SCHEDULE OF RATES
CONCRETING WORK
SCHEDULE OF RATES
CONCRETING WORK
SCHEDULE OF RATES
CONCRETING WORK
19 Supply and lay approved damp proof membrane complied with BS m2 6.90
6398 Type B (felt fibre base) to underside of reinforced concrete slab
including provision for laps and preparation of surface as specified.
23 Supply and lay approved felt as protective cover to bituthene 3000 m2 4.50
waterproofing membrane including EM 3000 mastic or other approved
adhesive.
24 Supply and apply 1 undercoat and 2 finishing coats of heavy duty m2 26.10
liquid plastic dressing (non-slip grade) or other approved liquid plastic
dressing (non-slip grade) to top of concrete surface including labour
and materials for surface preparation, etc in accordance with
manufacturer's instructions (rate inclusive of the provision of a 5-year
warranty).
25 Supply and lay approved Cold Liquid Applied Polyurethane High m2 17.40
Performance Elastomeric Waterproofing Membrane to bath/wc/kitchen
floors including preparation of surfaces and dressing up to pipes and
walls and application of priming coat all as specified (measured flat-
on-plan and no adjustment to be made for voids occupied by pipes.
Rates inclusive of the provision of a 5-Year Warranty).
SCHEDULE OF RATES
CONCRETING WORK
SCHEDULE OF RATES
CONCRETING WORK
52 A5. m2 2.50
53 A6. m2 3.20
54 A7. m2 4.00
55 A8. m2 5.00
56 A10. m2 7.50
CONCRETING WORK SOR 6
SCHEDULE OF RATES
CONCRETING WORK
57 A12. m2 10.50
58 B5. m2 4.30
59 B6. m2 5.00
60 B7. m2 5.60
63 B8. m2 7.30
64 B8A. m2 4.20
66 B9. m2 8.50
68 B10. m2 9.70
69 B12. m2 12.80
70 B13. m2 15.90
71 D4. m2 10.90
72 D5. m2 4.50
73 D6. m2 5.80
74 D7. m2 7.40
75 D8. m2 9.50
CONCRETING WORK SOR 7
SCHEDULE OF RATES
CONCRETING WORK
76 D9. m2 11.80
77 D10. m2 14.60
78 D11. m2 17.40
79 D12. m2 20.80
80 D13. m2 24.40
90 Supply and fix prefabricated beam capping cage reinforcement no. m2 9.20
R10-300.
SCHEDULE OF RATES
CONCRETING WORK
SCHEDULE OF RATES
CONCRETING WORK
110 LABOUR ONLY for preparing, cleaning, assembling, erecting and m2 14.40
dismantling of metal formwork of any types to surfaces of concrete
columns, walls, suspended slabs, staircases, canopies, beams, etc.
111 PRECAST CONCRETE (Grade 20) with reinforcement in heel stones, m3 305.50
sills, lintols, slabs, etc. including moulds, hoisting and fixing in
position.
112 PRECAST CONCRETE (Grade 25) with reinforcement in heel stones, m3 308.30
sills, lintols, slabs, etc. including moulds, hoisting and fixing in
position.
113 PRECAST CONCRETE (Grade 30) with reinforcement in heel stones, m3 311.10
sills, lintols, slabs, etc. including moulds, hoisting and fixing in
position.
114 PRECAST CONCRETE (Grade 40) with reinforcement in heel stones, m3 318.40
sills, lintols, slabs, etc. including moulds, hoisting and fixing in
position.
SCHEDULE OF RATES
CONCRETING WORK
119 100mm high heelstone in cement mortar (1:2) to base of door frame no 1.40
(100 x 63mm or 100 x 50mm) including 1 no. 12mm diameter mild
steel rod.
120 Hacking through reinforced concrete floors or walls (any thickness) to m3 295.50
form opening including making good and remove debris from site.
123 Supply and lay a layer of approved epoxy concrete bonding agent to m2 25.20
hacked concrete surfaces before concreting.
124 Concrete (Grade 20) in small quantities not exceeding 0.15 metre cube m3 227.70
including all necessary formwork.
125 Concrete (Grade 25) in small quantities not exceeding 0.15 metre cube m3 231.90
including all necessary formwork.
126 Concrete (Grade 30) in small quantities not exceeding 0.15 metre cube m3 236.20
including all necessary formwork.
127 Concrete (Grade 40) in small quantities not exceeding 0.15 metre cube m3 247.10
including all necessary formwork.
SCHEDULE OF RATES
CONCRETING WORK
SCHEDULE OF RATES
CONCRETING WORK
155 Supply and install 25mm diameter brass tube sleeve for gondola no 68.90
suspension cable not exceeding 210mm long complete with removable
brass capping screw and welded with 2mm thick brass collar plate
including casting into concrete structure as specified.
