Professional Documents
Culture Documents
Assignment Pp (1) NEW (3)
Assignment Pp (1) NEW (3)
Assignment Pp (1) NEW (3)
ASSIGNMENT 1
PREPARED BY:
NAME MATRIC NO
NURAZIAH JASMIN BINTI ZULKEPLY 2019601628
RAJA NUR ANISAH BT RAJA ARIFIN 2019608088
EZYAN KAUSAR BT EZANI 2019818898
SITI NUR AIN BT SUKERI 2019660222
AIRA NABAHAH BT NAHARUDDIN 2019601902
HAFIY AMSYAR BIN RUSLI 2019884208
TABLE OF CONTENT
6.0 References
1.0 NAME OF THE CASE LAW
This a turnkey contract awarded to the plaintiffs on the date of 15 June 1996 where
the employer, Gaya Kombinasi (M) Sdn Bhd has issued the letter of award. The
turkey contract was for the construction of an office building which consists of 7 floors
of office building and 3 floors of parking located at Lot 16717 in Mukim Petaling,
Daerah Petaling, Selangor Darul Ehsan. This project also known as Mines Waterfront
Business Park. The total project cost of construction was at the consideration of
RM70,500,000.00 and the actual agreed completion date between the employer and
This case was rise once again to court of appeal by the appellant/defendant
(Uniphone Telecommunication Bhd) against the decision of the High Court to argue
Corporation (M) Sdn Bhd) regarding the issues of payment and the Certificate of
Practical Completion.
Explanation of the dispute
Primarily, there should be a clear vision that Gaya entered into a sale and purchase
agreement (SPA) with the defendant on 4 December 1996 six months while the
project was still ongoing. Therefore, there have been an agreement where Gaya will
sell the land and the defendant shall buy the land together with the construction of
the office building with the sum of RM161,088,000.00. Thus, this shows that the
plaintiff was not involve in the SPA agreement while the defendant was not involved
A deed of assignment (DOA) dated on 12 February 1999 about more than two years
later, where was entered between the three parties, which is Gaya,
payment, which the total of RM19,386,709.00 to the respondents that is under the
turnkey contract. Therefore, the sum of RM15 million is the sum payable by the
appellant to Gaya that is under the SPA and as part of owning by Gaya to the
respondents that this RM15 million sum also shall be paid by the appellant to the
respondents.
The amount of RM15 million shall be paid in the manner of RM7 million to be paid
upon the execution of DOA by the appellant and the balance of RM8 million is to be
paid 18 months after the issuance of CPC or earlier which will be paid by the
appellant also.
On 21 April 1999, the new CPC date have been issues by the architect to the
respondents and thus the claim for extension of time or liquidated damages cannot
be made. Moreover, there shall be no changes and threaten and cause of stoppage
of works be made by the appellant or the employer to avoid any extension of new
CPC date. The respondents were also obliged to work diligently to rectify any defects
that appear within the 18 months from the new CPC date under the turnkey contract.
Thus, on the issuance of the new CPC on 21 April 1999, the respondents shall entitle
to be paid the remaining balance of the sum by the appellant within that 18 months.
However, the appellant/defendant refused to pay the sum of that said RM8 million to
been so defects that is not satisfied for the appellant and the respondents seems had
failed to complete their works. This counterclaim filed by the appellant on 5 June
2001.
In their defence, the appellant also claimed that the CPC issued to the respondents
was defective and inappropriately issued. The CPC was then found unsigned by the
employer which it was a triable issue as to the validity of the CPC which means that
the CPC was invalid. It is known that CPC is required to have the employer’s
signature for its validity. However, there was no explanation from the respondents
Though, the respondents argue that the balance sum of RM8 million under the DOA
is free of obligation towards the appellant that is under the SPA. It is said by the
respondents that any obligations to make good any defects during the defect liability
period are only toward the employer which is Gaya Kombinasi as this both parties
are under the turnkey contract and not with the appellant.
explanation and declaration done by the respondents that the CPC was issued in the
manner as prescribed by PAM and why was it unsigned by the employer where it will
SDN BHD & ANOR, the high court had dismissed the appeal with cost. The appellant
need to pay all cost because the appeal had been rejected. However, the appellant
had succeeded in raising triable issues. The appeal was made by defendant (UTB)
after the summary of judgement to the plaintiff had been decided by high court.
