Professional Documents
Culture Documents
ACA Asset Condition Operations Guide v1.0
ACA Asset Condition Operations Guide v1.0
Version History
Table of Contents
1 Introduction ..................................................................................................................................................6
1.1 Background ..........................................................................................................................................6
1.2 Purpose ................................................................................................................................................6
1.3 Reasonable Adoption ...........................................................................................................................6
1.4 Change Management ...........................................................................................................................6
3 Document Structure.....................................................................................................................................7
3.1 General Guidelines (Section 4) ............................................................................................................7
3.2 Asset Subclass Specific Guidelines (Section 5) ..................................................................................7
3.3 Technical Performance Measures Library (Section 6) .........................................................................7
4 General Guidelines for all Asset Subclasses ..............................................................................................8
4.1 Work Health & Safety ...........................................................................................................................8
4.2 Qualifications ........................................................................................................................................8
4.3 Condition Assessment Process ...........................................................................................................8
4.4 General TPM Definitions & Process Guidance ................................................................................. 11
4.5 Undertaking the ACA Analysis Requirements .................................................................................. 12
5 Asset Subclass Specific Guidelines ......................................................................................................... 40
5.1 IS-001 Buildings ................................................................................................................................ 40
5.2 IS-003 Tram Track ............................................................................................................................ 64
5.3 IS-004 Tram Overhead Wiring .......................................................................................................... 70
5.4 IS-010 Bridges, Subways & Culverts ................................................................................................ 73
5.5 IS-025 Platforms................................................................................................................................ 83
5.6 IS-029 Lifts & Escalators ................................................................................................................... 97
5.7 IS-030 Fire Hydrants & Pump Systems .......................................................................................... 101
5.8 IS-032 Retaining Walls .................................................................................................................... 102
5.9 IS-035 Buffer Stops ......................................................................................................................... 111
5.10 IS-039 At Grade Carparks ........................................................................................................... 112
5.11 IS-041 OHWS, Attachments & Signal Gantries ........................................................................... 113
5.12 IS-042 Poles ................................................................................................................................ 114
5.13 IS-050 Level Crossings & Protection ........................................................................................... 117
5.14 IS-051 Drainage .......................................................................................................................... 125
5.15 IS-053 Embankments and Cuttings ............................................................................................. 127
5.16 IS-058 Signals ............................................................................................................................. 128
5.17 IS-061 Power Supply & Signalling Enclosures ............................................................................ 131
5.18 IS-063 Signal Points – Manual & Spring Loaded ........................................................................ 132
5.19 IS-064 Signal Points – Powered Machines ................................................................................. 136
5.20 IS-065 Signal Points – Point Controller ....................................................................................... 140
5.21 IS-067 Switches ........................................................................................................................... 142
5.22 IS-068 Section Insulators ............................................................................................................ 143
5.23 IS-069 Earthing & Bonding .......................................................................................................... 144
5.24 IS-071 HV AC Switchgear ........................................................................................................... 146
4
1 Introduction
1.1 Background
The Asset Condition Assessment (ACA) process captured within this document is to deliver a
consistent assessment of the condition of the assets within the metropolitan rail networks of Victoria. It
builds upon the work of the Asset Condition Assessment Project (ACAP), describing the requirements
for the capture of asset condition data to the Franchisees. Upon collection of this asset condition data,
analysis will be required against a series of condition scores, which will be reported to the Department
of Transport and Planning (DTP) on an agreed periodical basis.
The ACA process identifies the key life-defining performance requirements of a system, capturing the
physical defects, supportability, regulatory and overall system performance issues. These issues may
generate the requirement for renewal by means of non-routine major overhaul, system replacement or
extraordinary intervention, and require future capital expenditure. Within this framework, this is
referred to as “renewals”, as opposed to “operational maintenance” which represent the ongoing and
routine efforts to retain assets in a serviceable condition. These renewals are generally outside the
scope of Franchisee maintenance activities (except possible inspections/checks) and occur only rarely
or not at all within a single franchisee period.
1.2 Purpose
The purpose of the Asset Condition Operations Guide (ACOG) is to provide context and guidance in
implementing the ACA Minimum Data Requirements (MDR).
The information in this document should be taken as a guide on the potential processes and
methodologies which can be used; but not considered to be the only method in which the required
data can be acquired and analysed. Alternative methodologies, such as the technologies used to
capture the data, are encouraged to take into account evolving best practices and alignment with any
established processes that Franchisees may have in order to provide the required data as specified
within the MDR.
3 Document Structure
This document has three main sections that act as a guide to support the MDR document, the General
Guidelines, the Asset Subclass Specific Guidelines and the Technical Performance Measures Library.
4.2 Qualifications
It is expected that all personnel carrying out work in relation to the collection and analysis of data are
appropriately qualified for the task. The required qualifications are to be identified by the Franchisees.
Start
Detail of each step of this process is contained within the following table:
Table 4-1: General Condition Assessment Process Description
Step Description
1. Complete pre- This may include activities such as:
assessment checks • Completing pre-work documentation
• Completing all WHS/OHS related activities (i.e.: Safe Work Method
Statement (SWMS))
• Confirming that personnel conducting the activity have the
appropriate skills
• Confirming that all equipment, tools & PPE are available
• Ensuring all documentation in regards to the required checks and
assets are available
• Obtaining pre-analysis or data required for the task.
2. Check Section 4 for Check the “Condition Assessment Process” section of the Asset Subclass
Asset Subclass Specific Guideline and follow any specific instructions (if applicable)
specific condition relating to the Asset Subclass in addition to this general guidance.
assessment process
requirements
10
3. Determine Asset Refer to the MDR for the required data inputs and subsequent analysis for
Subclass data input the Asset Subclass under consideration.
and analysis
requirements
4. Collate data & Collate the data depending on the type of analysis that is required by the
Quality Assurance Asset Subclass.
(QA) Physical (Defect Assessment)
A physical defect assessment is carried out to identify potential defects
and failure modes on an asset which may require intervention or lead to
degradation of the functionality of the asset.
During the conduct of an inspection and recording information, the
following actions should be taken:
• Documenting any limitations of recording information (i.e. Inability to
access all elements/components of a system).
• Identifying all defects on the assets.
• Referring to the necessary TPMs for guidance on measuring and
recording defects.
• Making sure measurements where required are to an appropriate
level of accuracy (and record the devices used to make the
measurement).
• Taking photographs the overall asset/element/component as well
as closeups of any identified defects to clearly identify the location
of a defect on the asset/element/component.
• Assessing defects according to defect condition ratings where
applicable.
• Updating the element/component model is where applicable.
Supportability Analysis
A supportability analysis is undertaken for assets that have been identified
as having dependence on external support or specialist skill sets. This
represents an assessment of the level of obsolescence exhibited by an
asset. The following general steps should be followed to collate the data
for a supportability assessment.
• Identify the grouping at which the analysis will be performed.
• Identify and obtain a copy of the required questionnaire (refer to
MDR).
• Ensure access to relevant information on the asset (supply
contracts, supplier/OEM information, etc).
System Performance Analysis
A system performance analysis is based on an assessment of historical
failure data to determine if the system is degrading over time.
The following general steps should be followed to collate the data required
for assessment.
• Identify the grouping at which the analysis will be performed.
• Collect all available historic failure data relevant to the method of
failure analysis specified for the Asset Subclass in the MDR.
Regulatory Analysis
A regulatory analysis is based on compliance to specific regulation which
may be applicable to the Asset Subclass (such as compliance to DSAPT
requirements). Noting the variability in regulatory requirements, no general
guidance can be provided. Consult the respective sections within the
Asset Subclass in the MDR for specific guidance on collating data for
regulatory analysis.
5. Undertake analysis Refer to the MDR for the relevant analysis methodology that is required to
requirements for Asset be followed and calculated for the Asset Subclass. Where the Franchisee
Subclass has an alternative methodology, this is to be discussed with DTP for
consideration.
6. Verify and Submit Franchisee to perform final checks on data and analysis undertaken and
then submit to DTP as per the data transfer requirements outlined within
the MDR.
11
Further defect specific TPM processes relating to Asset Subclasses have been collated in section 6 as
an overall TPM library. The TPM library is called out by the individual Asset Subclasses as required for
defects relevant to that Asset Subclass.
These are to be read in conjunction with the measurements, measurement accuracy (and devices),
and measurement units outlined in MDR.
12
Identify the asset; then populate & verify the asset attributes as per Section 4.3 of the MDR.