Supply and drive bakau piles minimum 80mm diameter at the larger
end including cutting of piles (provision, assembly, and subsequent
dismantling and removal of piling equipment measured separately) :-
158 Exceeding 4.00m but not exceeding 6.00m long complete with mild no 10.90
steel pipe sleeves.
159 Exceeding 6.00m but not exceeding 8.00m long complete with mild no 13.80
steel pipe sleeves.
160 Providing and assembling of necessary piling equipment to drive any item 600.00
size of BAKAU PILES including all necessary tools and appliances,
subsequent dismantling and removal on completion of the work on
site.
CONCRETING WORK SOR 13
SCHEDULE OF RATES
CONCRETING WORK
164 Supply and fix 4.5mm thick x 450mm long bituminous painted MILD no 10.90
STEEL BOX JOINT to 125x125mm treated timber piles.
165 Supply and fix 4.5mm thick x 450mm long bituminous painted MILD no 12.10
STEEL BOX JOINT to 150x150mm treated timber piles.
166 Supply and fix 4.5mm thick x 450mm long bituminous painted MILD no 15.70
STEEL BOX JOINT to 175x175mm treated timber piles.
167 Providing and assembling of necessary piling equipment to drive any item 750.00
size of Treated Timber Piles including all necessary tools and
appliances, subsequent dismantling and removal on completion of the
work on site.
168 Labour, instruments and tools to carry out WORKING LOAD TEST ton 46.00
on driven treated timber piles.
SCHEDULE OF RATES
CONCRETING WORK
175 Providing and assembling of necessary piling equipment to drive any item 3,300.00
size of reinforced concrete piles including all necessary tools and
appliances, subsequent dismantling and removal on completion of the
work on site.
176 'Working Load Test' for reinforced concrete piles including provision ton 46.00
of kentledge and all labour, instruments and tools to carry out the work
as specified.
177 'Ultimate Load Test' for reinforced concrete piles including supply and ton 46.00
drive of pile and kentledge and all labour, instruments and tools to
carry out the work as specified.
178 Dynamic testing of piles complete with CAPWAPC Analysis and the item 1,495.00
submission of all readings and 4 sets of comprehensive reports as
directed by SO Representative including the provision of all labour,
instruments and tools to carry out the work as specified.
181 Forming of 25mm wide expansion joint in cavity with foam plastic m2 2.10
infill as specified.
182 Forming of surface channel 150mm wide x 50mm deep on concrete m 1.00
floor slab to fall.
CONCRETING WORK SOR 15
SCHEDULE OF RATES
CONCRETING WORK
184 Add to LAST ITEM for the increase in stages of 150mm deep. m 14.20
186 Add to LAST ITEM for the increase in stages of 150mm deep. m 14.70
187 Extra over 225mm wide reinforced concrete drain for PRECAST m 5.00
CONCRETE INVERT.
188 225mm wide (internal) Grade 40 precast concrete house drain not m 53.70
exceeding 400mm deep (average) to invert with 100mm thick sides
and bottom complete with reinforcement and topping up sides with in-
situ concrete including all necessary jointing, excavation, formwork
and lean concrete and laid to falls as specified.
189 Add to LAST ITEM for the increase in stages of 100mm deep. m 3.10
190 300mm diameter spun concrete pipes class 'S' to conduit drain not m 56.20
exceeding 1m deep (average) to invert level, laid on hardcore bed and
concrete haunching (1:3:6) to all pipe joints including all necessary
excavation and formwork.
191 Add to LAST ITEM for the increase in stages of 150mm deep. m 1.37
192 Supply and install 300 x 300 x 50mm thick precast concrete (Grade m 13.30
30) drain slab reinforced with D6 fabric reinforcement with 'HDB'
lettering cast on the slab.
193 Supply and lay 300 x 300 x 50mm thick polypropylene fibre m 13.70
reinforced vibro-compacted porous concrete slab with cement and 9 or
14mm thick aggregate (1:4) mix for concealed drain.
CONCRETING WORK SOR 16
SCHEDULE OF RATES
CONCRETING WORK
194 Supply, delivery and installation of 70mm thick prestressed precast m2 38.60
concrete planks including all necessary prestressing wires,
reinforcement, mould, formwork, labour and materials for jointing,
testing accessories and protection, etc as specified.
195 Supply, delivery and installation of 110mm thick prestressed precast m2 42.30
concrete planks including all necessary prestressing wires,
reinforcement, mould, formwork, labour and materials for jointing,
testing accessories and protection, etc as specified.
198 Supply, delivery and installation of precast concrete parapet walls of m3 93.20
102 - 12mm thickness complete with coping and projecting nib for
jointing including all necessary reinforcement, mould, formwork,
stacking, hoisting, setting, labour, materials for jointing, testing
accessories and protection etc, as specified.