Before the appeal has been made, the majority are stated that DOA was clear and
unambiguous statement. The terms of the deed of assignments (DOA) referred to the
sales and purchase agreement (SPA) and turnkey contract. It was clearly stated that
defendant (UTB) needs to pay the plaintiff (Brigdecon Engineering) on behalf of Gaya
for the balance sum due from Gaya to plaintiff under the turnkey contract. Remaining
sum of money is RM8,000,000. This sum is the total amount of sum that defendant
need to paid to Gaya under SPA for the office building which Gaya will need to pay it
to the plaintiff. By being a party to the DOA, the defendant agreed to pay that sum of
money to the plaintiffs on behalf of Gaya. Therefore, defendant was obligated to pay
On the appellant, some triable issues had been raised. The issue is on defects and
substantial defects in the construction of the project and whether the respondent is
expected to complete the works and repair the defects before the respondent can
The dispute is either there were defects and incomplete works or not. The statement
given by the respondent and appellant are opposed each other. For respondent, they
agreed that the whole work have been completed with the minor defects which are
not serious in nature. In the other hand, the appellant opposes that there were
incomplete works and there are serious and substantial defects occurred in the
project which the respondents should not claim the payment from them.
The appellant has succeeded to raise the issue of incomplete and substantial
defective works in the statement of defence and counterclaim. In their affidavits, the
application that the appellant refused to pay the claim and the fact that they obtained
the quotation for the completion works with the estimated sum of RM16,349,005.77.
The appellant has even filed a counterclaim for RM17m. In their counterclaim the
appellant claims that they have incurred RM856,481.70 to rectify some of the defects
which documents detailing on the defects have been produced as of their first
affidavit. Other than that, the appellant is also claiming a further sum of
RM16,349,005.77 which was claiming to be the sum that they need to incur in order
to complete the works and repair the defects. In their affidavits, the appellant also
has produced details of the incomplete works and defects, the contractors that would
be involved to complete the works and or to remedial the defects and also the
quotations.
The next issue which are more sided to the appellant is the issuance of Certificate of
Making Good Defects (CMGD). CMGD is only being issued by the project architect,
KPK architect to the respondent on 6 November 2001 which is more than two and a
half year after the issuance of CPC on 21 April 1999. If it is only the minor defects, it
will not be taking such a long time to be completed. Therefore, the duration of making
good defects which are quite long is being more sided to appellant’s claim which the
defects were extensive and substantial in nature. The defects are not the minor one
(CPC). The format of CPC required to the approval of Gaya Kombinasi who is the
employer but the CPC was unsigned by the employer. The respondent and project
architect did not have any explanation on the reason of the obvious omission. Other
than that, the CPC has the appendix which contains a long list of works that need to
be completed by the respondent. But the appendix was being omitted by the
respondent in their first affidavit in which the respondent only displaying the CPC
without any appendix. This shows that the CPC that had been display were not
complete. The appellant than displayed the appendix when they filed their affidavit as
responded to the respondent’s affidavit. When this failure on the part of the
respondents to show the appendix to the CPC was pointed out by the appellant in
their affidavit, in their reply, the respondents did not bother to provide any explanation
whatsoever. From the response, the interpretation then can be made that the
The deed of assignment (DOA) instructs in clause 8.1 that the new Certificate of
being challenge because the CPC is not signed by the employer, contains the
appendix with the long list works to be completed and no declaration in the CPC that
In the dispute between the appellant and the respondents, the CPC is a vital
document for the appellant's liability to pay depends upon the issuance of a valid
CPC. Now, the validity of the CPC is being seriously challenged by the appellant.
