26.71 M2

26. Pek. Pembesian Balok = 238.62 Kg


Balok Ramp
Tulangan Pokok Dia 16 = Pjg 1 Tul. X Jml Tul. X Bj. = - X 6 Bh X 1.58 = - Kg
Dia 12 = Pjg 1 Tul. X Jml Tul. X Bj. = - X 4 Bh X 0.89 = - Kg
Tul. Sengkang Dia 8 = Pjg 1 Sengk. X Jml Sengk. X= 1.04 X - X 0.39 = - Kg
Balok Diatas Kusen
Tulangan Pokok Dia 12 = Pjg 1 Tul. X Jml Tul. X Bj. = 56.83 X 4 Bh X 0.89 = ### Kg
Dia 10 = Pjg 1 Tul. X Jml Tul. X Bj. = 56.83 X 0 Bh X 0.62 = - Kg
Tul. Sengkang Dia 6 = Pjg 1 Sengk. X Jml Sengk. X= 0.44 X ### X 0.22 = 36.98 Kg
Balok Plat
Tulangan Pokok Dia 12 = Pjg 1 Tul. X Jml Tul. X Bj. = - X 4 Bh X 0.89 = - Kg
Dia 10 = Pjg 1 Tul. X Jml Tul. X Bj. = - X 2 Bh X 0.62 = - Kg
Tul. Sengkang Dia 6 = Pjg 1 Sengk. X Jml Sengk. X= 0.44 X - X 0.22 = - Kg
### Kg

27. Pek. Beton Ringbalk = - M

28. Pek. Balok Late = - M

29. Pek. Beton Plat 10cm = 0.99 M3


Plat Diatas Kusen Pjg Pla = 9.12+15.32+2.87+4.23+4.23 = 35.77 M
= Pjg Plat X Lbr X Tbl = 35.77 X 0.30 X 0.08 = 0.86 M3
Plat Samping Kusen = Lbr Rata2 X Tgg X Tbl X J = 0.20 X 4.00 X 0.08 X 2 Bh = 0.13 M3
= 0.99 M3

30. Pek. Bakesting Plat 10 cm = 11.94 M2


Plat Diatas Kusen = Pjg X Lbr Rata2 + Pjg X Tbl = 35.77 X 0.20 + 35.77 X 0.08 = 10.02 M2 = 10.0156 M2
Plat Samping Kusen = (Lbr Rata2 X Tgg X 2 Sisi + Tbl X Tgg= 0.20 X 4.00 X 2 Sisi + 0.08 X 4.00 X 1 Bh = 1.920 M2
11.94 M2

Plasteran = 11.94 M2 = 11.94 M2


Acian = 11.94 M2 = 11.94 M2
Pengecatan Tembok Baru = 11.94 M2 = 11.94 M2

31. Pek. Pembesian Plat 10 cm = 121.67 Kg


Plat Diatas Kusen =
Arah X Dia 10 = Pjg Tul. X Jml Tul. X BJ. Tu= 0.30 X 238 Bh X 0.616 = 43.98 Kg
Arah Y Dia 10 = Pjg Tul. X Jml Tul. X BJ. Tu= 35.77 X 3 Bh X 0.616 = 66.10 Kg
Plat Samping Kusen =
Arah Horisontal Dia 10 = Pg Rata2 Tul. X Jml Tul X Bj. Tul. X = 0.40 X 27.00 X 0.616 X 1 Bh = 6.65 Kg
Arah Vertikal Dia 10 = Pjg Tul. X Jml Tul. X BJ. Tul X Jml T = 4.00 X 2.00 X 0.616 X 1 Bh = 4.93 Kg
### Kg

32. Pek. Beton Plat 12 cm Pada Plat Ramp & Bordes = - -


Plat Ramp = Pjg Plat X Lbr Plat X Tbl Pl =
Plat Bordes = Pjg Plat X Lbr Plat X Tbl Pl =

33. Pek. Bakesting Plat 12 cm Pada Plat Ramp & Bordes = - M2


Plat Ramp = Pjg Plat X Lbr Plat + Pjg Plat X Tbl Pla= - X - + - X - = - M2
Plat Bordes = Pjg Plat X Lbr Plat + Pjg Plat X Tbl Pla= - X - + - X - = - M2
- M2

Plasteran = Pjg Plat X Tbl Pla= - X - = - M2 = - M2


Acian = - M2 = - M2
Pengecatan Tembok Baru = - M2 = - M2

34. Pek. Pembesian Plat 12 cm Pada Plat Ramp & Bordes = - Kg


Plat Ramp = Pjg Tul X Jml Tul. X Bj Tul.
Tulangan Lentur Arah Memanjang Dia 10 = - X - X 0.616 = - Kg
Tulangan Lentur Arah Melintang Dia 10 = - X - X 0.616 = - Kg
Tulangan Susut Arah Memanjang Dia 10 = - X - X 0.616 = - Kg
Tulangan Susut Arah Melintang Dia 10 = - X - X 0.616 = - Kg
Plat Bordes = Pjg Tul X Jml Tul. X Bj Tul.
Tulangan Lentur Arah Memanjang Dia 10 = - X - X 0.616 = - Kg
Tulangan Lentur Arah Melintang Dia 10 = - X - X 0.616 = - Kg
Tulangan Susut Arah Memanjang Dia 10 = - X - X 0.616 = - Kg
Tulangan Susut Arah Melintang Dia 10 = - X - X 0.616 = - Kg
- Kg
35. Pek. Plat Lantai Bondek Tebal 12cm = - M3
Luas = Luas Bangunan - Luas Void Rampp - L=
= (Pjg X Lbr Bangunan ) - (Pjg X Lbr Void Ramp) - (Luas Permukaan Klm Baja X Jml Klm Baja)
Dimana Luas Permukaan Kl = 0.125*0.009*2+0.25*0.006* = ### M2

= 15.00 X 13.00 - 11.00 X 4.00 - 0.00 X 16 Bh = ### M2


Volume Plat Lantai = Luas X Tbl Plat = ### X 0.12 = 18.11 M3

36. Pek. Granit Lantai 60x60cm = 156.91 M2

R. Perawatan 1 = 5.37 X 3.87 + 3.87 X 2.05 = 28.72 M2


R. Perawatan 2 = 5.37 X 3.87 + 3.87 X 2.05 = 28.72 M2
R. Perawatan 3 = 5.87 X 3.87 = 22.72 M2
R. Perawat = 2.87 X 1.37 + 1.37 X 1.50 = 5.99 M2
Lorong = 2.87 X 9.87 + 1.87 X 2.39 = 32.80 M2
R. Depan Ramp = 0.63 X 2.39 + 3.37 X 3.89 = 14.62 M2
Ramp = = - M2
Gudang = 1.37 X 1.87 = 2.56 M2
Teras = 3.85 X 5.50 = 21.18 M2
Pengurangan Sedut Klm = 0.50 X 0.18 X 0.18 X 23 Bh = (0.37) M2
### M2

37. Pas. Plint/list keramik ukuran 10cmx 60cm = - M2

38. Pas. Lantai Keramik Motif KM/WC = 9.56 M2


= Pjg X Lbr
KM/WC R. Perawatan 1 = 1.37 X 1.87 = 2.56 M2
KM/WC R. Perawatan 2 = 1.37 X 1.87 = 2.56 M2
KM/WC R. Perawatan 3 = 1.37 X 1.87 = 2.56 M2
KM/WC R. Perawat = 1.37 X 1.37 = 1.88 M2
9.56 M2