This results in the following asset attributes being recorded and verified:
Table 4-3: Worked Example – Pole Asset Attributes to be recorded
Attribute Name Value
Location (-37.776941, 144.997463)
ACA Asset Subclass Poles
ACA Asset Type Poles
Construction date 01/01/1965
Asset ID 1001
DTP Asset ID 300001
Franchisee Tram
Table 4-4: Worked Example – Pole Asset Attributes to be verified
Attribute Name Value
Structure Type Steel
Pole Number 66
Step 2:
Step 3:
Rating (DCRraw)
Criterion (RMC)
Renewal Mode
Criticality (CC)
Measurement
Measurement
Component
Uncertainty
TPM Units
Approach
Condition
Defect Type
Component
Defect
TPM
Asset Sub
Defect ID
Asset ID
Class ID
Step 4:
The steps required to calculate the ACR for a Simple Asset are as per the following steps from the
MDR:
1. Assign the Defect Condition Rating (DCRraw) as per the guidelines for the Asset Subclass
2. Adjust the DCRraw for Component Criticality (CC) as follows:
0 , 𝐶𝐶 < 3
Equation 1: 𝐷𝐶𝑅𝑐𝑐 = {
𝐷𝐶𝑅𝑟𝑎𝑤 + 1, 𝐶𝐶 ≥ 3
Note: for Asset Subclasses with no criticality ratings, DCR CC = DCRraw +1
3. Adjust DCRCC based on the RMC (See table in Section 4.4 of the MDR) to obtain DCRadjust
4. Repeat the above steps for each defect.
5. Calculate the ACR:
Equation 2: 𝐴𝐶𝑅𝑆𝐼𝑀𝑃𝐿𝐸 = max(𝐷𝐶𝑅𝑎𝑑𝑗𝑢𝑠𝑡 )
The ACR is then the maximum of DCRadjust which for this example is equal to 4.
4.5.1.2 Example 2: Complex Asset with Construction Element Definition - Buildings (IS-001)
This example is for a station building of timber construction with a metal sheeting roof. It is inspected
against the requirements of IS-001. The requirements of the MDR requires the following steps:
Step 1:
Identify the asset; then populate & verify the asset attributes as per Section 4.3 of the MDR.
This results in the following asset attributes being recorded & verified:
14
Identify Simple or Complex Asset as per IS-001 in the MDR. If Complex – identify element
definition.
It has been identified that Buildings are to be analysed as a “Complex” asset and the required element
definition is “Construction”.
This requires an element model to be created for the building following the guidance within IS-001:
Table 4-9: Worked Example – Building Element definition breakdown
Element Constituent Element Number
External Wall Each Wall 4
Concourse Each Area 2
Floor Each Floor 1
Foundations n/a 1
Freestanding Walls Each wall 0
Internal Elements Each room 3
Roofing and Canopy Each roof structure 2
Miscellaneous Each item 0
The element attributes are then also recorded as per Section 4.3 of the MDR.
Table 4-10: Worked Example – Building Element Attributes
Asset Element Element Element Constructio Constructio Start Node End Node Length
ID ID Name Type n Date n Material (m)
1002566 23001 Wall 1 Walls 1965 Timber (-37.776941, (-37.776941, 10
144.997463) 144.997473)
1002566 23002 Wall 2 Walls 1965 Timber (-37.776941, (-37.776961, 20
144.997473) 144.997473)
1002566 23003 Wall 3 Walls 1965 Timber (-37.776961, (-37.776941, 10
144.997473) 144.997463)
1002566 23004 Wall 4 Walls 1965 Timber (-37.776941, (-37.776941, 20
144.997463) 144.997463)
1002566 23005 Concourse 1 Concourse 1965 Timber (-37.776941,
144.997463)
1002566 23006 Concourse 2 Concourse 1965 Timber (-37.776941,
144.997463)
1002566 23007 Floor 1 Floors 1965 Concrete (-37.776941,
144.997463)
1002566 23008 Floor 2 Floors 1965 Concrete (-37.776941,
144.997463)
1002566 23009 Foundation Foundations 1965 Concrete (-37.776941,
144.997463)
1002566 23010 Room 1 Internal 1965 Timber (-37.776941,
Elements 144.997463)
1002566 23011 Room 2 Internal 1965 Timber (-37.776941,
Elements 144.997463)
1002566 23012 Roof 1 Roofing and 1965 Steel (-37.776941,
Canopy 144.997463)
15
Step 3:
Identify and record defects – noting complex asset with a construction element definition
For each element identified in the previous table, inspect for defects:
• Conduct the physical inspection and identify defect type in line with guidance in IS-001 of the
MDR
• Identify component type (on which the defect is identified) as per the matrix provided in IS-001
of the MDR.
• Identify Component Criticality (CC) as per Section 4.4 of the MDR.
• Measure defects as per Section 4.4 & IS-001 of the MDR.
o Assign DCR to defect (and TPM where applicable)
o Record measurement approach and assign uncertainty
o Assign Renewal Mode Criteria
o Where the element(s) could not be inspected this should be noted. In this worked example,
all elements were inspected.
Criterion (RMC)
Renewal Mode
Criticality (CC)
Measurement
Measurement
Component
Uncertainty
TPM Units
Element Name
Approach
TPM
Defect Type
Component
Defect ID
Asset ID
Defect Condition
Rating (DCRraw)
Criterion (RMC)
Renewal Mode
Criticality (CC)
Measurement
Measurement
Component
Uncertainty
TPM Units
Element Name
Approach
TPM
Defect Type
Component
Defect ID
Asset ID
Step 4:
The steps required to calculate the ACR for a Complex Asset with Construction Element definition
from the MDR is as follows:
1. Assign the Defect Condition Rating (DCRraw) as per the guidelines for the Asset Subclass.
2. Adjust the DCRraw for CC as follows:
𝐷𝐶𝑅𝑟𝑎𝑤 , 𝐶𝐶 < 3
Equation 3: 𝐷𝐶𝑅𝑐𝑐 = {
𝐷𝐶𝑅𝑟𝑎𝑤 + 1, 𝐶𝐶 ≥ 3
Note: If DCRraw was originally 4, no adjustment is needed as the maximum value of DCR CC is 4.
3. Adjust DCRCC based on the RMC (See table in Section 4.4 of the MDR) to obtain DCRadjust.
4. Repeat the above steps for each defect identified for the element.
See Table 4-12 for the results of this exercise.
8. For all elements which could not be inspected, the AECR for these elements are to be set to -1
and not considered in the calculation of ACR.
9. Plot a cumulative distribution function (CDF) for all the AECR values.
10. Take the 80%tile AECR value as the Asset AECR as per
11. Convert to ACR for the asset as follows:
Equation 5: 𝐴𝐶𝑅 = 𝐴𝐸𝐶𝑅80% + 1
See Table 4-13 for the summary of the AECRs for the elements and the CDF calculation which
shows an overall outcome of ACR = 2 for this Asset.
Table 4-13: Worked Example – Building Asset AECR Calculation and ACR Rollup
Element Element Element Max AECR AECR AECR AECR AECR AECR
ID Type DCR 0 1 2 3 4
23001 Walls Wall 1 2 2 0 0 1 0 0
23002 Walls Wall 2 2 2 0 0 1 0 0
23003 Walls Wall 3 1 1 0 1 0 0 0
23004 Walls Wall 4 1 1 0 1 0 0 0
23005 Concourse Concourse 1 0 0 1 0 0 0 0
18
Element Element Element Max AECR AECR AECR AECR AECR AECR
ID Type DCR 0 1 2 3 4
23006 Concourse Concourse 2 0 0 1 0 0 0 0
23007 Floors Floor 1 0 0 1 0 0 0 0
23008 Floors Floor 2 0 0 1 0 0 0 0
23009 Foundations Foundation 0 0 1 0 0 0 0
23010 Internal Room 1 0 0 1 0 0 0 0
Elements
23011 Internal Room 2 0 0 1 0 0 0 0
Elements
23012 Roofing and Roof 1 2 2 0 0 1 0 0
Canopy
4.5.1.3 Example 3: Complex Asset with Linear Element Definition – Retaining Walls (IS-032)
This example is for a 100m long retaining wall that is of timber construction. It is inspected against the
requirements of IS-032. The requirements of the MDR requires the following steps:
Step 1:
Identify the asset; then populate & verify the asset attributes as per Section 4.3 of the MDR.
This results in the following asset attributes being recorded & verified:
Table 4-14: Worked Example – Retaining Wall Asset Attributes to be recorded
Attribute Name Value
Location (-37.776941, 144.997463)
ACA subclass Retaining Wall
ACA Type Retaining Wall
Construction date 1965
Asset ID 10001
DTP Asset ID 500001
Franchisee Train
Table 4-15: Worked Example – Retaining Wall Asset Attributes to be verified
Attribute Name Value
Maximum Height 2
Length 100
Material Timber Column and Timber Slab
Step 2:
Identify Simple or Complex Asset as per IS-032 in the MDR. If Complex – identify element
definition.
It has been identified that Retaining Walls are to be analysed as a “Complex” asset and the required
element definition is “Linear”.
This requires the retaining wall to be segmented into 50m elements and the start & end position of
these recorded. The element attributes are then also recorded as per Section 4.3 of the MDR.
19
Step 3:
Identify and record defects – noting complex asset with a linear element definition
For each element identified in the previous table, inspect for defects:
• Conduct the physical inspection and identify defect type in line with guidance in IS-032 of the
MDR.
• Identify component type (on which the defect is identified) as per the matrix provided in IS-032
of the MDR.
• Identify Component Criticality (CC) as per Section 4.4 of the MDR.
