BILL ABSTRACT

(S.H:- RCC Bridge 15.00 M Span)

Sl No Sub-head and items of work Quantity Unit Rate Amount (in Rs.) Remarks

1 2 3 4 5 6 7
Sub Head- I - Sub Structure (Abutment & Wing
Wall)
1 Excavation for Structures (Earth work in excavation of
foundation of structures as per drawing and technical
specification, including setting out, construction of
shoring and bracing, removal of stumps and other
deleterious matter, dressing of sides and bottom and
backfilling with approved material.)
I Ordinary soil
Foundation
A Manual Means
(ii) 3 m to 6 m depth 627.19 Cum. 283.32 177695.00
(ii) 3 m to 6 m depth 275.90 Cum. 336.44 92824.00

270519.00
2 PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 62.72 Cum. 5375.23 337134.00 337134.00
nominal mix in foundation with crushed stone 6 07 653.00
aggregate 40 mm nominal size mechanically mixed,
placed in foundation and compacted by vibration
including curing for 14 days.)
3 Plain/Reinforced cement concrete in sub-structure
complete as per drawing and technical specifications Abutment &
F RCC Grade M25 Wing Wall
(q) Height 5m to 10 M
Case I Using concrete Mixer 619.72 Cum. 6537.89 4051661.00 4051661.00

4 Drainage spouts complete 16.00 Nos 2392.46 38279.00 38279.00

5 Provididng weep holes in brick masonry/plain/ 180.00 each 287.11 51680.00 51680.00
reinforcement concrete abutment, wing wall/ return
wall with 100 mm dia AC Pipe extending through the
full width of the structure with slope of 1V:20H
towards drwaing face, complete as per drawing and 46 47 527.00
technical specifications.
6 Back filling behind abutment, wing wall and return
wall complete as per drawing and Technical
A specification
Granular material 131.20 Cum. 829.84 108875.00 108875.00
Plain/Reinforced cement concrete in sub-structure
7 complete as per drawing and technical specifications. 9.39 Cum. 7437.55 69839.00 69839.00
RCC Grade M-20
8 Providing PCC M-20 architectural Coping 37.89 Rmt 8635.33 327193.00 327193.00

52 55 180.00 (A)
Sub Head- II - Superstructure
1 Providing and laying RCC in Wall, return wall, etc. RCC
84.96 Cum 8635.33 733657.64 733657.64
Grade-M25
2 Supplying ,fitting and placing HYSD bar reinforcement 11.96 MT 75933.10 908160.00 908160.00
in super-structure complete as per drawing and
technical specifications
3 Elastomeric Slab Steel Expansion Joint (Providing 12.00 Mtr 13722.93 164675.00 164675.00
and laying of an elastomeric slab steel expansion joint,
catering to right or skew (less than 20 deg.,
moderately curved with maximum horizontal
movement upto 50 mm, complete as per approved 21 92 963.24
drawings and standard specifications to be installed
by the manufacturer/supplier or their authorised
representative ensuring compliance to the
manufacturer's instructions for installation and clause
2606 of MoRTH specifications for road & bridge
works.)
4 Providing and laying wire crated boulders structures 170.10 Cum 2272.02 386470.60 386470.60
size 22.5cm
Carriage charge of material Cement (270.59 MT)
883198.50 883198.50
Carriage charge of material Steel (12.56 MT) 41251.19 41251.19
Carriage charge of material Sand (352.444Cum) 152749.29 152749.29
14 55 967.37
Carriage charge of material Boulder & Aggregate
(862.32 Cum) 378768.39 378768.39

36 48 930.61 'B'

GROSS Amount (A+B ): 89 04 110.61 'C'


DEDUCTIONS :
GST : 18% 1602739.91
Income Tax: 2% 178082.21
Labour Cess: 1% 89041.11
Mineral & Mining (Royaly): 2% 178082.21
Security Deposit : 7.5% 667808.30
Total Deductions : 27 15 753.74 'D'

NET Amount (C-D ): 61 88 356.87 'E'

CE : 1% 61883.57
EE: 2% 123767.14
AE: 2% 123767.14
JE: 2% 123767.14
Firm Charge : 2% 178082.21
Deductions to Deptt: 6 11 267.19 'F'

Total (E-F ): 55 77 089.68 'G'