39. Pas. Keramik Dinding ukuran 20x60cm (termasuk pada KM/WC) = 87.52 M2
KM/WC R. Perawatan 1 = 2.74 X 1.50 + 3.74 X 1.50 - 1.00 X 1.50 = 8.22 M2
KM/WC R. Perawatan 2 = 2.74 X 1.50 + 3.74 X 1.50 - 1.00 X 1.50 = 8.22 M2
KM/WC R. Perawatan 3 = 2.74 X 1.50 + 3.74 X 1.50 - 1.00 X 1.50 = 8.22 M2
KM/WC R. Perawat = 2.74 X 1.50 + 2.74 X 1.50 - 0.90 X 1.50 = 6.87 M2
R. Perawatan 1 = 10.74 X 1.50 + 3.87 X 1.50 - 1.00 X 1.50 - 1.40 X 1.50 = 18.31 M2
R. Perawatan 2 = 10.74 X 1.50 + 3.87 X 1.50 - 1.00 X 1.50 - 1.40 X 1.50 = 18.31 M2
R. Perawatan 3 = 11.74 X 1.50 + 3.87 X 1.50 - 1.70 X 1.50 - 1.00 X 1.50 = 19.37 M2
87.52 M2
Pengurangan
Plasteran = - M2 = - M2
Acian = ### M2 = (87.52) M2
Pengecatan Tembok Baru = ### M2 = (87.52) M2

40. Pas. Dinding Batu Tempel Motif = - M2

41. Pas. Keramik Dinding Artistik motif Batu Alam = - M2

42. Plesteran dinding Camp. 1Pc;3Ps, Tebal 15mm = - M2


Total = - M2
43. Plesteran dinding dan Beton Camp. 1Pc;5Ps, Tebal 15mm = 768.14 M2
Total Plasteran = ### M2
44. Acian PC. pada Dinding dan Beton = 726.85 M2
Total Acian = ### M2

45. Pasang Kusen Pintu dan Jendela Alumunium = 140.70 M


= Lbr X 1 Bh + Tgg X 2 Bh X Jml
Pintu Masuk Utama P1 = 2.28 X 1 Bh + 4.30 X 2 Bh X 0 Unit = - M
Pintu P2 = 1.70 X 1 Bh + 2.10 X 2 Bh X 1 Unit = 5.90 M
Pintu P3 = 1.40 X 1 Bh + 2.10 X 2 Bh X 3 Unit = 16.80 M
Pintu P4 = 1.00 X 1 Bh + 2.00 X 2 Bh X 2 Unit = 10.00 M
Pintu P5 = 1.00 X 1 Bh + 1.85 X 2 Bh X 3 Unit = 14.10 M
Pintu P6 = 0.80 X 1 Bh + 1.85 X 2 Bh X 1 Unit = 4.50 M
Jendela J1 = 1.90 X 2 Bh + 1.75 X 2 Bh X 4 Unit = 29.20 M
Jendela J2 = 1.05 X 2 Bh + 1.45 X 2 Bh X 7 Unit = 35.00 M
Ventilasi V1 = 0.60 X 2 Bh + 0.30 X 2 Bh X 5 Unit = 9.00 M
Ventilasi V2 = 1.00 X 2 Bh + 0.35 X 2 Bh X 6 Unit = 16.20 M
### M

46. Pek. Kusen Kayu Kalas I = - M2

47. Pasang Daun Pintu Kaca Bening T= 8mm Rangka Alumunium = - M2

48. Pek. Pintu Double Kaca Tempret T= 12mm Lengkap dengan Handle dan Expanolet serta Kelengkapannya = - M2
= Pjg X Lbr
= - X - = - M2
49. Pek. Partisi Kaca Tempret T= 12mm
50. Pek. daun pintu panel kayu klas I = = 11.97 M2
Pintu P3 = 1.30 X 2.10 X 3 Unit = 8.19 M2
Pintu P4 = 0.90 X 2.10 X 2 Unit = 3.78 M2
11.97 M2
51. Pek. Daun pintu plywood 4mm rangkap Lapis HPL , rangka kayu klas I tertutup (KM/WC) = 6.29 M2
Pintu P5 = 0.90 X 1.85 X 3 Unit = 4.99 M2
Pintu P6 = 0.70 X 1.85 X 1 Unit = 1.30 M2
6.29 M2
52. Pek. Daun pintu plywood 6mm rangkap Lapis HPL , rangka kayu klas I tertutup (lebar sampai 90cm) = 3.36 M2
Pintu P2 = 1.60 X 2.10 X 1.00 = 3.36 M2
53. Pek. Jendela dan Fentilasi Casement Kaca Bening T=5mmRangka Alumunium(Lengkap dgn Asesoris) = 5.25 M2
Jendela J2 = 0.60 X 1.25 X 7 Unit = 5.25 M2

54. Pek. Daun Jendela Sliding Kaca Bening T=5mmRangka Alumunium(Lengkap dgn Asesoris)
55. Pek. Kaca Bening T= 5mm(Jendela Kaca Mati) = 2.63 M2
Jendela J2 = 1.25 X 0.30 X 7.00 = 2.63 M2
56. Pek. Kaca Bening T= 8 mm(Jendela Kaca Mati) = 10.56 M2
Jendela J1 = 1.50 X 0.88 X 2 Bh X 4 Unit = 10.56 M2
57. Pengadaan dan Pemasangan Stiker Sanblast = 0.96 M2
Pintu Masuk Utama P1 = 1.60 X 0.60 = 0.96 M2
58. Pengadaan dan Pemasangan Stiker One Way = 16.13 M2
Jendela J1 10.56 = 10.56 M2
Jendela J2 = 2.94 + 2.63 = 5.56 M2
16.13 M2
59. Pek. Grendel Pintu Tanam Pada Pintu Dobel = 4.00 Bh
Pintu P2 = 1.00 X 1.00 = 1.00 Bh
Pintu P3 = 1.00 X 3.00 = 3.00 Bh
4.00 Bh
60. Pek. Grendel Jendela = 14.00 Bh
Jendela J2 = 2 Bh X 7 Unit = 14.00 Bh
61. Pek. Haag Angin = 7.00 Bh
Jendela J2 = 1 Bh X 7.00 = 7.00 Bh
62. Pek. Pengadaan dan Pemasangan Kunci Pintu Kwalitas I 2 Slaag = 6.00 Bh
Pintu P2 = - X 1 Unit = - Bh
Pintu P3 = - X 3 Unit = - Bh
Pintu P4 = 1.00 X 2 Unit = 2.00 Bh
Pintu P5 = 1.00 X 3 Unit = 3.00 Bh
Pintu P6 = 1.00 X 1 Unit = 1.00 Bh
6.00 Bh
63. Pek. Engsel Pintu Mutu Baik (Doors Hinge) setara Deksson = 18.00 Bh
Pintu P2 = 2.00 X 1 Unit = - Bh
Pintu P3 = 2.00 X 3 Unit = 6.00 Bh
Pintu P4 = 2.00 X 2 Unit = 4.00 Bh
Pintu P5 = 2.00 X 3 Unit = 6.00 Bh
Pintu P6 = 2.00 X 1 Unit = 2.00 Bh
18.00 Bh
64. Pek. Engsel Jendela Mutu Baik (windows Hinge) = 14.00 Bh
Jendela J2 = 2 Bh X 7 Unit = 14.00 Bh
65. Pasang Kunci Silinder Pintu mutu baik pada Pintu Dobel = 4.00 Bh
Pintu P2 = 1.00 X 1.00 = 1.00 Bh
Pintu P3 = 1.00 X 3.00 = 3.00 Bh
4.00 Bh
66. Pengadaan Handel Pintu Panjang Minal 60cm = 1.00 Bh
Pintu P2 = 1.00 X 1.00 = 1.00 Bh
67. Pek. Rangka Atap Baja Ringan Profil "C", ukuran 75 x 35 x 0.75 mm dan Reng ukuran 0,45/16/31/11mm = 235.98 M2
Didapat Langsung dari Luas Pd GBr Sketchup = 51.93 X 2 Sisi + 66.06 X 2 Sisi = ### M2
68. Pek. Atap Zincalume (Spandek) T.0,40mm = 235.98 M2
= Pek. Rangka Atap Baja Ringan Profil "C", ukuran 75 x 35 x 0.75 mm dan Reng = ### M2
69. Pek. Listplank (Kalciplank) = 62.80 M2
= 14.70 X 2.00 + 16.70 X 2.00 = 62.80 M2
70. Pek. Rangka Langit-Langit/Plafon Besi Holow 40/40mm& 40/20 mm, Modul 60/60cm = 253.52 M2
= Volume Granit Lantai + Keramik Lant = ### + 9.56 = ### M2
Ruang Ramp = Pjg X Lbr = 3.87 X 10.81 = 41.83
Tritisan = Pjg Tritisan X Lbr Tritisan = 56.52 X 0.80 = 45.22 M2
### M2
71. Pek. Langit-Langgit / Plafon Kalsiboard 3,5 mm = 253.52 M2
= Pek. Rangka Langit-Langit/Plafon Besi Holow 40/40mm& 40/20 mm, = ### M2
72. Pek. List Plafond GypsumProfil C-7 = 306.49 M
R. Perawatan 1 = 5.37 X 2.00 + 5.87 X 2.00 = 22.48 M
R. Perawatan 2 = 5.37 X 2.00 + 5.87 X 2.00 = 22.48 M
R. Perawatan 3 = 5.87 X 2.00 + 3.87 X 2.00 = 19.48 M
R. Perawat = 2.87 X 2.00 + 2.87 X 2.00 = 11.48 M
Lorong = 2.87 X 2.00 + 9.87 X 2.00 = 25.48 M
R. Depan Ramp = 3.38 X 2.00 + 3.89 X 1.00 = 10.65 M
Ramp = 3.87 X 2.00 + 10.98 X 2.00 = 29.70 M
Gudang = 1.37 X 2.00 + 1.87 X 2.00 = 6.48 M
Teras = 3.85 X 2.00 + 5.50 X 2.00 = 18.70 M
KM/WC R. Perawatan 1 = 1.37 X 2.00 + 1.87 X 2.00 = 6.48 M
KM/WC R. Perawatan 2 = 1.37 X 2.00 + 1.87 X 2.00 = 6.48 M
KM/WC R. Perawatan 3 = 1.37 X 2.00 + 1.87 X 2.00 = 6.48 M
KM/WC R. Perawat = 1.37 X 2.00 + 1.37 X 2.00 = 5.48 M
Tritisan = 56.52 X 2.00 + 0.80 X 2.00 = ### M
### M
73. Pek. Instalasi Listrik (Titik Lampu) dengan Kabel NYA 3X2.5mm = 23.00 -
74. Pek. Lampu Downlight ex. Philips 4" + lampu 18 Watt = 20.00 -