• Measure defects as per Section 4.4 & IS-032 of the MDR.
o Assign DCR to defect (and TPM where applicable)
o Record measurement approach and assign uncertainty
o Assign Renewal Mode Criteria
o Where the element(s) could not be inspected this should be noted. In this worked example,
all elements were inspected.
Criterion (RMC)
Renewal Mode
Criticality (CC)
Measurement
Measurement
Component
Uncertainty
TPM Units
Approach
TPM
Defect Type
Component
Element ID
Defect ID
Asset ID
Defect Condition
Rating (DCRraw)
Criterion (RMC)
Renewal Mode
Criticality (CC)
Measurement
Measurement
Component
Uncertainty
TPM Units
Approach
TPM
Defect Type
Component
Element ID
Defect ID
Asset ID
Step 4:
The steps required to calculate the ACR for a Complex Asset with Linear Element definition from the
MDR is as follows:
1. Assign the Defect Condition Rating (DCRraw) as per the guidelines for the Asset Subclass.
2. Adjust the DCRraw for CC as follows:
𝐷𝐶𝑅𝑟𝑎𝑤 , 𝐶𝐶 < 3
Equation 6: 𝐷𝐶𝑅𝑐𝑐 = {
𝐷𝐶𝑅𝑟𝑎𝑤 + 1, 𝐶𝐶 ≥ 3
Note: If DCRraw was originally 4, no adjustment is needed as the maximum value of DCRCC is 4.
3. Adjust DCRCC based on the RMC (See table in Section 4.4 of the MDR) to obtain DCRadjust.
4. Repeat the above steps for each defect identified for the element.
See Table 4-18 for the results of this exercise.
9. Plot a cumulative distribution function (CDF) for all the AECR values.
10. Take the 80%tile AECR value as the Asset AECR as per
11. Convert to ACR for the asset as follows:
Equation 8: 𝐴𝐶𝑅 = 𝐴𝐸𝐶𝑅80% + 1
See Table 4-19 for the summary of the AECRs for the elements and the CDF calculation which
shows an overall outcome of ACR = 3 for this Asset.
Table 4-18: Worked Example – Retaining Wall Asset Defect Analysis
Asset ID Element ID Defect ID DCRraw CC DCRCC RMC DCRadjust
60292057 1 11 3 3 4 2 2
60292057 1 12 1 2 1 2 0
60292057 1 13 3 2 3 2 2
60292057 2 14 3 2 3 2 2
60292057 2 15 4 2 4 2 2
60292057 2 16 3 3 4 2 2
60292057 2 17 1 2 1 2 0
60292057 2 18 3 2 3 2 2
60292057 3 19 3 2 3 2 2
60292057 3 20 4 2 4 2 2
60292057 3 21 3 3 4 2 2
60292057 3 22 1 2 1 2 0
60292057 3 23 3 2 3 2 2
60292057 4 24 3 2 3 2 2
60292057 4 25 4 2 4 2 2
60292057 4 26 3 2 3 2 2
60292057 4 27 3 2 3 2 2
Table 4-19: Worked Example – Retaining Wall Asset AECR Calculation and ACR Rollup
Element Element Type Element Name Max AECR AECR AECR AECR AECR AECR
ID DCR 0 1 2 3 4
1 Section Section 1 2 2 0 0 1 0 0
2 Section Section 2 2 2 0 0 1 0 0
3 Section Section 3 2 2 0 0 1 0 0
4 Section Section 4 2 2 0 0 1 0 0
5 Section Section 5 0 0 1 0 0 0 0
Cumulative # of Elements 1 1 5 5 5
Cumulative % of Elements 20% 20% 100% 100% 100%
Is CDR > 80% N N Y Y Y
4.5.1.4 Example 4: Complex Asset with Component Element Definition – Bridges (IS-010)
This example is for a predominantly concrete bridge. It is inspected against the requirements of IS-
010. The requirements of the MDR requires the following steps:
Step 1:
Identify the asset; then populate & verify the asset attributes as per Section 4.3 of the MDR.
This results in the following asset attributes being recorded & verified:
Table 4-20: Worked Example – Bridge Asset Attributes to be recorded
Attribute Name Value
Location (-37.776941, 144.997463)
ACA subclass Bridges, Subways & Culverts
ACA Type Underbridge
Construction date 1950
Asset ID 78050
DTP Asset ID 600001
Franchisee Train
Table 4-21: Worked Example – Bridge Asset Attributes to be verified
Attribute Name Value
Type Rail over Road
Superstructure type Deck/Slab
Substructure type Concrete
No. of spans 2
Overall width 20
Overall length 100
Deck Construction Concrete Deck
Deck Material Concrete
Step 2:
Identify Simple or Complex Asset as per IS-010 in the MDR. If Complex – identify element
definition.
It has been identified that this bridge is to be analysed as a “Complex” asset and the required element
definition is “Component” (each component is considered its own element).
This requires an element (component) model to be created for the bridge. The element attributes are
then also recorded as per Section 4.3 of the MDR.
Table 4-22: Worked Example – Bridge Element definition breakdown
Element (Component) Number of
Components
Deck / slab 2
Kerb 0
Railings / Barrier 2
Safety Screen 0
Girder / Beam 6
Truss 0
Arch 0
Cable / Hangers 0
Corbel 0
Crossbeam 0
Diaphragm / Bracing 4
Bearing 0
Deck joint 3
Stringer 0
Headstock 2
Column / Pile / Pier wall 1
Abutment 2
23
Wingwall / Retaining 4
wall
Footing / Pile cap 1
Deflection Walls 0
Bracing / Waler 0
Anchorage 0
Step 3:
Identify and record defects – noting complex asset with a component element definition
For each element identified in the previous table, inspect for defects:
• Conduct the physical inspection and identify defect type in line with guidance in IS-010 of the
MDR.
• Identify component type (on which the defect is identified) as per the matrix provided in IS-010
of the MDR.
• Identify Component Criticality (CC) as per Section 4.4 of the MDR.
• Measure defects as per Section 4.4 & IS-010 of the MDR.
o Assign DCR to defect (and TPM where applicable)
o Record measurement approach and assign uncertainty
o Assign Renewal Mode Criteria
o Where the component(s) could not be inspected this should be noted. In this worked
example, the Footing component of the bridge was inaccessible.
24
Measurement Approach
Defect Condition Rating
Component Criticality
Measurement
Uncertainty
TPM Units
(DCRraw)
(RMC)
TPM
(CC)
Defect Type
Component
Element ID
Defect ID
Asset ID
Step 4:
The steps required to calculate the ACR for a Complex Asset with Component Element definition from
the MDR is as follows:
1. Assign the Defect Condition Rating (DCRraw) as per the guidelines for the Asset Subclass.
2. Adjust the DCRraw for CC as follows:
𝐷𝐶𝑅𝑟𝑎𝑤 , 𝐶𝐶 < 3
Equation 9: 𝐷𝐶𝑅𝑐𝑐 = {
𝐷𝐶𝑅𝑟𝑎𝑤 + 1, 𝐶𝐶 ≥ 3
Note: If DCRraw was originally 4, no adjustment is needed as the maximum value of DCR CC is 4.
3. Adjust DCRCC based on the RMC (See table in Section 4.4 of the MDR) to obtain DCRadjust.
25
4. Repeat the above steps for each defect identified for the element.
See Table 4-25 for the results of this exercise.
Table 4-26: Worked Example – Bridge Asset AECR Calculation and ACR Rollup
Element Element Type Max DCR AEC AECR0 AECR1 AECR2 AECR3 AECR4
R
Deck 1 Deck / slab 0 0 1 0 0 0 0
Deck 2 Deck / slab 0 0 1 0 0 0 0
Railing 1 Railings / Barrier 0 0 1 0 0 0 0
Railing 2 Railings / Barrier 0 0 1 0 0 0 0
Beam 1 Girder / Beam 3 3 0 0 0 1 0
Beam 2 Girder / Beam 0 0 1 0 0 0 0
Beam 3 Girder / Beam 0 0 1 0 0 0 0
Beam 4 Girder / Beam 0 0 1 0 0 0 0
Beam 5 Girder / Beam 0 0 1 0 0 0 0
26
Element Element Type Max DCR AEC AECR0 AECR1 AECR2 AECR3 AECR4
R
Beam 6 Girder / Beam 2 2 0 0 1 0 0
Bracing 1 Diaphragm / Bracing 2 2 0 0 0 1 0
Bracing 2 Diaphragm / Bracing 0 0 1 0 0 0 0
Bracing 3 Diaphragm / Bracing 0 0 1 0 0 0 0
Bracing 4 Diaphragm / Bracing 0 0 1 0 0 0 0
Joint 1 Deck joint 0 0 1 0 0 0 0
Joint 2 Deck joint 0 0 1 0 0 0 0
Joint 3 Deck joint 0 0 1 0 0 0 0
Headstock 1 Headstock 0 0 1 0 0 0 0
Headstock 2 Headstock 1 1 0 1 0 0 0
Column 1 Column / Pile / Pier wall 0 0 1 0 0 0 0
Wingwall 1 Wingwall / Retaining 0 0 1 0 0 0 0
wall
Wingwall 2 Wingwall / Retaining 0 0 1 0 0 0 0
wall
Footing 1 Footing 0 -1 0 0 0 0 0
Abutment 1 Abutment 0 0 1 0 0 0 0
Abutment 2 Abutment 0 0 1 0 0 0 0
Y
Is the component Y
readily available off-
the-shelf?
