NAME OF WORK.

CONSTRUCTION OF RCC DRAINAGE LINE@


SINDH UNIVERSITY COLONY TALUKA KOTRI DISTRICT JAMSHORO.

PART A
1 Cost of civil work without fabrication = 436467

2 Cost of Fabrication = 199404


3 Add Premium above
4 10.00% = 19940

5 Total Cost Of Fabrication = 219344

PART B

6 PUBLIC Health SCHEDULE ITEM = 64260


7 Add Premium on (7)
8 5.00% = 3213

9 TOTAL PART B = 67473

PART C

10 Cost of RCC/ UPVC PIPE = 561000


11 Add Premium on 11
12 15.00% = 84150

13 Total Amount Part C = 645150

14 Cost Of Carriage = 44895

15 Contigencey Lump Sump = 40000

16 Total Amount = 1453330

Total Cost in million = 1.453

SUB ENGINEER BUILDINGS ASSISTANT ENGINEER BUILDINGS


SUB DIVISION KOTRI DISTRICT JAMSHORO SUB DIVISION KOTRI DISTRICT JAMSHORO
NAME OF WORK. CONSTRUCTION OF RCC DRAINAGE LINE@
SINDH UNIVERSITY COLONY TALUKA KOTRI DISTRICT JAMSHORO.

ITEM QTY CEMENT H. SAND SHINGLE STONE STEEL Brick

1 CC 1:4:8 334 32 160 321

2 CC 1:2:4 817 144 359 719

3 RCC 1:2:4 638 112 281 561

4 Fabrication 40 1.99

5 B.W 1:6 (fdn)/ G.F 371 13 103 5012

6 C.P ( 1:4 ) 3/4" 851 10 47

TOTAL 311 950 1280 321 1.99 5012

RATE 41.73 1032.44 902.20 1358.04 967.32 1164.59

TOTAL 12960 9808 11549 4356 386 5837

TOTAL AMOUNT 44895

SUB ENGINEER BUILDINGS ASSISTANT ENGINEER BUILDINGS


SUB DIVISION KOTRI DISTRICT JAMSHORO SUB DIVISION KOTRI DISTRICT JAMSHORO
NAME OF WORK. CONSTRUCTION OF RCC DRAINAGE LINE@
SINDH UNIVERSITY COLONY TALUKA KOTRI DISTRICT JAMSHORO.

1 Cement Luky Miles 59


Ist & 2nd 7.53
3rd & Sbsequent Mile 57 0.6 34.20
= 41.73

2 Hill Sand Bolhari Miles 14


Ist & 6th 771.96
7th & Sbsequent Mile 8 32.56 260.48
= 1032.44

3 Crush Patero Miles 10


Ist & 6th 771.96
7th & Sbsequent Mile 4 32.56 130.24
= 902.20

4 Stone Metal Ongar Miles 24


Ist & 6th 771.96
7th & Sbsequent Mile 18 32.56 586.08
= 1358.04

5 Steel / Tile Hyderabad Miles 12


Ist & 6th 771.96
7th & Sbsequent Mile 6 32.56 195.36
= 967.32

6 Bricks Tando fazal Miles 27


Ist & 4th 617.54
7th & Sbsequent Mile 21 26.05 547.05
1164.59

SUB ENGINEER BUILDINGS ASSISTANT ENGINEER BUILDINGS


SUB DIVISION KOTRI DISTRICT JAMSHORO SUB DIVISION KOTRI DISTRICT JAMSHORO
NAME OF WORK. CONSTRUCTION OF RCC DRAINAGE LINE@
SINDH UNIVERSITY COLONY TALUKA KOTRI DISTRICT JAMSHORO.

PART A

1 Excavtion in foundation of bulding, bridges and other structure including dag belling
reflling around strecture with excavated earth watering and ramming. lead upto
upto 5ft(b) in Ordinary or soft murum. (S.I.NO.18(b)/C-1