199 Supply, delivery and installation of precast concrete staircase with m3 576.80
stainless steel nosings including all necessary reinforcement, mould,
formwork, stacking, hoisting, setting, labour, materials for jointing,
testing accessories and protection etc, as specified.
200 Supply, delivery and installation of precast concrete 100mm thick m2 85.10
wall/column/beam cladding including all necessary reinforcement,
mould, formwork, stacking, hoisting, setting, labour, materials for
jointing, testing accessories and protection etc, as specified.
201 Supply, delivery and installation of precast concrete 100mm thick m2 58.40
infill/party wall between units including all necessary reinforcement,
mould, formwork, stacking, hoisting, setting, labour, materials for
jointing, testing accessories and protection etc, as specified.
202 Supply, delivery and installation of precast concrete 100mm thick half m2 73.60
façade wall/plain wall complete with or without cills and other
projections including all necessary reinforcement, mould, formwork,
stacking, hoisting, setting, labour, materials for jointing, testing
accessories and protection etc, as specified.
CONCRETING WORK SOR 17
SCHEDULE OF RATES
CONCRETING WORK
203 Supply, delivery and installation of precast concrete 100mm thick m2 80.90
screen wall complete with coping and other projects at watertank
including all necessary reinforcement, mould, formwork, stacking,
hoisting, setting, labour, materials for jointing, testing accessories and
protection etc, as specified.
204 Supply, delivery and installation of precast concrete parapet with m 180.60
approximate height of 750mm complete with base slab of approximate
width of 840mm incorporating wheel stoppers to multi-storey capark
including all necessary reinforcement, mould, formwork, stacking,
hoisting, setting, labour, materials for jointing, testing accessories and
protection etc, as specified.
205 Supply, delivery and installation of precast concrete gable end walls m2 82.80
overall thickness 225mm (consisting of 2 layers of walls) with 25mm
cavity filled in with polystyrene insulation complete with beams and
other projection including all reinforcement, mould, formwork,
stacking, hoisting, setting, labour, materials for jointing, testing
accessories and protection etc, as specified (measured nett).
206 Supply, delivery and installation of precast concrete façade panels m2 77.10
comprising of 132mm thick walls with beams, cills and other
projections including all necessary reinforcement, mould, formwork,
stacking, hoisting, setting, labour, materials for jointing, testing
accessories and protection etc, as specified (measured nett).
207 Refuse chute (approximate size 1000 x 1000 x 2800mm height) no 416.30
comprising of 100mm thick walls with 1 no. opening of size 500 x
725m.
Extra over precast concrete component for supply and lay of 190 x 90
x 12mm thick heavy duty 'Cera Renga' homogeneous modular
extruded clinker tiles to concrete surface including 6mm thick cement
and sand (1:2) base screed as specified and in the following colours :-
SCHEDULE OF RATES
CONCRETING WORK
Extra over precast concrete component for supply and lay of 190 x 90
x 12mm thick heavy duty 'Cera Renga' homogeneous modular
extruded clinker tiles to concrete surface including 6mm thick cement
and sand (1:2) base screed as specified and in the following colours :-
(Cont’d)
213 Red (R), Pebble (B), Dessert (CY), Brown (BR), Ivory (CC), Light m2 44.30
Grey (OG), Light Yellow (CY), Pepper (CNH), Dark Brown (A),
Light Red (CO) or Greyish Brown (NY).
Extra over precast concrete component for supply and lay of 190 x 90
x 12mm thick heavy duty 'Mizuno' homogeneous modular extruded
clinker tiles to concrete surface including 6mm thick cement and sand
(1:2) base screed as specified and in the following colours :-
220 Red (PNC-35), Pebble (PNC-4), Apricot (PNC-3), Beige (PNC-2), m2 50.80
Creme (PNC-1), Light Grey (PNC-6) or Dark Grey (PNC-7).
Extra over precast concrete component for supply and lay of 190 x 90
x 12mm thick heavy duty unglazed 'Inax' homogeneous modular
extruded clinker tiles to concrete surface including 6mm thick cement
and sand (1:2) base screed as specified 3 colours :-
221 Red (FC 75-2), Pebble (FC 71-1), Apricot (FC 65-2), Fawn (FC 62-1), m2 71.40
Brown (FC 65-4) and Kaki (FC 71-3).
SCHEDULE OF RATES
CONCRETING WORK
Extra over precast concrete component for supply and lay of 190 x 90
x 12mm thick heavy duty unglazed 'Inax' homogeneous modular
extruded clinker tiles to concrete surface including 6mm thick cement
and sand (1:2) base screed as specified 3 colours :- (Cont’d)
227 Beige (FC 53-1), Crene (FC 63-1), Ivory (FC 63-3), Light Grey (FC m2 71.40
53-2), Dark Grey (FC 53-3) and Light Yellow (FC 73-1).