75. Pek. Lampu Downlight ex. Philips 4" + lampu 11 Watt = 4.00 -

76. Pek. Pengadaan Dan Pemasangan Saklar Dobel Panasonic = 4.00 -

77. Pek. Pengadaan Dan Pemasangan Saklar Tunggal = 10.00 -

78. Pek. Pengadaan Dan Pemasangan Stop Kontak = 12.00 -

79. Pek. AC 1 PK Termasuk MCB = 1.00 -

80. Pek. MCB Untuk Persiapan AC = 3.00 -

81. Pek. Zakering Box 3 Group = 1.00 -

82. Pek. Panel Induk = 1.00 -

83. Pek. Exhaust Fan 6" ex. PANASONIC KM/WC = - -

84. Pek. Kabel Inlet Panel NYA 1x 16 mm (Pengadaan + Biaya Pasang) = 70.00 -

85. Pek. Kabel Outlet Panel 1X10 mm (Pengadaan + Biaya Pasang) = 70.00 -

86. Pek. Penambahan Daya dari 7,700 Volt Menjadi 23,000 Volt pada PLN = - Pkt
73. Pek. Pengadaan dan Pemasangan Closed Duduk Kwalitas I (Merk Toto) = 4.00 Bh
74. Pek. Pengadaan dan Pemasangan Closed Jongkok Kwalitas I = - Bh

75. Pasang Wasthafel Model Kotak Merk Toto lengkap dengan Kran Air = 5.00 Unit

76. Pengadaan dan Pemasangan bak cuci piring stainlessteel + Acc + Kran = - Bh

77. Pasang Pipa PVCØ 4" type D& Accessories (dari Klosed) = - M

78. Pasang Pipa PVCØ 3" type D& Accessories (dari Klosed) = 27.37 M

79. Pasang Pipa PVCØ 2" type AW& Accessories (Air Kotor) = 26.57 M

80. Pasang Pipa GI Medium Ø 1 1/4" & Accessories (Dari Tandon Air) = - M

81. Pasang Pipa PVCØ 1/2" type AW& Accessories (yg Menuju Kran Air) = 9.50 M

82. Pasang Pipa PVCØ 1" type AW& Accessories (Pembagi Air Bersih dari Tandon) = 29.29 Bh

83. Pasang Pipa PVCØ 3/4" type AW& Accessories (Distribusi Air Bersih) = - Bh

84. Pek. Pengeboran Air Tanah Dangkal Min 30m = - Bh


85. Pek. Pengadaan dan Pemasangan Pompa Air Jenis Jetpam = - Bh

86. Pengadaan Ember Besar + Gayung = 4.00 Pkt

87. Pasang Kran air Besi (ex Taho) Ø ½" dan Accessories = 4.00 Bh

88. Pasang Saringan air (Avour) Besi (Stainles) = 4.00 Bh

89. Pembuatan Septiptank dan Sumur Peresapan (Lengkap) Kapasitas 2,00 m3 = - Unit

90. Pek. Pipa Pegangan Stainless (Handle Grib) Ø 1.5" Panjang 100cm pada KM/WC Pasien (Harga + Biaya Pasang) = 12.00 Bh

91. Pek. Pengadaan Dan Pemasangan Tandon Air MPOIN PLUS L SNI 2400 Liter (Anti Lumut), lengkap dengan Accessories (input 1 1/2" Output 1 1/2") (Harga + Biaya Pasang = 1.00 Unit

92. Pengecatan Tembok dengan Cat Tembok Mutu Baik yang mengandung Acrelic Merk Nippon Paint = 726.85 M2
Total ecatan Tembok Baru = ### M2
93. Pek. Plafond dengan Cat Tembok Mutu Baik yang mengandung Acrelic Merk Nippon Paint = 253.52 M2
= Volume Plafond = ### M2
94. Pengecatan Baja IWF dengan Cat Anti Karat
= Pada BOQ Baja
95. Pek. Pengecatan/Polituran Daun Pintu dan Kusen Kayu = 41.70 M2
Pintu Masuk Utama P1 =
Pintu P2 = Luas Pintu X 2 Si = - X 2 Sisi = - M2
Pintu P3 = Luas Pintu X 2 Si = 8.19 X 2 Sisi = 16.38 M2
Pintu P4 = Luas Pintu X 2 Sisi 3.78 X 2 Sisi = 7.56 M2
Pintu P5 = Luas Pintu X 2 Sisi 4.99 X 2 Sisi = 9.99 M2
Pintu P6 = Luas Pintu X 2 Sisi 1.30 X 2 Sisi = 2.59 M2
Jendela J1 = = - M2
Jendela J2 = (1.25 X 2.00 + 0.60 X 2.00) X 2 Sisi X 0.10 X 7 Unit = 5.18 M2
Ventilasi V1 = = - M2
Ventilasi V2 = = - M2
41.70 M2