Conduct supportability
assessment
1 2 3 4 5
TTISUP > 20yrs 20 ≥ TTISUP > 14 14 ≥ TTISUP > 8 8 ≥ TTISUP > 3 TTISUP ≤ 3yrs
The level of analysis which will be carried out per Asset Subclass is to be determined.
Supportability Analysis was conducted per make/model of asset for this Asset Subclass.
Step 2:
Fill out the questionnaire for each component of the system under consideration. Note that
software must also be considered as a separate ‘component’ if relevant to the system under
analysis and the questionnaire contains a different set of questions when considering
software.
Answer the questions in the Supportability Questionnaire below and record each outcome, as
required.
The Supportability Questionnaire from Section 9 of the MDR was answered and the outcomes are
shown in blue below for Specialist Servers.
Table 4-28: Supportability Questionnaire for Specialist Servers
Question Question – Physical Asset Question – Software Answer & Recording Next Step
No. and Applications Instruction
Q1 Is the component available, N/A for software and Record either ‘Yes’ If ‘Yes’ progress to Q2,
as new, from the OEM or applications or ‘No’ in Table 4-30 if ‘No’ progress to Q4
Distributor? under A1
Q2 Is there an end-date for the N/A for software and Record either ‘Yes’ or If ‘Yes’ progress to Q3,
supply of new components, applications ‘No’ in Table 4-30 if ‘No’ progress to Q4
as advised by the OEM or under A2
Distributor?
Q3 When is the end-date for the N/A for software and Record the time Progress to Q4
supply of new components? applications remaining until the
end-date for the supply
of new components
relative to the date of
assessment (in years)
in Table 4-29 under A3
Q4 Is a contract established Is the software or Record either ‘Yes’ If ‘Yes’ progress to
with the OEM or Distributor application covered by a or ‘No’ in Table 4-30 Q5, if ‘No’ progress to
for the continued support contract with the under A4 Q8
supply/replacement of OEM or an endorsed
components? support agency?
Q5 When does the When does the support Record the time Progress to Q6
supply/replacement contract expire? remaining until
contract expire? supply/replacement
contract end date
relative to the date of
assessment (in
years) in Table 4-29
under A5
Q6 Does an option exist to Is there an option to Do not record A6 If ‘Yes’ progress to Q7,
renew the renew the support if ‘No’ progress to Q8
supply/replacement contract?
contract?
30
Question Question – Physical Asset Question – Software Answer & Recording Next Step
No. and Applications Instruction
Q7 What is the length of the What is the length of the Record the length of Progress to Q8
extension option? extension option? the extension option
relative to the existing
supply/replacement
contract end-date (in
years) in Table 4-29
under A7
Q8 Is a repair/renewal contract Is there an internal Record either ‘Yes’ If ‘Yes’ progress to
in place which covers support team who have or ‘No’ in Table 4-30 Q9, if ‘No’ progress to
component renewal? the ability to make: under A8 Q12
• User changes
• Configuration changes
• Integration changes
Architectural changes
Q9 What is the end date for the What are the dates at Record the time Progress to Q10
repair/maintenance which there is an remaining until
contract? anticipated system repair/renewal
change that the internal contract end date
support team can no relative to the date of
longer make: assessment (in
• User changes years) in Table 4-29
• Configuration changes under A9
• Integration changes
Architectural changes
Q10 Does an option exist to N/A for software and Do not record A10 If ‘Yes’ progress to
renew the repair/renewal applications. Q11, if ‘No’ progress
contract? to Q12
Q11 What is the length of the N/A for software and Record the length of Progress to Q12
extension option? applications the extension option
relative to the existing
repair/renewal
contract end-date (in
years) in Table 4-29
under A11
Q12 What is the quantity of N/A for software and Record Average Progress to Q13
Average Stock on Hand for applications. Stock on Hand (qty)
the component? in Table 4-29 under
A12
Q13 What is the component N/A for software and Record Usage Rate
Usage Rate? applications. (qty/year) in Table
4-29 under A13
Step 3:
Using the outputs of the questionnaire – determine the inputs to the calculation of TTISUP.
For Specialist Servers, the Supportability Questionnaire (Table 4-28) was followed, and the answers
are recorded in Table 4-29 and Table 4-30 below:
Table 4-29: Supportability Questionnaire Answers (TTISUP Calculation Inputs)
Component A3 A5 A7 A9 A11 A12 A13
[years] [years] [years] [years] [years] [qty] [qty/yea
r]
Specialist Servers N/A -2 N/A 4 N/A 2 1
Note A5 is negative for this example which indicates that there is no existing contract in place and the
previous contract has already lapsed for a number of years.
Table 4-30: Supportability Questionnaire Answers (TSETime Inputs)
31
Using the values in Table 4-29, calculate each of the below and record in Table 4-31.
A. End of OEM/distributor availability (N/A for software/applications) = A3
B. Supply/replacement contract expiry (end of application/software support by OEM) = A5 + A7
C. Repair/maintenance contract expiry (end of internal team ability to accommodate user changes,
configuration changes, integration changes, architectural changes) = A9 + A11
D. Years of Available Spares Stock (SYears) (N/A for software/applications) = A12/A13
Specialist Servers:
A. End of OEM/distributor availability = N/A
B. Supply/replacement contract expiry (end of application/software support by OEM) = A5 + A7 = -
2 + 0 = -2
C. Repair/maintenance contract expiry (end of internal team ability to accommodate user changes,
configuration changes, integration changes, architectural changes) = A9 + A11 = 4 + 0 = 4
D. Years of Available Spares Stock (SYears) = 2/1 = 2
Table 4-31: Raw TTISUP Calculation Inputs
Component A [years] B [years] C [years] D [years]
Specialist Servers N/A -2 4 2
Determine Time to Supportability Expiry in accordance with Figure 4-4. For Specialist Servers, the
steps followed to Determine Time to Supportability Expiry are shown in red below:
32
Start
Y
A1 TSETime = 0
N
N
N N
A2 A4 A8
Y Y Y
Y Y
Is ‘C’ greater
A8
than ‘B’?
N N
Record ‘A’ as the Limitation Record ‘B’ as the Limitation Record ‘C’ as the Limitation
Criteria in Table 1-6 and Criteria in Table 1-6 and Criteria in Table 1-6 and
record the corresponding record the corresponding record the corresponding
value from Table 1-5 as value from Table 1-5 as value from Table 1-5 as
‘TSEtime’ in Table 1-6 ‘TSEtime’ in Table 1-6 ‘TSEtime’ in Table 1-6
Record ‘B’ as the Limitation Record ‘C’ as the Limitation
The answers from the Time to Supportability Expiry are filled out below:
Table 4-32: TTISUP Calculation Inputs (Equation 12)
Component Limitation Criteria (A, B or C) TSETime SYears (D)
Specialist C 4 years 2 years
Servers
Step 4:
Calculate the Objective Supportability Time to Intervention (TTI SUP) using Equation 13 for each
component.
Equation 13: 𝑇𝑇𝐼𝑆𝑢𝑝 = (𝑇𝑆𝐸𝑇𝑖𝑚𝑒 ) + 𝑆𝑌𝑒𝑎𝑟𝑠
Specialist Servers:
𝑇𝑇𝐼𝑆𝑢𝑝 = 4 + 2 = 6 𝑦𝑒𝑎𝑟𝑠
33
Step 5:
Record the TTISUP for each component of the system, the minimum TTI SUP is then recorded as
the “System TTISUP”.
Step 6:
Determine the Supportability DCR of the system based on the following bandings of System
TTISUP:
1 2 3 4 5
TTISUP > 20yrs 20 ≥ TTISUP > 14 14 ≥ TTISUP > 8 8 ≥ TTISUP > 3 TTISUP ≤ 3yrs
The level of analysis which will be carried out per Asset Subclass is to be determined.
Supportability Analysis was conducted per make/model of asset for this Asset Subclass.
Step 2:
Fill out the questionnaire for each component of the system under consideration. Note that
software must also be considered as a separate ‘component’ if relevant to the system under
analysis and the questionnaire contains a different set of questions when considering
software.
Answer the questions in the Supportability Questionnaire below and record each outcome, as
required.
The Supportability Questionnaire from Section 9 of the MDR was answered and the outcomes are
shown in blue below for Specific Cameras.
Table 4-33: Supportability Questionnaire for Specific Cameras
Question Question – Physical Asset Question – Software Answer & Recording Next Step
No. and Applications Instruction
Q1 Is the component available, N/A for software and Record either ‘Yes’ If ‘Yes’ progress to
as new, from the OEM or applications or ‘No’ in Table 4-30 Q2, if ‘No’ progress to
Distributor? under A1 Q4
Q2 Is there an end-date for the N/A for software and Record either ‘Yes’ If ‘Yes’ progress to Q3,
supply of new components, applications or ‘No’ in Table 4-30 if ‘No’ progress to Q4
as advised by the OEM or under A2
Distributor?