Main Hole 1 x 33 x 4.50 x 4.50 x 2.00 = 1337

O%Cft 1337 x 3176.25 = 4245

2 Cement concrete brick or stone ballast1.5 inch to2 inch guage.(b) Ratio 1:4:8. (S.I.No.4 (b) /C-4).

Main Hole 1 x 33 x 4.50 x 4.50 x 0.50 = 334


= 334

%Cft 334 x 9416.28 = 31462

3 Pacca Brick work in foundation and plinth in


cement sand mortar in 1:6
item 4 ( e ) page 20 chapter 5

Main Hole L.wall 1 x 33 x 4.50 x 0.75 x 1.00 = 111


Main Hole S.wall 1 x 33 x 3.00 x 0.75 x 1.00 = 74
= 186

%Cft 186 x 11948.36 = 22179

4 Pacca Brick work in ground floor in


cement sand mortar in 1:6
item 5(E) page 21 chapter 5

Main Hole L.wall 1 x 33 x 4.50 x 0.75 x 1.00 = 111


Main Hole S.wall 1 x 33 x 3.00 x 0.75 x 1.00 = 74
= 186

%Cft 186 x 12674.36 = 23527

5 Erection and removal of centering for reniforced or palin cement concrete works of partial wood
( 2nd Class ) ( B) Vertical.

Main Hole 1 x 30 x 2 x 0.75 x 2.00 = 90


= 90

%Sft 90 x 3127.41 = 2815

6 Cement concrete plain including placing , compacting finishing and curing complete
( including screening and washing of stone aggrete without shuttering ( F ) Ratio 1:2: 4

Main Hole Inside 1 x 63 x 3.0 x 3.00 x 0.25 = 142


Main Hole L. Walls 30 x 2 x 4.50 x 0.75 x 2.00 = 405
Main Hole S. Walls 30 x 2 x 3.00 x 0.75 x 2.00 = 270
= 817

%Cft 817 x 14429.25 = 117851

7 Cement plaster 1:4 upto 20 height (a) 1/2" thick (S.I.No.11(a)/C-9)

Main Hole inside 1 x 63 x 3.00 x 3.00 x 2.00 = 1134


Main Hole L.wall Out Side 1 x 63 x 4.50 x 0.75 x 2.00 = 425
Main Hole S.wall Out Side 1 x 63 x 4.50 x 0.75 x 2.00 = 425
= 851

%Sft 851 x 2283.93 = 19425

8 Reinforced cement concrete work i/c all labour and material


except the cost of steel reinforcement and its labour for
bending and binding whidh will be paid separately. This rate
also includes of forms, moulds,lifting, shuttering, rendering
and finishing and finishing the exposed surface ( i/c screening,
shingle ( a ) Rc work in roof slab, beams, columns, rafts,
lintals and other structural members laid in situ or precast
laid in position. Complete in all respects ( I ) Ratio 1:2:4,
90 lbs ( S.I.No. 6 ( a ) ( i ) - P / 19 )

Main hole Slab 1 x 63 x 4.50 x 4.50 x 0.50 = 638


= 638

P.Cft 638 x 337.00 = 214964

9 Fabrication of Miled Steel Reinforcement for Cement Concrete including cutting, bending,
laying in position, making joints and fastly including cost of binding wire (also includes \
removal of rust from bars

Qty same as item no(08)


1 x 1 x 638 x 7.00 / 112.00 = 40

Pcwt 40 x 5001.70 = 199404

= 635871

SUB ENGINEER BUILDINGS ASSISTANT ENGINEER BUILDINGS


SUB DIVISION KOTRI DISTRICT JAMSHORO SUB DIVISION KOTRI DISTRICT JAMSHORO
)
NAME OF WORK. CONSTRUCTION OF RCC DRAINAGE LINE@
SINDH UNIVERSITY COLONY TALUKA KOTRI DISTRICT JAMSHORO.

PART B

1 Excavation of pipe line into trenches and pits in gravely soils i/c trimming & dressing sides to
to true alignment and shape leveling of beds of trenches to correct level and grade cutting
joint holes and disposal of surplus earth within a one chain as directed by Engineer incharge
providing fence guards lights flags and temporary crossing for non vehicular traffic where
ever required to lift upto 5' ft (1.52m) and lead upto one chain (30.50 mm ) (P.H.S.I NO. 4 P/61)

For Pipe Line 1 x 1 x 1700 x 3.00 x 3.00 = 15300

%Sft 15300 x 4200.00 = 64260

2 Excavation of pipe line into trenches and pits in all kind of soils of morum i/c trimming & dressing sides to
to true alignment and shape leveling of beds of trenches to correct level and grade cutting
joint holes and disposal of surplus earth within a one chain as directed by Engineer incharge
providing fence guards lights flags and temporary crossing for non vehicular traffic where
ever required to lift upto 5' ft (1.52m) and lead upto one chain (30.50 mm ) (P.H.S.I NO. 5 P/62)