96. Pek. Pengecatan Batu Alam = - M2


97. Pelapisan Waterprofing atap beton / Pelat Dak = - M2
98. Pengacatan Tembok dengan Cat KCA (Cat Textur Pasir) Termasuk Pengecatan Dasar = 5.44 M2
Pada Papan Nama Ruang Perawatan = 1.70 X 3.20 = 5.44 M2
99. Pek. ACP Exterior 4mm rangka Konstruksi Pipa Kotak = - M2
= = - M2
100. Pek. Pengadaan dan Pemasangan Atap Kaca Tempered Clear 5 mm + PVB Clear 0.38mm + Kaca Tempered Clear 5 mm (Tebal Total 10.38mm) pada Teras Termasuk Aseso = - M2
101. Pek. Leter Nama dari Acrilic 5MM = 0.74 M2
= 0.15 X 2.00 + 0.15 X 2.90 = 0.74 M2
BOQ RUANG PERAWATAN PUSKESMAS RASANAE TIMUR LT.1
No URAIAN PEKERJAAN PERHITUNGAN VOLUME VOLUME
1. Pek. Pengukuran, Pematokan, dan Pemasangan Bauplank = 45.60 M
Arah Horisontal = 6.95 + 6.55 + 1.10 + 6.55 + 1.50 + 6.95 = 29.60 M
Arah Vertikal = 11.00 + 1.50 + 1.50 + 2.00 = 16.00 M
45.60 M

2. Pek. Galian Tanah FootPlate Menggunakan Alat Berat = - -

3. Pek. Galian Tanah Menggunakan Tenaga Manusia = 42.64 M3


Panjang Arah Horisontal = 6.95 + 6.55 + 1.10 + 6.55 + 1.50 + 6.95 = 29.60 M
Arah Vertikal = 15.00 + 1.50 + 1.50 + 3.95 + 1.75 = 23.70 M
53.30 M
Volume = Pjg X Lbr Gal. X = 53.30 X 0.80 X 1.00 = 42.64 M3

4. Urugan Kembali Tanah Hasil Gali = 10.66 M3


= 0.25 X 42.64 = 10.66 M3

5. Urugan Tanah Pilihan Peninggian Lantai = 31.32 M3


Volume = Pjg X Lbr X Tgg
Teras = 6.65 X 3.70 X 0.15 = 3.69 M3
Ruang Tindakan = (6.65 X 5.20 + 5.15 X 1.65) X 0.40 = 17.23 M3
KM/WC Ruang Tindakan = 1.20 X 1.20 X 0.40 = 0.58 M3
Ruang Perawatan UGD = 5.15 X 1.65 + 6.65 X 2.20 X 0.40 = 9.25 M3
KM/WC Ruang Perawatan UGD = 1.20 X 1.20 X 0.40 = 0.58 M3
31.32 M3
6. Pek. Urugan Pasir dibawah Pondasi dan Lantai = 7.01 M3
Volume = Pjg X Lbr X Tgg
Dibawah Pondasi = 53.30 X 0.80 X 0.05 = 2.13 M3
Dibawah Lantai Teras = 6.80 X 3.85 X 0.05 = 1.31 M3
Dibawah Lantai Ruang Tindakan = (6.80 X 5.05 + 5.30 X 1.80) X 0.05 = 2.19 M3
Dibawah Lantai KM/WC Ruang Tindakan = 1.35 X 1.35 X 0.05 = 0.09 M3
Dibawah Lantai Ruang Perawatan UGD = (5.30 X 1.50 + 6.80 X 2.35) X 0.05 = 1.20 M3
Dibawah Lantai KM/WC Ruang Perawatan UGD = 1.35 X 1.35 X 0.05 = 0.09 M3
7.01 M3

7. Pek. Pasangan Batu Kosong = 8.52 M3


= Pjg Pondasi X Lbr X Tbl Pas. Batu Ko = 53.30 X 0.80 X 0.20 = 8.53 M3

8. Pek. Pondasi Pas. Batu = 19.98 M3


= Pjg Pondasi X Lbr Rata2 X Tgg = 53.30 X 0.50 X 0.75 = 19.99 M3

Plasteran = Pjg Pindasi Bagian Luar X Tgg Plastr = 34.10 X 0.20 X 1 Sisi = 6.82 M2
Acian = Plasteran = 6.82 M2
Pengecatan Tembok Baru = Plasteran = 6.82 M2
9. Pek. Pasangan Dinding 1/2 bata camp. 1pc:5ps = 155.59 M2
Dinding Pas. Bata
Dinding Tinggi 5.25m (termasuk Ringbalk & Blk Late) = (6.95 + 11.00) X 4.850 = ### M2
Tinggi 4.22m (Pd Pintu Keluar) = 2.00 X 3.82 = 7.64 M2
Tingg 3.60m (Termasuk Ringbalk) = 19.90 X 3.40 = 67.66 M2
Mainan pada Teras = 0.35 X 1.69 X 10 Bh = 5.91 M2
Papan Nama Pd Teras = (0.80 X 5.40 = 4.32 M2
Pengurangan
Beton Pintu Utama (pintu Tempered Depan) P1 = 2.42 X 2.10 X 1 Unit = (5.08) M2
Pintu P2 = 2.15 X 1.70 X 1 Unit = (3.66) M2
Pintu P3 = 2.15 X 1.40 X 1 Unit = (3.01) M2
Pintu P4 (KM/WC) = 1.90 X 1.00 X 2 Unit = (3.80) M2
Jendela J1 = 1.05 X 0.50 X 2 Unit = (1.05) M2
Ventilasi KM/WC (V1) = 1.00 X 0.40 X 1 Unit = (0.40) M2
### M2
Plasteran = Luas. Pas. Bata X 2 Sisi = ### X 2 Sisi = 311.18 M2
Acian = Plasteran = 311.18 M2
Pengecatan Tembok Baru = Plasteran = 311.18 M2

10. Pek. Rabbat Keliling Bangunan = - -

11. Pek. Rabbat dibawah Lantai = 8.30 M3


= Vol. Urugan Pasir dibawah L= 8.30 M3
=
12. Pek. Rabbat dibawah Footplate = - #REF!
13. Pek. Beton Pondasi Footplate = - #REF!

14. Pek. Bakesting Pondasi Footplate = - #REF!

15. Pek. Pembesian Footplate = - #REF!

16. Pek. Beton Sloof = 1.64 M3


= Pjg X Lbr X Tgg
= ### X 0.150 X 0.250 = 1.646 M3

17. Pek. Bakesting Sloof = 21.95 M2


= Pjg X Tgg X 2 Sisi
= 43.90 X 0.25 X 2 Sisi = 21.95 M2
21.95 M2
Plasteran = = - M2
Acian = Pjg Sloof Sisi Luar X Tgg X = 31.95 X 0.25 X 1 Sisi = 7.99 M2
Pengecatan Tembok Baru = = 7.99 M2

18. Pek. Pembesian Sloof = 197.34 Kg


Tulangan Pokok = Pjg Besi X Jml Besi X Bj Besi
Tul. Sengkang = Jml Sengk. X Pjg 1 Sengk. X Bj Besi
0
Tulangan Pokok Dia 12 = 43.90 X 4 Bh X 0.89 = ### Kg
Tul. Sengkang Dia 6 = ### X 0.64 X 0.22 = 41.58 Kg
= ### Kg
19. Pek. Beton Kolom = 2.05 M3
= Pjg X Lbr X Tgg Total
Klm K1 = 0.35 X 0.35 X 12.65 = 1.55 M3
Klm K2 = 0.20 X 0.35 X 3.00 = 0.21 M3
Klm K3 = 0.25 X 0.25 X 4.80 = 0.30 M3

2.06 M3

20. Pek. Bakesting Kolom = 25.81 M2


= (2XPjg + 2Xlbr )X Tgg Total
Klm K1 = (0.70 + 0.70) X 12.65 = 17.71 M2
Klm K2 = (0.40 + 0.70) X 3.00 = 3.30 M2
Klm K3 = (0.50 + 0.50) X 4.80 = 4.80 M2

25.81 M2

Plasteran = - M2 = - M2
Acian = 25.81 M2 = 25.81 M2
Pengecatan Tembok Baru = 25.81 M2 = 25.81 M2

