Professional Documents
Culture Documents
1705135 03
1705135 03
1705135 03
Unit arrangement
All installation measurements apply to finished wall/floor/ceiling and are to be checked prior to assembling the unit.
700 cm mm
324 376
781
Orientation point = reference point of the Siemens unit for planning and installation
Battery
UPS 1.29 General remarks
1.28 1.31 1.32 t = 20
Floor stand
200
The preinstallation parts are part of the preinstallation shipment.
Equipment Room
The preinstallation kit contains the mounting plate with installation hardware, as well as the ceiling outlet.
785
The installation gauge, Part No.65 72 627 G144E, is required for installation of the floor stand and patient
table mounting plates.
A 1 Patient table
The preinstallation parts are part of the preinstallation shipment.
The pre-installation parts include the installation plate and the mounting materials
Pre-installation in computer flooring
Recommendation: Floor stand installation plate on filled concrete or on the on-site substructure.
1.06 Patient table tension loads
A 1 3 Mounting plate on concrete fill-up.
Foot-end load per installation plate mounting point: max. tensile force 4.5 kN.
130
1.02 The two mounting plates for the stand and patient table must be installed on a solid base that has sufficient load
capacity. Cut away the floor covering. If necessary, any material in the location of the mounting plates that does
545
not have the required load capacity must be replaced with filled concrete.
4 For fixing purposes Hilti heavy-duty expansion anchors are supplied.
1.04 The minimum degree of firmness of the concrete is C 20/25 according to DIN 1045-1 for solid concrete If required,
1.05 the plates can be fixed with on-site threaded bolts through the solid concrete according to DIN 976-1-M12-8.8.
Examination Room If mounting using the Hilti floor anchors that are provided is not possible because of the floor conditions, other floor
509 anchors can also be used. These must have the same or better specifications (e.g. max. admissible pull forces) as
1 L-M the Hilti floor anchors that are provided.
459
229 Z
L M Center of gravity of the patient table
t=15 2
(not to scale)
1 Movement of center of gravity
434
1.18
Z 1:1
484
1.13 1.18d 2 Center of gravity, table rotated 120°
6 1
1.18c
1.17 1.10 3 Orientation point / center of rotation
5
218
1.18b 1.12 120°
1.15 1.09a 1.16 2 4 Center of gravity, table rotated -120°
1.11
Control Room 1 *1
Ø20.5 7 2 5 Center of gravity, table in 0° position
3
179
4
62
500
420 6
Mounting plate patient table 1:10
Equipment 1 3 509
300 1 Z L-0
Room 459 2
min. 195
max. 70
5 229
3
12.2 Pb 2mm Lead lining for all walls,frames and doors
100 in accordance to the national regulation up to 220 cm. L M
200
t=15
4
min. 160
4
434
2
484
Examination ≥ 355 N O
Room Z 1:2 5 6
≤ 780
219
7
□900
50 40
Ø20.5 8
35
1 Screed 2 Insulation
20
90
Pb. Option: Injector floor outlet. Area in which the outlet is installed.
3
Pb. Please note the instructions given by the manufacturer. 3 Concrete-fill-up 4 Solid concrete min. C20/25
35
4 Outlet centered to the table longitudinal axis 5 Head side 5 Insulating parts 6 Mounting plate
90 152
Equipment 6 In this area a minimum cable duct height of 7cm to ensure that the table cable is not bent too much. 7 Seal continously with hygienic-grade silicone 8 Floor covering
Room
An injector cable may not be pulled through the table base. It is absolutely necessary to route the When assembling of the plate on concrete fill-up the provided Hilti heavy-duty expansion anchors
injector cable (control cable between table stand and injector control) via the floor outlet. HSL-3-G M12/100 are to be used. Please note the instructions given by the manufacturer.
Load on each mounting point at the table foot end max. tensile force equaling 4.5 kN
99
15.5 L M
2 correct operation.
Control t=15 This plan is not a construction drawing and is not to be used for carrying out construction work.
min. 160
Room
Control
88
434
13
Z 1:2
5 Siemens Healthcare GmbH
Planning department
Hartmannstrasse 16
Ø20.5 6 D-91052 Erlangen