For Pipe Line 0 x 1 x 120 x 3.00 x 3.00 = 0

%Sft 0 x 4650.00 = 0

3 Excavation of pipe line into trenches and pits in all kindof soils of morum i/c trimming & dressing sides to
to true alignment and shape leveling of beds of trenches to correct level and grade cutting
joint holes and disposal of surplus earth within a one chain as directed by Engineer incharge
providing fence guards lights flags and temporary crossing for non vehicular traffic where
ever required to lift upto 5' ft (1.52m) and lead upto one chain (30.50 mm ) (P.H.S.I NO. 6 P/62)

For Pipe Line 1 x 1 x 1600 x 3.00 x 3.00 = 14400

%Sft 0 x 10770.00 = 0

4 Refilling the excavated stuff trench 6'' thick layers i/c watering ramming to full compaction etc
complete (P.H.S.I.NO. 24, P/53)

1 x 1 x 15300.00 x 2.00 / 3.00 = 10200

0 x 2760.00 = 0

= 64260

= 4.95%

= 3181
SUB ENGINEER BUILDINGS ASSISTANT ENGINEER BUILDINGS
SUB DIVISION KOTRI DISTRICT JAMSHORO SUB DIVISION KOTRI DISTRICT JAMSHORO = 67441
)
NAME OF WORK. CONSTRUCTION OF RCC DRAINAGE LINE@
SINDH UNIVERSITY COLONY TALUKA KOTRI DISTRICT JAMSHORO.

PART C

1 Providing RCC Pipes & collars of class C and fixing in trench including
cutting & fitting and jointing with maxphalt compostion and cement
1:1 including testing with water to headof 45 meter or i50 C class
item 3 page 16 chapter finished item Public health Engineering

6 inch dia 0 x 189.00 PRft = 0


9 inch dia 0 x 194.00 PRft = 0
12 inch dia 1700 x 330.00 PRft = 561000
15 inch dia 0 x 434.00 PRft = 0
18 inch dia 0 x 481.00 PRft = 0

2 Providing Laying UPVC presure pipes of Class D ( equivalent make ) fixing in trench i/c cutting, fitting
and jointing with Z joint with one rubber i/c testing with water to a head 122 meter or 400 ft
item 3 page 23 chapter finished item Public health

6 inch dia 0 486.00 PRft = 0


8 inch dia 0 742.00 PRft = 0
10 inch dia 0 1375.00 PRft = 0
12 inch dia 0 1929.00 PRft = 0

3 Providing Laying & fixing in trench including fitting , jointing& testinge etc in all respect
the high density of Polythylene PE pipes .
item 1 page 25 chapter finished item Public health Engineering

25mm 0 27.00 PRft = 0


32mm 0 32.00 PRft = 0
40mm 0 41.00 PRft = 0
250mm 0 1043.00 PRft = 0
280mm 0 1313.00 PRft = 0
1700

= 561000

= 14.93%

= 83757
= 644757

SUB ENGINEER BUILDINGS ASSISTANT ENGINEER BUILDINGS


SUB DIVISION KOTRI DISTRICT JAMSHORO SUB DIVISION KOTRI DISTRICT JAMSHORO
)
NAME OF WORK. CONSTRUCTION OF RCC DRAINAGE LINE@
SINDH UNIVERSITY COLONY TALUKA KOTRI DISTRICT JAMSHORO.

STREET
HOUSES HOUSES

STREET
GROUND
indus higway

RCC PIPE LINE


Disposal

HOUSES

SUB ENGINEER BUILDINGS ASSISTANT ENGINEER BUILDINGS


SUB DIVISION KOTRI DISTRICT JAMSHORO SUB DIVISION KOTRI DISTRICT JAMSHORO
NAME OF WORK. CONSTRUCTION OF RCC DRAINAGE LINE@
SINDH UNIVERSITY COLONY TALUKA KOTRI DISTRICT JAMSHORO.

WIDE 0.75 FT WIDE 0.75 FT


WALLS BRICK MASONARY 9 INCH

WALLS BRICK MASONARY 9 INCH

2.50 FT
2.0 ft wide

CC TOPPING 1:2:4 3 INCH

6 INCH
CC 1:4:8 BED 6 INCH

wide 4.50 ft

SUB ENGINEER BUILDINGS ASSISTANT ENGINEER BUILDINGS


SUB DIVISION KOTRI DISTRICT JAMSHORO SUB DIVISION KOTRI DISTRICT JAMSHORO