21. Pek. Pembesian Kolom = 121.99 Kg


Klm K1
Tulangan Pokok Dia 14 = Pjg 1 Tul. X Jml Tul. X Bj. = ### X 4 Bh X 1.207 = 61.09 Kg
Tul. Sengkang Dia 6 = Pjg 1 Sengk. X Jml Sengk. X= 1.240 X 84 Bh X 0.222 = 23.10 Kg
Klm K2
Tulangan Pokok Dia 12 = Pjg 1 Tul. X Jml Tul. X Bj. = 3.000 X 4 Bh X 0.887 = 10.64 Kg
Tul. Sengkang Dia 6 = Pjg 1 Sengk. X Jml Sengk. X= 0.940 X 20 Bh X 0.222 = 4.17 Kg
Klm K3
Tulangan Pokok Dia 12 = Pjg 1 Tul. X Jml Tul. X Bj. = 4.800 X 4 Bh X 0.887 = 17.03 Kg
Tul. Sengkang Dia 6 = Pjg 1 Sengk. X Jml Sengk. X= 0.840 X 32 Bh X 0.222 = 5.96 Kg

= ### Kg

22. Pek. Beton K.125 Pembungkus Kolom Baja = - -

23. Pek. Kolom Praktis = 55.40 M


= Tgg Kolom X Jml Kolom
= 5.05 X 4 Bh + 3.40 X 8 Bh + 4.00 X 2 Bh = 55.40 M

24. Pek. Beton Balok = 0.59 M3


= Lbr X Tgg X Pjg Total
Balok B1 (Teras dan diatas Tembok Dpn) = 0.20 X 0.20 X 12.25 = 0.49 M3
Balok B2 (Balok diatas Pintu Utama) = 0.25 X 0.25 X 1.60 = 0.10 M3
0.59 M3
25. Pek. Bakesting Balok = 7.35 M2
Balok B1 (Teras dan diatas Tembok Dpn) = (Lbr + 2xTgg )X Pjg Total = (0.20 + 0.40) X 12.25 = 7.35 M2
Balok B2 (Balok diatas Pintu Utama) = (Lbr + 2xTgg )X Pjg Total = (0.25 + 0.50) X 1.60 = 1.20 M2
7.35 M2

Plasteran = - M2 = - M2
Acian = 7.35 M2 = 7.35 M2
Pengecatan Tembok Baru = 7.35 M2 = 7.35 M2

26. Pek. Pembesian Balok = 87.40 Kg


Balok B1 (Teras dan diatas Tembok Dpn)
Tulangan Pokok Dia 12 = Pjg 1 Tul. X Jml Tul. X Bj. = 12.25 X 6 Bh X 0.887 = 65.20 Kg
Dia 10 = Pjg 1 Tul. X Jml Tul. X Bj. = 12.25 X 0 Bh X 0.616 = - Kg
Tul. Sengkang Dia 6 = Pjg 1 Sengk. X Jml Sengk. X= 0.64 X 82.00 X 0.222 = 11.64 Kg
Balok B2 (Balok diatas Pintu Utama)
Tulangan Pokok Dia 12 = Pjg 1 Tul. X Jml Tul. X Bj. = 1.60 X 6 Bh X 0.887 = 8.52 Kg
Dia 10 = Pjg 1 Tul. X Jml Tul. X Bj. = 1.60 X 0 Bh X 0.616 = - Kg
Tul. Sengkang Dia 6 = Pjg 1 Sengk. X Jml Sengk. X= 0.84 X 11.00 X 0.222 = 2.05 Kg

87.40 Kg

27. Pek. Beton Ringbalk = 32.25 M


= 11.00 + 6.80 + 1.80 + 12.65 = 32.25
28. Pek. Balok Late = 32.88 M
Balok Late = 6.85 + 11.00 = 17.85 M
Balok diatas Kusen = 1.35 + 2.70 + 1.35 + 1.35 + 3.30 + 3.30 + 1.68 = 15.03 M
32.88 M

29. Pek. Beton Plat = 0.44 M3


Plat Diatas Kusen Pjg Pla = 1.35+1+1 = 3.35 M
= Pjg Plat X Lbr X Tbl = 3.35 X 0.40 X 0.08 = 0.11 M3
Plat diatas Papan Nama Teras = Pjg X Lbr X Tbl = 6.70 X 1.00 X 0.05 X 1 Bh = 0.34 M3
= 0.44 M3

30. Pek. Bakesting Plat 10cm = 15.77 M2


Plat Diatas Kusen = Pjg X Lbr + Pjg X Tbl = 3.35 X 0.40 + 3.35 X 0.08 = 1.61 M2 = 1.608 M2
Plat diatas Papan Nama Teras = (Pjg X Lbr X 2 Sisi + Tbl X Pjg ) X Jm= 6.70 X 1.00 X 2 Sisi + 0.05 X 15.40 X 1 Bh = 14.170 M2
15.78 M2
Plasteran = 15.78 M2 = 15.78 M2
Acian = 15.78 M2 = 15.78 M2
Pengecatan Tembok Baru = 15.78 M2 = 15.78 M2

31. Pek. Pembesian Plat = 43.64 Kg


Plat Diatas Kusen =
Arah Melintang Dia 10 = Pjg Tul. X Jml Tul. X BJ. Tu= 0.40 X 22 Bh X 0.616 = 5.42 Kg
Arah Memanjang Dia 10 = Pjg Tul. X Jml Tul. X BJ. Tu= 3.35 X 3 Bh X 0.616 = 6.19 Kg
Plat diatas Papan Nama Teras =
Arah Melintang Dia 10 = Pg Tul. X Jml Tul X Bj. Tul. X Jml = 1.00 X 45.00 X 0.616 X 1 Bh = 27.72 Kg
Arah Memanjang Dia 10 = Pjg Tul. X Jml Tul. X BJ. Tul X Jml T = 1.00 X 7.00 X 0.616 X 1 Bh = 4.31 Kg
43.64 Kg

32. Pek. Beton Plat 12 cm Pada Plat Ramp & Bordes = - -

33. Pek. Bakesting Plat 12 cm Pada Plat Ramp & Bordes = - -

Plasteran = Pjg Plat X Tbl Pla= - X - = - M2 = - M2


Acian = - M2 = - M2
Pengecatan Tembok Baru = - M2 = - M2

34. Pek. Pembesian Plat 12 cm Pada Plat Ramp & Bordes = - Kg


0 = Pjg Tul X Jml Tul. X Bj Tul.
Tulangan Lentur Arah Memanjang Dia 10 = - X - X 0.616 = - Kg
Tulangan Lentur Arah Melintang Dia 10 = - X - X 0.616 = - Kg
Tulangan Susut Arah Memanjang Dia 10 = - X - X 0.616 = - Kg
Tulangan Susut Arah Melintang Dia 10 = - X - X 0.616 = - Kg
0 = Pjg Tul X Jml Tul. X Bj Tul.
Tulangan Lentur Arah Memanjang Dia 10 = - X - X 0.616 = - Kg
Tulangan Lentur Arah Melintang Dia 10 = - X - X 0.616 = - Kg
Tulangan Susut Arah Memanjang Dia 10 = - X - X 0.616 = - Kg
Tulangan Susut Arah Melintang Dia 10 = - X - X 0.616 = - Kg
- Kg

35. Pek. Plat Lantai Bondek Tebal 12cm = - -


Luas =
=

=
Volume Plat Lantai =

36. Pek. Granit Lantai 60x60cm = 60.42 M2

Ruang Tindakan = 6.80 X 5.25 + 5.30 X 1.50 = 35.70 M2


Ruang Perawatan UGD = 5.15 X 1.50 + 2.50 X 6.80 = 24.73 M2

60.43 M2

37. Pas. Plint/list keramik ukuran 10cmx 60cm = - M2

38. Pas. Lantai Keramik Motif KM/WC = 3.64 M2


= Pjg X Lbr
KM/WC Ruang Tindakan = 1.35 X 1.35 = 1.82 M2
KM/WC Ruang Perawatan UGD = 1.35 X 1.35 = 1.82 M2