Q3 When is the end-date for the N/A for software and Record the time Progress to Q4
supply of new components? applications remaining until the
end-date for the supply
of new components
relative to the date of
assessment (in years)
in Table 4-29 under A3
34
Question Question – Physical Asset Question – Software Answer & Recording Next Step
No. and Applications Instruction
Q4 Is a contract established Is the software or Record either ‘Yes’ If ‘Yes’ progress to
with the OEM or Distributor application covered by a or ‘No’ in Table 4-30 Q5, if ‘No’ progress to
for the continued support contract with the under A4 Q8
supply/replacement of OEM or an endorsed
components? support agency?
Q5 When does the When does the support Record the time Progress to Q6
supply/replacement contract expire? remaining until
contract expire? supply/replacement
contract end date
relative to the date of
assessment (in
years) in Table 4-29
under A5
Q6 Does an option exist to Is there an option to Do not record A6 If ‘Yes’ progress to
renew the renew the support Q7, if ‘No’ progress to
supply/replacement contract? Q8
contract?
Q7 What is the length of the What is the length of the Record the length of Progress to Q8
extension option? extension option? the extension option
relative to the
existing
supply/replacement
contract end-date (in
years) in Table 4-29
under A7
Q8 Is a repair/renewal contract Is there an internal Record either ‘Yes’ If ‘Yes’ progress to Q9,
in place which covers support team who have or ‘No’ in Table 4-30 if ‘No’ progress to
component renewal? the ability to make: under A8 Q12
• User changes
• Configuration changes
• Integration changes
Architectural changes
Q9 What is the end date for the What are the dates at Record the time Progress to Q10
repair/maintenance contract? which there is an remaining until
anticipated system repair/renewal
change that the internal contract end date
support team can no relative to the date of
longer make: assessment (in years)
• User changes in Table 4-29 under A9
• Configuration changes
• Integration changes
Architectural changes
Q10 Does an option exist to renew N/A for software and Do not record A10 If ‘Yes’ progress to
the repair/renewal contract? applications. Q11, if ‘No’ progress to
Q12
Q11 What is the length of the N/A for software and Record the length of Progress to Q12
extension option? applications the extension option
relative to the existing
repair/renewal
contract end-date (in
years) in Table 4-29
under A11
Q12 What is the quantity of N/A for software and Record Average Progress to Q13
Average Stock on Hand for applications. Stock on Hand (qty)
the component? in Table 4-29 under
A12
Q13 What is the component N/A for software and Record Usage Rate
Usage Rate? applications. (qty/year) in Table
4-29 under A13
35
Step 3:
Using the outputs of the questionnaire – determine the inputs to the calculation of TTISUP.
For Specific Cameras, the Supportability Questionnaire (Table 4-33) was followed and the answers
are recorded in Table 4-34 and Table 4-35:
Table 4-34: Supportability Questionnaire Answers (TTISUP Calculation Inputs)
Component A3 A5 A7 A9 A11 A12 A13
[years] [years] [years] [years] [years] [qty] [qty/yea
r]
Specific Cameras N/A 3 3 N/A N/A 23 2
Specific Cameras:
A. End of OEM/distributor availability = N/A
B. Supply/replacement contract expiry (end of application/software support by OEM) = A5 + A7 = 3
+3=6
C. Repair/maintenance contract expiry (end of internal team ability to accommodate user changes,
configuration changes, integration changes, architectural changes) = A9 + A11 = 0
D. Years of Available Spares Stock (SYears) = 23/2 = 11.5
Determine Time to Supportability Expiry in accordance with Figure 4-6. For Specific Cameras, the
steps followed to Determine Time to Supportability Expiry are shown in red below:
36
Start
Y
A1 TSETime = 0
N
N
N N
A2 A4 A8
Y Y Y
Y Y
Is ‘C’ greater
A8
than ‘B’?
N N
Record ‘A’ as the Limitation Record ‘B’ as the Limitation Record ‘C’ as the Limitation
Criteria in Table 1-11and Criteria in Table 1-11 and Criteria in Table 1-11and
record the corresponding record the corresponding record the corresponding
value from Table 1-10 as value from Table 1-10 as value from Table 1-10 as
‘TSEtime’ in Table 1-11 ‘TSEtime’ in Table 1-11 ‘TSEtime’ in Table 1-11
Record ‘B’ as the Limitation Record ‘C’ as the Limitation
The answers from the Time to Supportability Expiry are filled out below:
Table 4-37: TTISUP Calculation Inputs (Equation 12)
Component Limitation Criteria (A, B or C) TSETime SYears (D)
Specific Cameras B 6 years 11.5 years
Step 4:
Calculate the Objective Supportability Time to Intervention (TTI SUP) using Equation 14 for each
component.
Equation 14: 𝑇𝑇𝐼𝑆𝑢𝑝 = (𝑇𝑆𝐸𝑇𝑖𝑚𝑒 ) + 𝑆𝑌𝑒𝑎𝑟𝑠
Specific Cameras:
𝑇𝑇𝐼𝑆𝑢𝑝 = 6 + 11.5 = 17.5 𝑦𝑒𝑎𝑟𝑠
37
Step 5:
Record the TTISUP for each component of the system, the minimum TTI SUP is then recorded as
the “System TTISUP”.
Step 6:
Determine the Supportability DCR of the system based on the following bandings of System
TTISUP:
1 2 3 4 5
TTISUP > 20yrs 20 ≥ TTISUP > 14 14 ≥ TTISUP > 8 8 ≥ TTISUP > 3 3yrs ≤ TTISUP
Step 1:
Identify how the asset will be grouped – for example, by Location / Asset Subclass / Asset type.
This asset type will be grouped by train line in order to analyse what is happening on one particular
train route. The train line to be analysed will be labelled “Line A”.
Step 2:
This is then converted to a time unit (in this case ‘000 hours) to enable the analysis to be conducted
with reference to the first failure (which set set to 0). This first value is then removed from the data set
for the analysis as a zero value will cause an error in subsequent calculations. The total number of
failures for subsequent calculations is then also considered to be 69.
Table 4-39: Failure times (‘000 hrs) of the asset type
0 3.456 9.504 16.824 18.312 21.192 26.64
0.048 6.144 10.512 16.872 19.008 21.24 27.288
0.84 6.216 11.52 17.184 19.008 21.312 27.312
1.392 6.816 11.592 17.808 19.176 21.384 27.432
1.704 7.608 12.36 17.856 19.68 22.416 27.432
1.992 7.776 14.256 17.88 19.92 24.576 27.48
2.568 7.8 15.192 18.144 20.544 25.056 27.552
2.616 8.496 15.384 18.144 20.736 25.56 27.984
2.808 8.496 15.624 18.168 20.832 25.8 29.232
2.928 8.88 16.272 18.168 21 26.136 29.664
Step 3:
Where:
𝑚 Is the total number of failures over the study period
𝑡𝑘 Is the total life (or operating cycles) observed for the asset to the end of the study period
𝑡𝑖 Is the time (or operating cycles) elapsed since the last failure
𝒎 (#) = 69
𝒕𝒌 = 29.664 (‘000 hrs)
Solve for β
𝜷 = 1.093
Step 4:
Step 5:
From the p-value, a rating can be determined using the following table.
Table 4-40: System Performance Condition Rating
System 1 2 3 4 5
Performance
Condition p≥0.2 or β≤1 0.2>p≥0.1 0.1>p≥0.05 0.05>p≥0.02 p<0.02
Rating β>1 β>1 β>1 β>1
General Statistically Weak evidence Some evidence Evidence exists Strong
Narrative significant exists to exists to to suggest an Evidence exists
evidence does suggest an suggest an increase in to suggest and
not exist to increase in increase in failure rate. increase in
suggest an failure rate. failure rate. failure rate.
increase in
failure rate.
As β>1 and p>0.2, the System Performance Condition Rating for “Line A” is 1. This indicates that
there does not exist statistically significant evidence that suggests an increase in failure rate.
Repeating this analysis for this asset type for a couple of other routes and the entire network
yields the following results:
Table 4-41: Summary of results
Route A Route B Route C Route D Entire Network
m 69 9 212 144 2104
tk 29.664 29.616 29.712 29.928 30.264
θ 1.698 6.52E-16 13.542 3.190 60.798
β 1.093 10.968 0.811 1.121 1.039
χ2 0.286 2.47E-06 0.109 0.0420
P 0.286 2.47E-06 0.109 0.0420
CR 1 5 1 (β<1) 2 4
These results highlight the importance of grouping on the data as different sub-populations within the
overall network may have significantly different results to each other, and the network as a whole.