Extra over precast concrete component for supply and lay of 190 x 190
x 12mm thick heavy duty unglazed 'Kozilius' homogeneous modular
extruded clinker tiles to concrete surface including 6mm thick cement
and sand (1:2) base screed as specified and in the following colours :-
230 Dark Rose (NH-2029), Skyblue (Nh-2015) and Dawn (NH-2024). m2 73.60
231 Apricot (NH-1118), Desert (NH-1216), Red (NH-0110) and Overburnt m2 38.70
(NH-1330).
233 Cloud Grey (NH-2031), Stone Grey (NH-2033) and Crème (NH- m2 41.70
2002).
SCHEDULE OF RATES
CONCRETING WORK
238 Extra over precast concrete component for the supply and laying of m2 16.10
exposed aggregate finish to the external face comprising of Grade 30
concrete mix with 20 to 40mm single-sized grey colour aggregate as
specified.
239 Extra over precast concrete component for the supply and laying of m2 15.30
exposed aggregate finish to the external face comprising of Grade 30
concrete mix with 20 to 40mm single-sized pink colour aggregate as
specified.
240 Extra over precast concrete component for the supply and laying of m2 16.30
exposed aggregate finish to the external face comprising of Grade 40
concrete mix with 20 to 40mm single-sized grey colour aggregate as
specified.
241 Extra over precast concrete component for the supply and laying of m2 15.60
exposed aggregate finish to the external face comprising of Grade 40
concrete mix with 20 to 40mm single-sized pink colour aggregate as
specified.
Drain/Water Channel
Construct 230mm wide (internal) CONCRETE (Grade 25) SURFACE
DRAIN with 100mm thick sides, 100mm thick base reinforced with a
layer of BRC No. B6 wiremesh. All exposed sides, base and arises
rendered smooth in cement mortar (1:3) including all necessary
excavation, hardcore, sand blinding and formwork, laid to fall as
directed for the following average depth to invert:
245 Construct 230mm wide (internal) reinforced concrete (Grade 25) m 75.60
surface drain with 100mm thick sides and base reinforced with a layer
of BRC No. B6 wire mesh. All exposed sides, base and arises rendered
smooth in cement mortar (1:3) including all necessary excavation,
hardcore, sand blinding and formwork, laid to fall as directed for more
than 600mm depth to invert
246 Extra over items for precast concrete channel to 230mm wide m 2.20
reinforced concrete surface drain.
SCHEDULE OF RATES
CONCRETING WORK
DRAIN with 100mm thick sides and base reinforced with a layer of
BRC No. B6 wire mesh. All exposed sides, base and arises
rendered smooth in cement mortar (1:3) including all necessary
excavation, hardcore, sand blinding and formwork, laid to fall as
directed for the following average depth to invert :
251 Extra over items for precast concrete channel to305mm wide m 3.50
reinforced concrete surface drain.
252 Extra over for forming 50mm x 25mm rebate on both sides of channel m 2.60
for precast drain cover slab
(Measurement based on length of drain)
Hack out existing concrete drain invert (Average Depth not exceeding
600mm) and regrade to fall towards outlet with cement mortar screed
and finished smooth
258 Break up damaged/sunken 300mm closed conduit drain spun pipe m 72.30
include hacking through floor, excavation, planking, making good etc.
CONCRETING WORK SOR 22
SCHEDULE OF RATES
CONCRETING WORK
259 Reconstruct existing scupper drain outside bin chute chamber with m 22.80
new half round salt glazed stoneware pipes, side and base embedded in
G20 concrete including adjusting existing gulley to match drain level
bedded and jointed with cement mortar
260 Construct scupper drain not exceeding 150mm wide and 75mm deep m 5.50
on existing floor including trowelling surface smooth
261 Regrade existing scupper drain with waterproofing cement mortar laid m 4.20
to fall not exceeding 150mm wide and 75mm deep including
trowelling surface smooth
262 Regrade existing scupper drain with waterproofing cement mortar laid m 5.50
to fall exceeding 150mm but not exceeding 300mm wide, 75mm deep
including trowelling surface smooth
263 Construction of concrete footpath 1.5m to 2.0m wide consists of not m2 19.90
exceeding 300mm deep excavation of site on ordinary grounds,
backfilling, forming of surfaces and edges, making good, removal of
surplus excavated material off site to approved dumping good, 150mm
thick hardcore including 25mm thick sand binding, compaction of
ground, A6 BRC welded steel fabric reinforcement weld/apped and
tied at joings, 100mm thick grade 25 reinforced concrete including pvc
strip expansion joint where necessary, formwork and trowelling