Hence, the legal burden is on the respondents to verify that the CPC is validly issued.
It is compulsory upon the respondents to prove that that the CPC was issued as
being prescribed by Pertubuhan Akitek Malaysia (PAM). Based on the CPC and the
affidavits of the respondents, there is no statement stated that the CPC is issued in
of law that where an architect issues a CPC, it must be presumed that the CPC was
There were also serious disputes in relation to the list of defects as set out in the
appendix to the CPC. According to the appellant, the defects were extensive and
substantial and that some of the works are even incomplete. The appellant opposes
that the architect should not have issued the CPC. However, the appellant cannot be
able to prove that the defects are extensive and there were incomplete works.
Hence, the defence and counterclaim of the appellant was not an accused. This case
was not the straightforward case as granted by the summary of judgement. In the
court of appeal, the appellant need to satisfy the court that there were real triable
issues and they actually have succeeded to prove it although the appellant lost the
case.
5.0 CONCLUSION & LESSON LEARNT
In conclusion, the dispute in the construction industry might occur between the
parties. The parties can decide to bring the dispute into Alternative Dispute
Telecommunications Bhd v Bridgecon Engineering Sdn Bhd & Anor, the appellant
bring the dispute to Court of Appeal (Putrajaya) after the first proceeding is Bridgecon
winning. The High Court judge also give winning to the defendant because of the
terms in Deed of Assignment (DOA) is clear and they entitled to the claim.
This case shows the importance of the CPC validity because it can bring the cases to
another dispute and all the parties need to understand the contract carefully to avoid
any problem arise. There are several lessons learn in this study that is portray:
From this case, the plaintiff succeeds to get their claim, which is RM 8 million after
CPC. This is because the plaintiff had achieved the CPC before exceed the revised
date. After all, this project has an extension of time. This show that the plaintiff
manages to follow the revised contract period. The defendant needs to pay the
plaintiff the amount of money that had been agreed in DOA. The court had come to
the plaintiff side because the plaintiff has their right on this case.
fault because by right, plaintiff deserves to claim the money because they achieve
the CPC. Even the plaintiff claims the works have defects, however, the issuance of
CPC already made by the Architect. The date of CPC is important because if it
exceeds, the defendant will not get the claim and will be charge for LAD. Low Hop
Bing and Syed Ahmad Helmy JJCA also agree that the plaintiff needs to pay
From this case, the defendant success to arise the dispute by bringing the validity of
Practical Completion is not found but it can be found at SPA agreement. The CPC
CPC was not signed by the Employer and for this case, refer to Gaya Kombinasi.
is important to fill all the requirement in the document. This is to ensure the validity of
the contract. The appellant even they are not winning the appeal, they success to
bring this issue because it is clear that all documents must be completed.
iii. All parties need to understand the contract and their rights
In this contract, the turnkey contract was made between Gaya Kombinasi and the
involved only have to follow the obligation towards the party that they enter the
contract.
Even all the parties entered contract under Deed of assignment, the contract only
stated that the defendant needs to pay the plaintiff on behalf of Gaya Kombinasi. The
defendant argues that they are defective works and the CPC is not valid. However,
the work to rectify the defect is between the Plaintiff and Gaya Kombinasi under a
turnkey contract. Plaintiff and defendant do not enter the contract for the plaintiff to
The defendant still needs to pay the plaintiff the remaining amount agreed after
issuance of CPC as stated in SPA and the judge stated that the appellant could ask
remedy for the defects and incomplete works by the defendant. Through this case, it
is important for all the parties involved to understand their contract and their
obligation towards the parties and the contract. If a dispute occur later in the contract,
the parties can argue regarding their obligation toward the contract. Uniphone
Telecommunication must not clear regarding the contract decided to bring this case
to Court of Appeal. However, they still have a right to appeal the case even if they