40
2 Moderate
Defect
42
Corrosion
3 Major Defect
4 Severe
Defect
43
Cracking (Concrete)
Defect 1 Minor
Condition Defect
rating
2 Moderate
Defect
44
Cracking (Concrete)
3 Major
Defect
4 Severe
Defect
45
Cracking (Masonry)
Defect 1 Minor
Condition Defect
rating
2 Moderate
Defect
46
Cracking (Masonry)
3 Major
Defect
4 Severe
Defect
47
Missing/failed elements/connections
Defect 1 Minor Not available
Condition Defect
rating 2 Moderate
Defect
3 Major
Defect
49
Missing/failed elements/connections
4 Severe
Defect
50
2 Moderate
Defect
51
Mould
Defect 1 Minor
Condition Defect
rating
2 Moderate
Defect
3 Major
Defect
Rising Damp
Defect 1 Minor
Condition Defect
rating
2 Moderate
Defect
3 Major
Defect
54
Rising Damp
4 Severe
Defect
55
Rotting
Defect 1 Minor
Condition Defect
rating
2 Moderate
Defect
3 Major
Defect
56
Rotting
4 Severe
Defect
Spalling
Defect 1 Minor
Condition Defect
rating
Splitting/Splintering
Defect 1 Minor
Condition Defect
rating
2 Moderate
Defect
3 Major
Defect
58
Splitting/Splintering
4 Severe
Defect
Termite Attack
Defect 1 Minor
Condition Defect
rating
59
Termite Attack
2 Moderate
Defect
3 Major
Defect
60
Termite Attack
4 Severe
Defect
3 Major
Defect
62
Water Damage
Defect 1 Minor
Condition Defect
rating
63
Water Damage
2 Moderate
Defect
3 Major
Defect
5.2.3 Methodology
The methodology for determining the asset condition is to follow the process detailed by the following
sub-sections. This is intended as guidance to support the calculation steps in IS-003 in the MDR.
5.2.3.1 Inputs
Obtain and check all the latest required input data in accordance with the requirements contained in
IS-003 in the MDR for inputs.
In addition to the inputs identified in the MDR, the Junctions have been segmented but the asset
condition analysis has been conducted at a junction level primarily due to concerns about the ability to
accurately map survey data to the correct segment within a junction. If location accuracy of survey
data could be improved, it may be more appropriate to conduct the analysis at the segment level
within junctions to enable greater fidelity in the analysis of junctions.
If a previous segmentation exists, check if either the network, or the definitions of track types across
the network has changed, as this may negate the need to completely re-segment the network. Where
previous segmentation exists, updates to the segmentation shall retain the same segment
identification as the previous segmentation where there have been no changes to the network to allow
for the comparison of asset condition over time.
Apply data to network segmentation
• Apply asset attributes, utilisation attributes and network configuration attributes to the network
segmentation.
• Apply track survey data attributes to the network segmentation.
65
The required attributes & data to be applied to the segmentation can be found in IS-003 in the MDR
under the inputs requirements.
Example diagrams of the track types for segmentation are provided below to support the requirements
in the MDR.
Defect Condition Ratings DCRs are calculated according to the following steps:
(DCR)
a. Calculate deflection of individual survey measurements vs the
nominal values (found in the MDR).
b. Calculate the mean deflection over a single segment.
c. Calculate the standard deviation of the deflection over a single
segment.
d. Calculate the DCR from a combination of the mean & standard
deviation.
e. Normalise the DCR between 1 and 5.
Asset Condition Ratings (ACR) The ACR combines the normalised DCR values for each segment:
5.2.4 Assurance
Review the outputs of the analysis, as specified in IS-003 in the MDR, to check for potential errors and
unexpected results, for example:
1. Missing calculated values.
2. Poor condition track which is new and subject to low usage.
3. Isolated single segments of poor condition – particularly straights.
4. Segments within a polygon have all been assigned the same unique polygon identifier.
If a future works plan exists, compare the worst-case sections identified by this analysis with the
proposed sections being renewed for alignment.
In some instances, it may be warranted to perform a limited physical inspection on specific sections of
the track with unexpected results to confirm the accuracy of the analysis.
5.3.3 Methodology
The methodology for determining the asset condition is to follow the process detailed by the following
sub-sections. This is intended as guidance to support the calculation steps in IS-004 in the MDR.
5.3.3.1 Inputs
Obtain and check all the latest required input data in accordance with the requirements contained in
IS-004 in the MDR for inputs.
In addition to the inputs identified in the MDR, the following will also be considered where available:
• Cross-sectional area was not used due to current limitations in validating the survey data with
human inspections. It also did not have an available degradation relationship that provides high
confidence in the analysis as remaining thickness did. Cross section would provide a better
capture of the actual condition of the wire as opposed to the remaining thickness as it takes a
snapshot of the wire diameter.
• The Junctions have been segmented but the asset condition analysis has been conducted at a
junction level primarily due to concerns about the ability to accurately map survey data to the
correct segment within a junction. If location accuracy of survey data could be improved, it may
be more appropriate to conduct the analysis at the segment level within junctions to enable
greater fidelity in the analysis of junctions.
If a previous segmentation exists, check if either the network, or the definitions of track types in IS-003
across the network has changed, as this may negate the need to completely re-segment the network.
Where previous segmentation exists, updates to the segmentation shall retain the same segment
identification as the previous segmentation where there have been no changes to the network to allow
for the comparison of asset condition over time.
Apply data to network segmentation
• Apply asset attributes, utilisation attributes and network configuration attributes to the network
segmentation.
• Apply track survey data attributes to the network segmentation.
5.3.4 Assurance
Review the outputs of the analysis, as specified in IS-004 the MDR, to check for potential errors and
unexpected results, for example:
• missing calculated values.
• poor condition overhead wire which is new and subject to low usage.
• isolated single segments of poor condition.
• Segments within a polygon have all been assigned the same unique polygon identifier.
72
If a future works plan exists, compare the worst-case sections identified by this analysis with the
proposed sections being renewed for alignment.
In some instances, it may be warranted to perform a limited physical inspection on specific sections of
the Overhead Wires with unexpected results to confirm the accuracy of the analysis.
2 Moderate
Defect
3 Major
Defect
Cracking (Concrete)
Defect 1 Minor
Condition Defect
rating
2 Moderate
Defect
3 Major
Defect
76
Cracking (Concrete)
4 Severe
Defect
Cracking (Masonry)
Defect 1 Minor Not available
Condition Defect
rating 2 Moderate
Defect
77
Cracking (Masonry)
3 Major
Defect
4 Severe
Defect
Cracking (Shrinkage)
Defect 1 Minor Not available
Condition Defect
rating 2 Moderate
Defect
78
Cracking (Shrinkage)
3 Major
Defect
Deformation
Defect 1 Minor
Condition Defect
rating
Mortar Loss
Defect 1 Minor
Condition Defect
rating
Spalling
Defect 1 Minor
Condition Defect
rating
2 Moderate
Defect
3 Major
Defect
81
Spalling
4 Severe
Defect
Splitting / Splintering
Defect 1 Minor Not available
Condition Defect
rating 2 Moderate Not available
Defect
3 Major
Defect
4 Severe
Defect
82
Surface Rot
Defect 1 Minor Not available
Condition Defect
rating 2 Moderate Not available
Defect
3 Major
Defect
4 Severe
Defect
83
Additional structures built on top of the platform (e.g., awnings and non-protective fences/handrails)
are not components of this Asset Subclass and are not included in this inspection. Barriers that protect
against falls greater than 1m are included.
2 Moderate
Defect
Corrosion (Surface)
Defect 1 Minor
Condition Defect
rating
2 Moderate
Defect
Cracking (Concrete)
Defect 1 Minor
Condition Defect
rating
2 Moderate
Defect
3 Major
Defect
86
Cracking (Concrete)
4 Severe Not available
Defect
Cracking (Masonry)
Defect 1 Minor
Condition Defect
rating
2 Moderate
Defect
87
Cracking (Masonry)
3 Major
Defect
4 Severe
Defect
88
Differential Settlement
Defect 1 Minor
Condition Defect
rating
2 Moderate
Defect
89
Differential Settlement
3 Major
Defect
4 Severe
Defect
90
2 Moderate
Defect
91
Rotting
Defect 1 Minor
Condition Defect
rating
2 Moderate
Defect
92
Rotting
3 Major
Defect
4 Severe
Defect
Spalling
Defect 1 Minor
Condition Defect
rating
93
Spalling
2 Moderate
Defect
3 Major
Defect
4 Severe
Defect
94
Splitting/Splintering
Defect 1 Minor Not available
Condition Defect
rating 2 Moderate
Defect
Tilting
Defect 1 Minor
Condition Defect
rating
95
Tilting
2 Moderate
Defect
3 Major
Defect
96
Tilting
4 Severe
Defect
97
Electric lifts
Area • Component – Check.
General • Housekeeping - All components are clean; free from dust and corrosion.
• Electric wiring – Insulation.
• Pit area - For excess oil/grease at bottom of guides; area is clean, dry and free
Pit from debris.
• Anti-rebound device and switch - For free movement and operation; for equal
tension of ropes; switch (where fitted); lubrication.
• Buffers - Oil level; lubrication; switch (where fitted); fixings; operation.
• Electric safety devices – Operation.
• Drive motor/generator - Bearings for wear; lubrication; commutator condition.
• Gear box - Gear for wear; lubrication.
