Method of Statement for Installation of

Handrail
1. Objective:

The objective of this method statement is to provide a systematic procedure and guidelines for the
installation of handrails in compliance with Saudi Aramco standards. The method ensures a safe,
efficient, and quality installation process.

2. Scope:

This method statement covers the installation of handrails at designated locations as per the approved
drawings and specifications provided by Saudi Aramco.

3. REFERENCES

a) International Standards

➢ PIP STS0S130 Erection of structural & miscellaneous steel structure


➢ PIP STS05120 Fabrication of structural & miscellaneous steel specification
➢ AISC Code of standard practice for steel buildings & bridges Steel construction manual
➢ ASTM A36 Standard specification for carbon structural steel
➢ ASTM A307 Carbon steel bolts & studs, 60000 PSI tensile strength
➢ ASTM AS3 Standard Specification for pipe, steel, black & hot dipped, zinc coated, welded &
seamless
➢ ASTM AS00 Cold-formed welded & seamless carbon steel structure tubing in rounds and shapes
➢ ASTM A385 Standard practice for providing high-quality zinc coating (hot-dip)
➢ ANSI A1264.1 Safety requirements for workplace walking/working surfaces & their access;
workplace floor, wall & roof openings; stairs & guardrail systems

b) SAUDI ARAMCO ENGINEERING STANDARDS (SAES)

➢ SAES M-100 Saudi Aramco Building Code


➢ SAES-H-100 Coating material & application requirement for industrial facilities
➢ SAES-H-101 Approved protective coating system
➢ SAES-Q-001 Criteria for design & construction of concrete structure

c)SAUDI ARAMCO MATERIAL SPECIFICATION SYSTEM (SAMSS)

➢ 12-SAMSS-007 Fabrication of structural & miscellaneous steel


➢ 12-SAMSS-008 Erection of structural & miscellaneous steel
➢ 12-SAMSS-014 Pre-Engineered Metal Buildings.
d) SATIP

➢ SATIP-M-100-03 Structural steel for buildings

e) IFC & Shop drawings

➢ Shop drawings for Handrail

4. Materials and Equipment:

➢ Steel handrails as per Saudi Aramco standards


➢ Mounting brackets and fasteners
➢ Concrete anchors and bolts
➢ Spirit level, measuring tape, and marking tools
➢ Drilling machine and cutting tools
➢ Personal protective equipment (PPE) including helmets, gloves, safety harness, and safety
glasses

5. Installation Procedure:

a. Preparation:

➢ Ensure all necessary safety measures are in place, including barricades and warning signs.
➢ Verify the dimensions and locations of handrails as per the approved drawings.
➢ Inspect materials for any defects before installation.

b. Marking and Positioning:

➢ Use spirit levels and measuring tape to mark the exact positions for handrail installation on the
walls or columns.
➢ Mark the positions for drilling holes ensuring proper alignment and spacing as per the standards.

c. Drilling Holes:

➢ Use a drilling machine with appropriate drill bits to create holes in the concrete walls or columns
for installing anchors.
➢ Clean the holes from debris to ensure a proper fit for anchors.

d. Installation of Mounting Brackets:

➢ Fix the mounting brackets securely into the drilled holes using concrete anchors and bolts.
➢ Use a spirit level to ensure that the mounting brackets are installed horizontally and vertically
level.
e. Installation of Handrails:

➢ Attach the handrails to the mounting brackets securely using appropriate fasteners.
➢ Double-check the alignment and level of the handrails during installation.
➢ Ensure that the handrails are tightly fixed and do not wobble.

f. Welding:

➢ Conduct welding at marked points according to Saudi Aramco welding procedures and
standards.
➢ Ensure proper welding techniques and inspection to achieve high-quality welds.

g. Finishing:

➢ Clean the installed handrails, removing any marks or stains.


➢ Inspect the entire installation to ensure it meets Saudi Aramco standards and project
specifications.
➢ Conduct a safety inspection to ensure there are no sharp edges or protruding parts that could
pose a risk.

h. Documentation:

➢ Prepare an installation report detailing the procedures followed, deviations (if any), and
photographs of the installed handrails.
➢ Ensure that the installed handrails are inspected and approved by the designated authority
before considering the installation as complete.

5. Safety Precautions:

➢ All personnel involved in the installation must wear appropriate PPE at all times.
➢ Ensure proper training and supervision for the installation team.
➢ Regularly inspect and maintain all equipment to ensure safe operation.

6. Quality Control:

➢ Conduct regular inspections during the installation process to maintain the quality and
adherence to standards.
➢ Any deviations from the approved drawings or standards must be rectified immediately.