3.65 M2

39. Pas. Keramik Dinding ukuran 20x60cm (termasuk pada KM/WC) = 72.75 M2
KM/WC Ruang Tindakan = 2.70 X 1.50 + 2.70 X 1.50 - 1.00 X 1.50 = 6.60 M2
KM/WC Ruang Perawatan UGD = 2.70 X 1.50 + 2.70 X 1.50 - 1.00 X 1.50 = 6.60 M2
Ruang Tindakan = 13.60 X 1.50 + 13.70 X 1.50 - 1.00 X 1.50 - 3.80 X 1.50 = 33.75 M2
Ruang Perawatan UGD = 13.60 X 1.50 + 7.70 X 1.50 - 1.00 X 1.50 - 3.10 X 1.50 = 25.80 M2

72.75 M2
Pengurangan
Plasteran = - M2 = - M2
Acian = ### M2 = (72.75) M2
Pengecatan Tembok Baru = ### M2 = (72.75) M2

40. Pas. Dinding Batu Tempel Motif = - M2

41. Pas. Keramik Dinding Artistik motif Batu Alam = 6.75 M2


= 2.18 X 1.50 + 2.32 X 1.50 = 6.75 M2
Pengurangan
Plasteran = - - = - M2
Acian = (6.75) M2 = (6.75) M2
Pengecatan Tembok Baru = (6.75) M2 = (6.75) M2
42. Plesteran dinding Camp. 1Pc;3Ps, Tebal 15mm = - M2
Total = - M2
43. Plesteran dinding dan Beton Camp. 1Pc;5Ps, Tebal 15mm = 333.78 M2
Total Plasteran = ### M2
44. Acian PC. pada Dinding dan Beton = 295.43 M2
Total Acian = ### M2

45. Pasang Kusen Pintu dan Jendela Alumunium = 37.90 M


= Lbr X 1 Bh + Tgg X 2 Bh X Jml
Beton Pintu Utama (pintu Tempered Depan) P1 = (1.60 X 1 Bh + 2.05 X 2 Bh) X 0 Unit = - M
Pintu P2 = (1.70 X 1 Bh + 2.10 X 2 Bh) X 1 Unit = 5.90 M
Pintu P3 = (1.40 X 1 Bh + 2.10 - 2 Bh) X 1 Unit = 5.60 M
Pintu P4 (KM/WC) = (1.00 X 1 Bh + 1.85 - 2 Bh) X 2 Unit = 9.40 M
Jendela J1 = (1.05 X 3 Bh + 1.35 - 3 Bh) X 2 Unit = 14.40 M
Ventilasi KM/WC (V1) = (1.00 - 2 Bh + 0.30 - 2 Bh) X 1 Unit = 2.60 M

37.90 M

46. Pek. Kusen Kayu Kalas I = - M2

47. Pasang Daun Pintu Kaca Bening T= 8mm Rangka Alumunium = - M2

48. Pek. Pintu Double Kaca Tempret T= 12mm Lengkap dengan Handle dan Expanolet serta Kelengkapannya = 3.28 M2
= Pjg X Lbr
= 1.60 X 2.05 = 3.28 M2
49. Pek. Partisi Kaca Tempret T= 12mm = - M2
50. Pek. daun pintu panel kayu klas I = = 2.73 M2
Pintu P3 = 1.30 X 2.10 X 1 Unit = 2.73 M2

2.73 M2
51. Pek. Daun pintu plywood 4mm rangkap Lapis HPL , rangka kayu klas I tertutup (KM/WC) = 3.33 M2

Pintu P4 (KM/WC) = 0.90 X 1.85 X 2 Unit = 3.33 M2


3.33 M2
52. Pek. Daun pintu plywood 6mm rangkap Lapis HPL , rangka kayu klas I tertutup (lebar sampai 90cm) = 3.36 M2
Pintu P2 = 1.60 X 2.10 X 1 Unit = 3.36 M2
53. Pek. Jendela dan Fentilasi Casement Kaca Bening T=5mmRangka Alumunium(Lengkap dgn Asesoris) = 1.50 M2
Jendela J1 = 0.60 X 1.25 X 2 Unit = 1.50 M2
54. Pek. Daun Jendela Sliding Kaca Bening T=5mmRangka Alumunium(Lengkap dgn Asesoris) = - M2
55. Pek. Kaca Bening T= 5mm(Jendela Kaca Mati) = 0.75 M2
Jendela J1 = 1.25 X 0.30 X 2.00 = 0.75 M2
56. Pek. Kaca Bening T= 8 mm(Jendela Kaca Mati) = - -

57. Pengadaan dan Pemasangan Stiker Sanblast = 0.96 M2


Beton Pintu Utama (pintu Tempered Depan) P1 = 1.60 X 0.60 = 0.96 M2
58. Pengadaan dan Pemasangan Stiker One Way = - -

59. Pek. Grendel Pintu Tanam Pada Pintu Dobel = 1.00 Bh


Pintu P2 = - X 1.00 = - Bh
Pintu P3 = 1.00 X 1.00 = 1.00 Bh
1.00 Bh
60. Pek. Grendel Jendela = 4.00 Bh
Jendela J1 = 2 Bh X 2 Unit = 4.00 Bh
61. Pek. Haag Angin = 2.00 Bh
Jendela J1 = 1 Bh X 2.00 = 2.00 Bh
62. Pek. Pengadaan dan Pemasangan Kunci Pintu Kwalitas I 2 Slaag = 2.00 -
Pintu P2 = - X 1 Unit = - Bh
Pintu P3 = - X 1 Unit = - Bh
Pintu P4 (KM/WC) = 1.00 X 2 Unit = 2.00 Bh

2.00 -
63. Pek. Engsel Pintu Mutu Baik (Doors Hinge) setara Deksson = 12.00 Bh
Pintu P2 = 4.00 X 1 Unit = 4.00 Bh
Pintu P3 = 4.00 X 1 Unit = 4.00 Bh
Pintu P4 (KM/WC) = 2.00 X 2 Unit = 4.00 Bh

12.00 Bh
64. Pek. Engsel Jendela Mutu Baik (windows Hinge) = 4.00 Bh
Jendela J1 = 2 Bh X 2 Unit = 4.00 Bh
65. Pasang Kunci Silinder Pintu mutu baik pada Pintu Dobel = 1.00 Bh
Pintu P2 = - X 1.00 = - Bh
Pintu P3 = 1.00 X 1.00 = 1.00 Bh
1.00 Bh
66. Pengadaan Handel Pintu Panjang Minal 60cm = 1.00 Bh
Pintu P2 = 1.00 X 1.00 = 1.00 Bh
67. Pek. Rangka Atap Baja Ringan Profil "C", ukuran 75 x 35 x 0.75 mm dan Reng ukuran 0,45/16/31/11mm = 76.23 M2
Didapat Langsung dari Luas Pd GBr Sketchup = 11.55 X ### = 76.23 M2
68. Pek. Atap Zincalume (Spandek) T.0,40mm = 76.23 M2
= Pek. Rangka Atap Baja Ringan Profil "C", ukuran 75 x 35 x 0.75 mm dan Reng = 76.23 M2
69. Pek. Listplank (Kalciplank) = 6.95 M
= 6.95 M
70. Pek. Rangka Langit-Langit/Plafon Besi Holow 40/40mm& 40/20 mm, Modul 60/60cm = 64.06 M2
= Volume Granit Lantai + Keramik Lant = 60.42 + 3.64 = 64.06 M2

