SCHEDULE OF RATES
EXCAVATION
SCHEDULE OF RATES
EXCAVATION
15 Exceeding 2.00m but not exceeding 4.00m deep with granular m3 12.90
materials.
17 Exceeding 2.00m deep but not exceeding 4.00m deep with selected m3 8.10
excavated material.
19 Exceeding 2.00m but not exceeding 4.00m deep with selected m3 13.80
imported earth.
20 CART AWAY excavated materials off site and deposit at the m3 4.50
Contractor's own dumping ground.
21 Dry approved earth filling obtained from outside source and fill in m3 9.90
layers of 300mm thick; including labour for spreading, trimming and
consolidating to form earth mounds or to form levels outside buildings
and/or under floor slabs, etc as specified.
22 Selected excavated material obtained within the site and used as filling m3 6.10
to make up level including consolidation.
23 Supply and lay minimum 80mm diameter bakau piles as roller m 1.00
supports.
SCHEDULE OF RATES
EXCAVATION
30 Supply and deliver steel sheet pile for use as temporary shoring to ton 107.40
retain the sides of excavation in approved section and lengths.
31 Drive steel sheet pile including the provision of all labour, construction ton 299.00
equipment, tools and everything necessary for the installation as
specified.
32 Extract, recover and stack steel sheet piles including the provision of ton 230.00
all labour, construction equipment, tools and everything necessary for
the execution as specified.
33 Supply, deliver and drive steel sheet piles left - in permanently ton 1,219.00
including the provision of all labour, construction equipment, tools and
everything necessary for the installation as specified.