I PEKERJAAN PERSIAPAN
6.8 A. Pembersihan Lahan (m ²)
SNI 03-2835-2002 Tenaga
Pekerja Oh 0.100 36,000.00 3,600.00
Mandor Oh 0.050 40,000.00 2,000.00
Sub Total 5,600.00
6.1 B. Pemasangan Pagar Sementara dari Kayu tinggi 2 m (m ¹)
SNI 03-2835-2002 Bahan
Dolken Kayu Ø 8-10/400 cm Btg 1.250 25,000.00 31,250.00
Semen Portland Kg 2.500 1,050.00 2,625.00
Pasir Beton M³ 0.005 125,000.00 625.00
Koral Beton M³ 0.009 135,000.00 1,215.00
Kayu 5/7 M³ 0.072 1,700,000.00 122,400.00
Paku Biasa 2"-5" Kg 0.060 10,000.00 600.00
Residu Lt 0.400 11,000.00 4,400.00
Tenaga
Tukang Kayu Oh 0.200 47,500.00 9,500.00
Pekerja Oh 0.400 36,000.00 14,400.00
Kepala Tukang Oh 0.020 45,000.00 900.00
Mandor Oh 0.020 40,000.00 800.00
Sub Total 188,715.00
6.4 C. Memasang Bouwplank (m ¹)
SNI 03-2835-2002 Bahan
Kayu 5/7 M³ 0.012 1,700,000.00 20,400.00
Paku Biasa 2"-5" Kg 0.020 10,000.00 200.00
Kayu Papan Bengkirai 3/20 M³ 0.007 3,541,666.00 24,791.66
Tenaga
Tukang Kayu Oh 0.100 47,500.00 4,750.00
Pekerja Oh 0.100 36,000.00 3,600.00
Kepala Tukang Oh 0.010 45,000.00 450.00
Mandor Oh 0.005 40,000.00 200.00
Sub Total 54,391.66
ALS D. Memasang Papan Nama Proyek 80x120 cm (Bh)
Bahan
Kayu Meranti Btg 0.035 1,687,000.00 59,045.00
Paku Biasa 2"-5" Kg 0.600 10,000.00 6,000.00
Seng Lembaran 90 cm M¹ 1.400 27,000.00 37,800.00
Cat kayu Kg 1.500 38,000.00 57,000.00
Semen Portland Kg 16.800 1,050.00 17,640.00
Pasir Beton M³ 0.027 125,000.00 3,375.00
Koral Beton M³ 0.041 135,000.00 5,535.00
Tenaga
Tukang Kayu Oh 1.000 47,500.00 47,500.00
Tukang Batu Oh 0.018 42,500.00 765.00
Tukang Cat Oh 1.000 42,500.00 42,500.00
Pekerja Oh 2.100 36,000.00 75,600.00
Mandor Oh 1.005 40,000.00 40,200.00
Sub Total 392,960.00
6.5 E. Membuat direksi keet & Gudang Sementara (m ²)
SNI 03-2835-2002 Bahan
Dolken Kayu Ø 8-10/400 cm Btg 1.250 25,000.00 31,250.00
Kayu 5/7 M³ 0.180 1,700,000.00 306,000.00
Paku Biasa 2"-5" Kg 0.850 10,000.00 8,500.00
Besi Strip Kg 1.100 11,000.00 12,100.00
Semen Portland Kg 35.000 1,050.00 36,750.00
Pasir Pasang M³ 0.150 125,000.00 18,750.00
Pasir Beton M³ 0.100 125,000.00 12,500.00
Koral Beton M³ 0.150 135,000.00 20,250.00
Bata Merah Bh 30.000 500.00 15,000.00
Seng Plat Lbr 0.250 27,000.00 6,750.00
Jendela Nako Bh 2.0000 12,500.00 25,000.00
Kaca Polos 3 mm M² 0.080 50,000.00 4,000.00
Kunci Tanam Bh 0.150 25,000.00 3,750.00
Plywood 4 mm Lbr 0.060 50,000.00 3,000.00
Tenaga
Tukang Kayu Oh 2.000 47,500.00 95,000.00
Tukang Batu Oh 1.000 42,500.00 42,500.00
Pekerja Oh 2.000 36,000.00 72,000.00
Kepala Tukang Oh 0.800 45,000.00 36,000.00
Mandor Oh 0.050 40,000.00 2,000.00
Sub Total 751,100.00
II PEKERJAAN TANAH
6.1 A. Galian Tanah Biasa sedalam 1 m (m ³)
SNI 03-2835-2002 Tenaga
Pekerja Oh 0.400 36,000.00 14,400.00
Mandor Oh 0.040 40,000.00 1,600.00
Sub Total 16,000.00
6.9 B. Urugan Kembali (m ³)
SNI 03-2835-2002 Tenaga
Pekerja Oh 0.192 36,000.00 6,912.00
Mandor Oh 0.019 40,000.00 760.00
Sub Total 7,672.00
6.11 C. Urugan Pasir Bawah Pondasi (m ³)
SNI 03-2835-2002 Bahan
Pasir Urug M³ 1.200 100,000.00 120,000.00
Tenaga
Pekerja Oh 0.300 36,000.00 10,800.00
Mandor Oh 0.010 40,000.00 400.00
Sub Total 131,200.00
IV PEKERJAAN DINDING
6.11 A. Pasangan Tembok ½ Bata 1Pc:4Ps (Trasraam) (m ²)
SNI 03-2835-2002 Bahan
Bata Merah 5 X 11 X 22 cm Bh 70.000 500.00 35,000.00
Semen Portland Kg 11.500 1,050.00 12,075.00