• Traction sheave - Condition and grooves for wear.
Machine
• Brake - Braking system; parts for wear; stopping accuracy.
Room
• Controller - Cabinet is clean, dry and free from dust.
• Overspeed governor and tension pulley - Moving parts for free movement and
wear; operation; switch.
• Main rope diverter pulley(s) - Condition and grooves for wear; bearings for
abnormal noise and/or vibrations; guarding; lubrication.
• Suspension ropes/chains - For wear, elongation and tension; lubrication only
where intended.
• Rope/chains terminations - For deterioration and wear; fixings.
• Safety gear(s)/ascending car overspeed - Moving parts for free movement and
wear; lubrication; fixings; operation; switch protection means.
• Motor run time limiter – Operation.
• Electric safety devices - Operation; electric safety chain; correct fuses are fitted.
• Car/counterweight guides - For film of oil where required on all guide surfaces,
fixings.
• Car/counterweight guide shoes - Guide shoes/rollers for wear; fixings;
Well lubrication where necessary.
• Suspension ropes/chains - For wear, elongation and tension; lubrication only
where intended.
• Rope/chains terminations - For deterioration and wear; fixings.
• Final limit switches – Operation.
• Well lighting – Operation.
• Electric safety devices - Operation; electric safety chain.
98
Electric lifts
• Lift car - Emergency lighting, car buttons, key switches; fixings of panels and
ceiling.
• Landing entrances - Operation of landing locks; doors for free running; door
guiding; door gaps; wire rope, chain or belt when used, for integrity; emergency
External unlocking device; lubrication.
• Car door - Door closed contact or lock; doors for free running; door guiding;
door gaps; wire rope or chain when used for integrity; passenger door protective
device; lubrication.
• Floor level - Stopping accuracy at landing.
• Emergency alarm device – Operation.
• Landing controls and indicators – Operation.
99
Corrosion
3 Major Not available
Defect
4 Severe Not available
Defect
Cracking (Concrete)
Defect 1 Minor
Condition Defect
rating
2 Moderate
Defect
3 Major
Defect Not available
4 Severe Not available
Defect
104
Differential Settlement
Defect 1 Minor Not available
Condition Defect
rating 2 Moderate
Defect
3 Major
Defect
Erosion
Defect 1 Minor
Condition Defect
rating
3 Major
Defect
4 Severe
Defect
107
2 Moderate
Defect
Overturning (Tilting)
Defect 1 Minor Not available
Condition Defect
rating 2 Moderate
Defect
108
Overturning (Tilting)
3 Major
Defect
Rotting
Defect 1 Minor
Condition Defect
rating
2 Moderate
Defect
109
Rotting
3 Major
Defect
Spalling
Defect 1 Minor Not available
Condition Defect
rating 2 Moderate Not available
Defect
3 Major
Defect
Splitting/Splintering
Defect 1 Minor
Condition Defect
rating
2 Moderate
Defect
*For IS-035 (Buffer Stops): In addition, use the tape measure to obtain the distance from the stress
raised point such as bolt holes, welds, connections.
Cracking (Concrete)
Defect 1 Minor
Condition Defect
rating
Splitting/Splintering
Defect 1 Minor
Condition Defect
rating
2 Moderate
Defect
3 Major
Defect
119
Corrosion (Surface)
4 Severe
Defect
Cracking (concrete/asphalt)
Defect 1 Minor
Condition Defect
rating
120
Cracking (concrete/asphalt)
2 Moderate
Defect
3 Major
Defect
4 Severe
Defect
121
Differential Settlement
Defect 1 Minor
Condition Defect
rating
2 Moderate
Defect
122
Differential Settlement
3 Major
Defect
Missing/Failed Elements/Connections
Defect 1 Minor
Condition Defect
rating
Missing/Failed Elements/Connections
4 Severe
Defect
Splitting/Splintering
Defect 1 Minor
Condition Defect
rating
Cuttings:
• Cutting Face
• Erosion Control Grid / Layer
• Ground Anchors / Rock Bolts
• Open Channel Drainage – both of earthen and non-earthen material, which are integral to the
function and stability of the embankment.
3 Major
Defect
134
Corrosion (Surface)
Defect 1 Minor
Condition Defect
rating
135
Corrosion (Surface)
2 Modera
te
Defect
Figure 5.19-1: Powered Machine Guidance Photograph 1 taken from MR4 – Technical Maintenance Plans –
Infrastructure
137
Figure 5.19-2: Powered Machine Guidance Photograph 2 taken from MR4 – Franchise Infrastructure
Management Plan
3 Major
Defect
4 Severe
Defect
139
Corrosion (Surface)
Defect 1 Minor
Condition Defect
rating
2 Moderate
Defect
The components associated with Signal Points – Point Controller are detailed in Table 5.20-1 below.
This table provides for each component, the guidelines that are to be used for the condition
assessment of the component, and which asset that the outputs of the assessment should be reported
against.
Table 5.20-1: Components
Component Defect, System Performance and Asset that the analysis
Supportability Assessment outputs are to be
Guidance reported against
Small power and control cables IS-078 IS-078
Cabinets OC-004 OC-004
Earthing System:
1. Source drawings/documentation of the earthing system of the given asset to understand and
locate the main components of the earthing system such as the earthing electrode(s), earthing
system connections in the earth rod pits, the main earth bar, the Voltage Limiting Device (VLD)
(traction substations only) – if installed, other equipotential earth bonds such as security fencing,
framework, and other metallic components.
2. Note that VLDs will be located in all traction substations on the train network, and some traction
substation for the Tram network. They will not be present in tram network areas where the rail is
earthed (i.e. uninsulated rail cast in concrete or asphalt.)
3. The inspector shall also record the manufacturer of the VLD.
• Sheath damage. Degradation of the sheath can be attributed to atmospheric ozone, oxygen
and ultraviolet light, which breaks down the polymer bonds. The addition of heat to any of these
will act as a catalyst. Damage to the sheath is an indication of performance or mechanical
degradation that could lead to the future failure along the cable insulation. Key metrics for
identifying sheath damage include:
o Cracks
o Perforations rubbing
o Embrittlement of the sheath.
Thermal Degradation
Defect 1 Minor Not available
Condition Defect
rating 2 Moderate Not available
Defect
3 Major Not available
Defect
4 Severe
Defect
153
Sheath damage
Degradation of the sheath can be attributed to atmospheric ozone, oxygen and ultraviolet light, which
breaks down the polymer bonds. The addition of heat to any of these will act as a catalyst. Damage to
the sheath is an indication of performance or mechanical degradation that could lead to the future
failure along the cable insulation. Key metrics for identifying sheath damage include:
• Cracks
• Perforation rubbing
• Embrittlement of the sheath.
Thermal Degradation
Defect 1 Minor Not available
Condition Defect
rating 2 Moderate Not available
Defect
3 Major Not available
Defect
4 Severe
Defect
157
The components associated with Lighting are detailed in Table 5.33-1 below. This table provides for
each component, the guidelines that are to be used for the condition assessment of the component,
and which asset that the outputs of the assessment should be reported against.
Table 5.33-1: Lighting Components
Component Defect, System Performance and Asset that the analysis
Supportability Assessment outputs are to be
Guidance reported against
LV Switchgear IS-077 IS-077
Small Power and Control Cables IS-078 IS-078
Poles IS-042 IS-042
Terminal 0
corrosion/electrolyte
leakage
The components associated with PIS are detailed in Table 5.38-1 below. This table provides for each
component, the guidelines that are to be used for the condition assessment of the component, and
which asset that the outputs of the assessment should be reported against.
• Additional details surrounding the inspection of specific components are detailed below:
o PID Housings – Not all PIDs have housings, however for PIDs that do, damage to the
housing could result in the accelerated failure of critical internal equipment due to
corrosion and loss of ingress protection. The displays and their housings will usually be at
a height making close inspection from ground level unachievable. Assessing the condition
of the housings may still be possible, with the use of binoculars, by looking for indications
of failure on visible areas of the asset. However, closer inspection is recommended if
permitted. If the housing quality is poor across the asset base, then this reflects a likely
166
point of intervention.
o PID Anchor Points – The PID housing is most commonly suspended via anchorage
points to the support structure. This inspection looks at the anchorage points on the top
surface of the housing to assess their condition and potential for failure. Adequate
inspection of this component would require direct access to the anchor point of the PID
housing and consequently appropriate working at heights certification, access equipment
and PPE. Failure of this component would risk the safe anchorage of the unit to the
structure, potentially resulting in harm to anyone directly impacted by the failure moment.
o CHP – CHP include electrical, speaker and button circuitry. Damage to the externals of
the CHP could result in the accelerated failure of the CHP due to ingress of dust,
moisture, vermin etc.
*PID Housing Only: Using a measuring device, measure the proximity of corrosion to the nearest
seal(s) and edge(s).
1. Current Collection
a. Pantograph Assembly
b. Earth return.
2. Power Supply
a. Surge Arrester
b. High Speed Circuit Breaker (HSCB)
c. Line Filter
d. High Voltage Box (HV Box)
e. Main Isolating Switch.