Tritisan = = = - M2
64.06 M2
71. Pek. Langit-Langgit / Plafon Kalsiboard 3,5 mm = 64.06 M2
= Pek. Rangka Langit-Langit/Plafon Besi Holow 40/40mm& 40/20 mm, = 64.06 M2
72. Pek. List Plafond GypsumProfil C-7 = - M
Ruang Tindakan = 6.80 X 2.00 + 6.85 X 2.00 = 27.30 M
Ruang Perawatan UGD = 3.85 X 2.00 + 6.80 X 2.00 = 21.30 M
KM/WC Ruang Tindakan = 1.35 X 2.00 + 1.35 X 2.00 = 5.40 M
KM/WC Ruang Perawatan UGD = 1.35 X 2.00 + 1.35 X 2.00 = 5.40 M
59.40 M
73. Pek. Instalasi Listrik (Titik Lampu) dengan Kabel NYA 3X2.5mm = 7.00
74. Pek. Lampu Downlight ex. Philips 4" + lampu 18 Watt = 4.00
75. Pek. Lampu Downlight ex. Philips 4" + lampu 11 Watt = 2.00
76. Pek. Fitting Tanam + Lampu ex. Philips 18 Watt = 1.00
77. Pek. Pengadaan Dan Pemasangan Saklar Dobel Panasonic = 2.00
78. Pek. Pengadaan Dan Pemasangan Saklar Tunggal = 3.00
79. Pek. Pengadaan Dan Pemasangan Stop Kontak = 4.00
80. Pek. AC 1 PK Termasuk MCB = -
81. Pek. MCB Untuk Persiapan AC = -
82. Pek. Zakering Box 3 Group = -
83. Pek. Panel Induk = -
84. Pek. Exhaust Fan 6" ex. PANASONIC KM/WC = 1.00
85. Pek. Kabel Inlet Panel NYA 1x 16 mm (Pengadaan + Biaya Pasang) =
86. Pek. Kabel Outlet Panel 1X10 mm (Pengadaan + Biaya Pasang) = -
87. Pek. Penambahan Daya dari 7,700 Volt Menjadi 23,000 Volt pada PLN = - Pkt
88. Pek. Pengadaan dan Pemasangan Closed Duduk Kwalitas I (Merk Toto) = 2.00 Bh
74. Pek. Pengadaan dan Pemasangan Closed Jongkok Kwalitas I = - Bh
75. Pasang Wasthafel Model Kotak Merk Toto lengkap dengan Kran Air = 2.00 Unit

76. Pengadaan dan Pemasangan bak cuci piring stainlessteel + Acc + Kran = 1.00 Bh

77. Pasang Pipa PVCØ 4" type D& Accessories (dari Klosed) = - M

78. Pasang Pipa PVCØ 3" type D& Accessories (dari Klosed) = 18.20 M

79. Pasang Pipa PVCØ 2" type AW& Accessories (Air Kotor) = 18.45 M

80. Pasang Pipa GI Medium Ø 1 1/4" & Accessories (Dari Tandon Air) = - M

81. Pasang Pipa PVCØ 1/2" type AW& Accessories (yg Menuju Kran Air) = 16.55 M

82. Pasang Pipa PVCØ 1" type AW& Accessories (Pembagi Air Bersih dari Tandon) = 13.26 M

83. Pasang Pipa PVCØ 3/4" type AW& Accessories (Distribusi Air Bersih) = - M

84. Pek. Pengeboran Air Tanah Dangkal Min 30m = - Bh

85. Pek. Pengadaan dan Pemasangan Pompa Air Jenis Jetpam = - Bh

86. Pengadaan Ember Besar + Gayung = 2.00 Pkt

87. Pasang Kran air Besi (ex Taho) Ø ½" dan Accessories = 2.00 Bh

88. Pasang Saringan air (Avour) Besi (Stainles) = 2.00 Bh

89. Pembuatan Septiptank dan Sumur Peresapan (Lengkap) Kapasitas 2,00 m3 = 1.00 Unit

90. Pek. Pipa Pegangan Stainless (Handle Grib) Ø 1.5" Panjang 100cm pada KM/WC Pasien (Harga + Biaya Pasang) = 6.00 Bh

91. Pek. Pengadaan Dan Pemasangan Tandon Air MPOIN PLUS L SNI 2400 Liter (Anti Lumut), lengkap dengan Accessories (input 1 1/2" Output 1 1/2") (Harga + Biaya Pasang = - Unit

92. Pengecatan Tembok dengan Cat Tembok Mutu Baik yang mengandung Acrelic Merk Nippon Paint = 295.42 M2
Total ecatan Tembok Baru = ### M2
93. Pek. Plafond dengan Cat Tembok Mutu Baik yang mengandung Acrelic Merk Nippon Paint = 64.06 M2
= Volume Plafond = 64.06 M2
94. Pengecatan Baja IWF dengan Cat Anti Karat = - M2
= Pada BOQ Baja
95. Pek. Pengecatan/Polituran Daun Pintu dan Kusen Kayu = 5.46 M2
Beton Pintu Utama (pintu Tempered Depan) P1 =
Pintu P2 = Luas Pintu X 2 Si = - X 2 Sisi = - M2
Pintu P3 = Luas Pintu X 2 Si = 2.73 X 2 Sisi = 5.46 M2
Pintu P4 (KM/WC) = Luas Pintu X 2 Sisi - X 2 Sisi = - M2
Jendela J1 = Luas Pintu X 2 Sisi - X 2 Sisi = - M2
0 = = - M2
5.46 M2