Pasir Pasang M³ 0.043 125,000.00 5,375.00
Tenaga
Pekerja Oh 0.320 36,000.00 11,520.00
Tukang Batu Oh 0.100 42,500.00 4,250.00
Kepala Tukang Oh 0.010 45,000.00 450.00
Mandor Oh 0.015 40,000.00 600.00
Sub Total 69,270.00
6.15 B. Pasangan Tembok ½ Bata 1Pc:3Kp:10Ps (m ²)
SNI 03-2835-2002 Bahan
Bata Merah 5 X 11 X 22 cm Bh 70.000 500.00 35,000.00
Semen Portland Kg 4.500 1,050.00 4,725.00
Pasir Pasang M³ 0.050 125,000.00 6,250.00
Kapur Padam M³ 0.015 45,000.00 675.00
Tenaga
Pekerja Oh 0.320 36,000.00 11,520.00
Tukang Batu Oh 0.100 42,500.00 4,250.00
Kepala Tukang Oh 0.010 45,000.00 450.00
Mandor Oh 0.015 40,000.00 600.00
Sub Total 63,470.00
VI PEKERJAAN KAYU
6.1 A. Pasang Kusen Pintu dan Jendela Kayu Jati (m ³)
SNI 03-2835-2002 Bahan
Kayu jati, balok M³ 1.100 15,000,000.00 16,500,000.00
Tenaga
Pekerja Oh 6.000 36,000.00 216,000.00
Tukang Kayu Oh 20.000 47,500.00 950,000.00
Kepala Tukang Oh 2.000 45,000.00 90,000.00
Mandor Oh 0.300 40,000.00 12,000.00
Sub Total 17,768,000.00
6.7 B. Pasang Pintu Panel Kayu Jati (m ²)
SNI 03-2835-2002 Bahan
Kayu Jati, papan M³ 0.040 18,000,000.00 720,000.00
Tenaga
Pekerja Oh 1.000 36,000.00 36,000.00
Tukang Kayu Oh 2.500 47,500.00 118,750.00
Kepala Tukang Oh 0.250 45,000.00 11,250.00
Mandor Oh 0.050 40,000.00 2,000.00
Sub Total 888,000.00
ALS C. Pasang Nook, Gording, Murplat, Nook Kayu Bengkirai (m ³)
Bahan
Kayu Bengkirai, balok M³ 1.100 8,500,000.00 9,350,000.00
Tenaga
Pekerja Oh 2.000 36,000.00 72,000.00
Tukang Kayu Oh 8.000 47,500.00 380,000.00
Kepala Tukang Oh 1.200 45,000.00 54,000.00
Mandor Oh 0.200 40,000.00 8,000.00
Sub Total 9,864,000.00
6.35 D. Pasang Kaso+Reng Genteng Beton Kayu Borneo (m ²)
SNI 03-2835-2002 Bahan
Kayu Borneo, balok M³ 0.014 8,500,000.00 119,000.00
Paku Biasa 2"-5" Kg 0.150 10,000.00 1,500.00
Tenaga
Pekerja Oh 0.100 36,000.00 3,600.00
Tukang Kayu Oh 0.100 47,500.00 4,750.00
Kepala Tukang Oh 0.010 45,000.00 450.00
Mandor Oh 0.005 40,000.00 200.00
Sub Total 129,500.00
6.53 E. Pasang Listplank, Reuter 2X (2X20) cm, kayu borneo (m ³)
SNI 03-2835-2002 Bahan
Kayu Borneo,Papan M³ 0.009 10,000,000.00 88,000.00
Paku Biasa 2"-5" Kg 0.060 10,000.00 600.00
Tenaga
Pekerja Oh 0.100 36,000.00 3,600.00
Tukang Kayu Oh 0.100 47,500.00 4,750.00
Kepala Tukang Oh 0.010 45,000.00 450.00
Mandor Oh 0.050 40,000.00 2,000.00
Sub Total 99,400.00
6.40 F. Pasang Rangka Langit-langit 1X1 m Kayu Borneo (m ²)
SNI 03-2835-2002 Bahan
Kayu borneo, balok M³ 0.012 8,500,000.00 102,000.00
Paku biasa 2"-5" Kg 0.100 10,000.00 1,000.00
Tenaga
Pekerja Oh 0.150 36,000.00 5,400.00
Tukang Kayu Oh 0.250 47,500.00 11,875.00
Kepala Tukang Oh 0.025 45,000.00 1,125.00
Mandor Oh 0.075 40,000.00 3,000.00
Sub Total 124,400.00
IX PEKERJAAN PLAFON
6.19 A. Pasang List Langit-langit Kayu Profil (m ¹)
SNI 03-2835-2002 Bahan
Kayu Profil M¹ 1.100 3,333.33 3,666.67
Paku plafon Kg 0.010 10,000.00
Tenaga
Pekerja Oh 0.050 36,000.00 1,800.00
Tukang Kayu Oh 0.050 47,500.00 2,375.00
Kepala Tukang Oh 0.005 45,000.00 225.00
Mandor Oh 0.003 40,000.00 120.00
Sub Total 8,186.67
6.1 B. Langit-langit Asbes (m ²)
SNI 03-2835-2002 Bahan
Pelat Asbes tebal 6mm M² 1.100 32,000.00 35,200.00
Paku plafon Kg 0.010 10,000.00
Tenaga
Pekerja Oh 0.030 36,000.00 1,080.00
Tukang Kayu Oh 0.070 47,500.00 3,325.00
Kepala Tukang Oh 0.007 45,000.00 315.00
Mandor Oh 0.002 40,000.00 60.00
Sub Total 39,980.00