6 TPM Library
This section contains a library of Defect Specific TPM Processes that are applicable to one or more
Asset Subclasses.
The Asset Subclass specific guidelines in Section 5 will reference these specific TPM processes
where relevant.
1 Measure and record the connection resistance (micro-ohmic reading) of IEEE Std
each battery in accordance with the diagrams below. Measure the 1188-2005
micro-ohmic resistance between the post-top terminals of each battery
using a meter specifically designed to measure resistance in micro-
ohms.
6.4 Chipping
Table 6-4: Chipping Measurement Process
Step Action
1 Assess for chipping.
2 Using a measuring device, measure extent of chipping.
3 Ensure data points are assigned to either:
• Component type.
• Component as per element model.
• Element as per element model.
187
6.5 Collapse
Table 6-5: Collapse Measurement Process
Step Action
1 Use the tape measure to measure the area of the component affected. Calculate the
percentage area affected.
2 Ensure data points are assigned to either:
• Component type.
• Component as per element model.
• Element as per element model.
6.6 Corrosion
6.6.1 Corrosion (Pitting / Section Loss)
Table 6-6: Corrosion (Pitting / Section Loss) Measurement Process
Step Action
1 Assess areas for extent of section loss.
2 Identify section of member with significant pitting corrosion.
3 Using a measuring device to measure the corroded section dimensions at data point.
6.7 Cracking
6.7.1 Cracking (General)
Table 6-10: Cracking (General) Option 1 Measurement Process
Step Action
1 For each defect identified, record the number, direction and average spacing of cracks
on the component.
2 Use the crack width gauge to measure the width of each nominated crack where safe to
do so.
3 Use a measuring device to obtain the overall length of each nominated crack where safe
to do so.
4 Ensure data points are assigned to either:
• Component type.
• Component as per element model.
• Element as per element model.
6.8 Deflection
Table 6-16: Deflection (Option 1) Measurement Process
Step Action
1 Set up the tripod and laser distance meter.
2 Record vertical height of structure (l1) and angle () by pointing laser at the bottom and
move to the top of the structure.
3 Point the laser distance meter at the top of the hold down bolts and point the laser to the
end of the cantilever post or nominated feature.
4 Record distance (l2) and angle () measured from the laser distance meter.
5 Ensure data points are assigned to either:
• Component type.
• Component as per element model.
• Element as per element model.
6.12 Flashover
Table 6-23: Flashover Measurement Process
Step Action
1 Assess for flashover – looking for black/white flash marks on the insulator.
2 Using a measuring device, measure the extent of flashover across the component
length.
3 Ensure data points are assigned to either:
• Component type.
• Component as per element model.
• Element as per element model.
192
6.13 Fraying
Table 6-24: Fraying Measurement Process
Step Action
1 Count the number of frayed strands that are visible.
2 Identify if the second layer of the conductor/rope is exposed.
3 Ensure data points are assigned to either:
• Component type.
• Component as per element model.
• Element as per element model.
6.17 Mould
Table 6-28: Mould Measurement Process
Step Action
1 Use a measuring device to measure the area of the component affected. Calculate the
percentage area affected within the element / component (whichever is smaller).
2 Ensure data points are assigned to either:
• Component type.
• Component as per element model.
• Element as per element model.
6.19 Overheating
Table 6-30: Overheating Measurement Process
Step Action
1 Locate an area within the parameters of the thermal imaging camera where a clear
line-of-sight is available to the switch
2 Using the thermal imaging camera, pointing its laser to various locations on the switch
including the terminals, identify any locations exhibiting significantly higher
temperatures than the ambient
4 Take a minimum of two thermal images of the switch exhibiting higher than ambient
temperatures
5 Ensure data points are assigned to either:
• Component type.
• Component as per element model.
• Element as per element model.
6.20 Over-temperature
Table 6-31: Over-temperature (Uninsulated Conductors) Measurement Process
Step Action
1 For each defect identified, record the component type that has been identified as over
temperature.
2 Use a thermography camera to measure the temperature of the component and
calculate the temperature rise above that of the surrounding components.
3 Take thermal and visible light photographs of the component.
4 Ensure data points are assigned to either:
• Component type.
• Component as per element model.
• Element as per element model.
194
6.22 Pollution
Table 6-33: Pollution Measurement Process
Step Action
1 Identify components that appear to have been affected by arcing.
2 Take images of areas of deposition of pollutants on the components.
3 By visual observation estimate the percentage of area of the components covered by
pollutants.
4 Ensure data points are assigned to either:
• Component type.
• Component as per element model.
• Element as per element model.
6.23 Potholes
Table 6-34: Potholes Measurement Process
Step Action
1 Assess for potholes.
2 Select data point/s with the deepest point.
3 Using a straight edge, lay the straight edge across the rut and measure and record the
depth of the pothole.
Table 6-35: Resistance / Continuity Testing – Earthing System Resistance Measurement Process
Step Action
1 Record location earthing system.
2 Locate the main components of the earthing system such as:
• the earthing electrode(s),
• earthing system connections in the earth rod pits,
• the main earth bar,
• other equi-potential earth bonds such as security fencing, framework and other
metallic components.
3 For all low voltage installations (Multiple Earth Neutral (MEN) earths), perform a check
of the resistance of the earthing cable from any earth electrode to the main earth bar
using a low voltage ohm-meter.
If – >0.5 ohm record defective. If =<0.5 ohms the earthing system complies with
Australian Standards.
Do not undertake this test on high voltage systems and traction substations as it is
being undertaken by the Franchisee.
4 Testing which is not visual in nature must be undertaken by the Franchisee
representative(s).
Test the resistance of all substation security fencing to earth. Perform a check of the
resistance of the earthing cable from any earth electrode to the main earth bar using a
low voltage ohm-meter.
If – >0.5 ohm record defective. If =<0.5 ohms the earthing system complies with
Australian Standards.
5 Ensure data points are assigned to either:
• Component type.
• Component as per element model.
• Element as per element model.
6.27 Rutting
Table 6-39: Rutting Measurement Process
Step Action
1 Assess areas for extent of rutting.
2 Select data point/s with the deepest point.
3 Using a tape measure (or estimate if not accessible), calculate the area/length of rut.
Calculate the percentage of rutting on component.
4 Using a straight edge, lay the straight edge across the rut and measure and record
the depth of the rutting.
4 Ensure data points are assigned to either:
• Component type.
• Component as per element model.
• Element as per element model.
6.28 Scouring
Table 6-40: Scouring Measurement Process
Step Action
1 Measure length and width at scour location using laser or tape measure, documenting
the area of the element / component affected by scour.
2 Estimate average depth of lost material and maximum depth to nearest 0.2 m. String
line and tape measure may be used subject to safe access.
197
6.29 Settlement
Table 6-41: Settlement (Option 1) Measurement Process
Step Action
1 Use the permanent marker to mark four quadrant points on the circumference of the
pole.
2 Use a tape measure to measure the height of the points with reference to the ground.
3 Ensure data points are assigned to either:
• Component type.
• Component as per element model.
• Element as per element model.
6.30 Snipe
Table 6-43: Snipe Measurement Process
Step Action
1 Use the tape measure (or estimate if not accessible) the depth of snipe.
2 Ensure data points are assigned to either:
• Component type.
• Component as per element model.
• Element as per element model.
6.31 Spalling
Table 6-44: Spalling (Option 1) Measurement Process
Step Action
1 Assess areas for extent of section loss.
2 Select data point/s with the most significant loss of section.
3 Using a measuring device (or estimate if not accessible), calculate the area/length of
spalling. Calculate the percentage of the element / component affected by spalling.
4 Ensure data points are assigned to either:
• Component type.
• Component as per element model.
• Element as per element model.
198
6.32 Splitting
Table 6-46: Splitting Measurement Process
Step Action
1 Using a measuring device, measure length and width of split.
2 Ensure data points are assigned to either:
• Component type.
• Component as per element model.
• Element as per element model.
3 Photograph the split(s) and highlight the affected area if not visible from the
photograph.
6.36 Tilting
Table 6-50: Tilting (Option 1) Measurement Process
Step Action
1 Place the laser level immediately adjacent to the structure and orientate the laser
vertically upwards.
2 Use a measuring device to measure the distance from the laser line to a building
corner at two points.
3 Calculate the alignment difference. Ensure data points are assigned to either:
• Component type.
• Component as per element model.
• Element as per element model.
6.38 Uplift/heave
Table 6-54: Uplift/Heave Measurement Process
Step Action
1 Place the straight edge on the surface horizontally.
2 Use a tape measure to measure the distance from the laser line to a common point at
the base of the surface on one side of the surface (e.g. the railway track). Repeat the
measurement at a corresponding point on the opposite side of the surface.
3 Calculate the alignment difference. Ensure data points are assigned to either:
• Component type.
• Component as per element model.
• Element as per element model.
6.41 Wear
Table 6-58: Wear Measurement Process
Step Action
1 Identify areas of wear along the runner
2 Measure or estimate the minimum thickness of the runner.
3 Ensure data points are assigned to either:
• Component type.
• Component as per element model.
• Element as per element model.