96. Pek. Pengecatan Batu Alam = - M2


97. Pelapisan Waterprofing atap beton / Pelat Dak = - M2
98. Pengacatan Tembok dengan Cat KCA (Cat Textur Pasir) Termasuk Pengecatan Dasar = - M2
Pada Papan Nama Ruang Perawatan = = - M2
99. Pek. ACP Exterior 4mm rangka Konstruksi Pipa Kotak = - M2
= = - M2
100. Pek. Pengadaan dan Pemasangan Atap Kaca Tempered Clear 5 mm + PVB Clear 0.38mm + Kaca Tempered Clear 5 mm (Tebal Total 10.38mm) pada Teras Termasuk Aseso = - M2
101. Pek. Leter Nama dari Acrilic 5MM = 0.84 M2
= 0.30 X 2.80 + - X - = 0.84 M2
BOQ RUANG PERAWATAN PUSKESMAS RASANAE TIMUR LT.1
No URAIAN PEKERJAAN VOLUME
1. Pek. Pengukuran, Pematokan, dan Pemasangan Bauplank - M
2. Pek. Galian Tanah FootPlate Menggunakan Alat Berat - M3
3. Pek. Galian Tanah Menggunakan Tenaga Manusia - M3
4. Urugan Kembali Tanah Hasil Gali - M3
5. Urugan Tanah Pilihan Peninggian Lantai - M3
6. Pek. Urugan Pasir dibawah Pondasi dan Lantai - M3
7. Pek. Pasangan Batu Kosong - M3
8. Pek. Pondasi Pas. Batu - M3
9. Pek. Pasangan Dinding 1/2 bata camp. 1pc:5ps 159.81 M2
10. Pek. Rabbat Keliling Bangunan - M3
11. Pek. Rabbat dibawah Lantai - M3
12. Pek. Rabbat dibawah Footplate - M3
13. Pek. Beton Pondasi Footplate - M3
14. Pek. Bakesting Pondasi Footplate - M2
15. Pek. Pembesian Footplate
16. Pek. Beton Sloof - M3
17. Pek. Bakesting Sloof - M2
18. Pek. Pembesian Sloof - Kg
19. Pek. Beton Kolom 8.84 M3
20. Pek. Bakesting Kolom 101.08 M2
21. Pek. Pembesian Kolom 159.23 Kg
22. Pek. Beton K.125 Pembungkus Kolom Baja - M3
23. Pek. Kolom Praktis 18.00 M
24. Pek. Beton Balok 2.26 M3
25. Pek. Bakesting Balok 41.58 M2
26. Pek. Pembesian Balok 537.22 Kg
27. Pek. Beton Ringbalk 52.27 M
28. Pek. Balok Late 3.20 M
29. Pek. Beton Plat 8cm 1.50 M3
30. Pek. Bakesting Plat 10 cm 20.51 M2
31. Pek. Pembesian Plat 10 cm 149.18 Kg
32. Pek. Beton Plat 12 cm Pada Plat Ramp & Bordes - -
33. Pek. Bakesting Plat 12 cm Pada Plat Ramp & Bordes - M2
34. Pek. Pembesian Plat 12 cm Pada Plat Ramp & Bordes - Kg
35. Pek. Plat Lantai Bondek Tebal 12cm - M3
36. Pek. Granit Lantai 60x60cm 131.35 M2
37. Pas. Plint/list keramik ukuran 10cmx 60cm - M2
38. Pas. Lantai Keramik Motif KM/WC 5.12 M2
39. Pas. Keramik Dinding ukuran 20x60cm (termasuk pada KM/ 17.04 M2
40. Pas. Dinding Batu Tempel Motif - M2
41. Pas. Keramik Dinding Artistik motif Batu Alam - M2
42. Plesteran dinding Camp. 1Pc;3Ps, Tebal 15mm - M2
43. Plesteran dinding dan Beton Camp. 1Pc;5Ps, Tebal 15mm 337.35 M2
44. Acian PC. pada Dinding dan Beton 485.92 M2
45. Pasang Kusen Pintu dan Jendela Alumunium 219.60 M
46. Pek. Kusen Kayu Kalas I - M2
47. Pasang Daun Pintu Kaca Bening T= 8mm Rangka Alumunium - M2
48. Pek. Pintu Double Kaca Tempret T= 12mm Lengkap dengan Ha - M2
49. Pek. Partisi Kaca Tempret T= 12mm
50. Pek. daun pintu panel kayu klas I 1.89 M2
51. Pek. Daun pintu plywood 4mm rangkap Lapis HPL , rangka kay 2.10 M2
52. Pek. Daun pintu plywood 6mm rangkap Lapis HPL , rangka kayu - M2
53. Pek. Jendela dan Fentilasi Casement Kaca Bening T=5mmRang 14.99 M2
54. Pek. Daun Jendela Sliding Kaca Bening T=5mmRangka Alumun - M2
55. Pek. Kaca Bening T= 5mm(Jendela Kaca Mati) 14.45 M2
56. Pek. Kaca Bening T= 8 mm(Jendela Kaca Mati) - M2
57. Pengadaan dan Pemasangan Stiker Sanblast - M2
58. Pengadaan dan Pemasangan Stiker One Way - M2
59. Pek. Grendel Pintu Tanam Pada Pintu Dobel - Bh
60. Pek. Grendel Jendela 10.00 Bh
61. Pek. Haag Angin 10.00 Bh
62. Pek. Pengadaan dan Pemasangan Kunci Pintu Kwalitas I 2 Slaa 5.00 Bh
63. Pek. Engsel Pintu Mutu Baik (Doors Hinge) setara Deksson 9.00 Bh
64. Pek. Engsel Jendela Mutu Baik (windows Hinge) 24.00 Bh
65. Pasang Kunci Silinder Pintu mutu baik pada Pintu Dobel - Bh
66. Pengadaan Handel Pintu Panjang Minal 60cm - Bh
67. Pek. Rangka Atap Baja Ringan Profil "C", ukuran 75 x 35 x 0 233.68 M2
68. Pek. Atap Zincalume (Spandek) T.0,40mm 233.68 M2
69. Pek. Listplank (Kalciplank) 57.68 M2
70. Pek. Rangka Langit-Langit/Plafon Besi Holow 40/40mm& 40/ 189.35 M2
71. Pek. Langit-Langgit / Plafon Kalsiboard 3,5 mm 189.35 M2
72. Pek. List Plafond GypsumProfil C-7 - M
73. Pek. Instalasi Listrik (Titik Lampu) dengan Kabel NYA 3X2.5m 23.00 -
74. Pek. Lampu Downlight ex. Philips 4" + lampu 18 Watt 13.00 -

75. Pek. Lampu Downlight ex. Philips 4" + lampu 11 Watt 3.00 -
76. Pek. Fitting Tanam + Lampu ex. Philips 18 Watt -
76. Pek. Pengadaan Dan Pemasangan Saklar Dobel Panasonic 4.00 -

77. Pek. Pengadaan Dan Pemasangan Saklar Tunggal 3.00 -

78. Pek. Pengadaan Dan Pemasangan Stop Kontak 5.00 -

79. Pek. AC 1 PK Termasuk MCB - -

80. Pek. MCB Untuk Persiapan AC 3.00 -

81. Pek. Zakering Box 3 Group 1.00 -

82. Pek. Panel Induk 1.00 -

83. Pek. Exhaust Fan 6" ex. PANASONIC KM/WC 1.00 -

84. Pek. Kabel Inlet Panel NYA 1x 16 mm (Pengadaan + Biaya Pasa 70.00 -

85. Pek. Kabel Outlet Panel 1X10 mm (Pengadaan + Biaya Pasang) 70.00 -

86. Pek. Penambahan Daya dari 7,700 Volt Menjadi 23,000 Volt p - Pkt
73. Pek. Pengadaan dan Pemasangan Closed Duduk Kwalitas I (Mer 2.00 Bh
74. Pek. Pengadaan dan Pemasangan Closed Jongkok Kwalitas I - Bh

75. Pasang Wasthafel Model Kotak Merk Toto lengkap dengan Kra 2.00 Unit

76. Pengadaan dan Pemasangan bak cuci piring stainlessteel + Acc - Bh

77. Pasang Pipa PVCØ 4" type D& Accessories (dari Klosed) - M

78. Pasang Pipa PVCØ 3" type D& Accessories (dari Klosed) 27.37 M

79. Pasang Pipa PVCØ 2" type AW& Accessories (Air Kotor) 26.57 M

80. Pasang Pipa GI Medium Ø 1 1/4" & Accessories (Dari Tandon A 5.66 M

81. Pasang Pipa PVCØ 1/2" type AW& Accessories (yg Menuju Kran 7.60 M

82. Pasang Pipa PVCØ 1" type AW& Accessories (Pembagi Air Bersi 29.29 Bh

83. Pasang Pipa PVCØ 3/4" type AW& Accessories (Distribusi Air Be - M

84. Pek. Pengeboran Air Tanah Dangkal Min 30m - PKT

85. Pek. Pengadaan dan Pemasangan Pompa Air Jenis Jetpam 1.00 Bh

86. Pengadaan Ember Besar + Gayung 2.00 Pkt

87. Pasang Kran air Besi (ex Taho) Ø ½" dan Accessories 2.00 Bh

88. Pasang Saringan air (Avour) Besi (Stainles) 2.00 Bh

89. Pembuatan Septiptank dan Sumur Peresapan (Lengkap) Kapasi - Unit

90. Pek. Pipa Pegangan Stainless (Handle Grib) Ø 1.5" Panjang 1 - Bh

91. Pek. Pengadaan Dan Pemasangan Tandon Air MPOIN PLUS L SNI 2 - Unit

92. Pengecatan Tembok dengan Cat Tembok Mutu Baik yang menga 485.92 M2

93. Pek. Plafond dengan Cat Tembok Mutu Baik yang mengandung 189.35 M2

94. Pengecatan Baja IWF dengan Cat Anti Karat - M2

95. Pek. Pengecatan/Polituran Daun Pintu dan Kusen Kayu 3.78 M2


96. Pek. Pengecatan Batu Alam - M2
97. Pelapisan Waterprofing atap beton / Pelat Dak - M2
98. Pengacatan Tembok dengan Cat KCA (Cat Textur Pasir) Terma 13.87 M2
99. Pek. ACP Exterior 4mm rangka Konstruksi Pipa Kotak - M2
100. Pek. Pengadaan dan Pemasangan Atap Kaca Tempered Clear 5 - M2
101. Pek. Leter Nama dari Acrilic 5MM 1.18 M2

You might also like